Of mice and IT elephants – guest blog

By John Pearce

I heard your interview on BBC’s World at One today Tony. You were saying there may be potential for fleet-of-foot small IT firms to access government contracts. It was music to my ears.

You referred to the NHS and Universal Credit IT disasters and the way contracting has been dominated by a few big beasts and multi-nationals.  You killed the myth that “big is beautiful”  and praised “new rules”  to break up projects into smaller units.

Small can be perfectly formed and powerful. Businesses like ours are quick-reflex mice stuck behind the elephants blocking the doors. Why don’t they just sit out of the way, in the room, like other elephants?

We are an SME in IT.  We have great pedigree, an innovative product, a presence in education and are ready to break into the business world and government work more generally. But without the bulk and buying power to advertise, lobby and bid for the current huge projects we have not been able to do much, if anything. We are encountering elephant in the door syndrome.

So we continue doing what we do, scurrying like mad, working unreasonable but happily given hours. It is not in the country’s interest for us to be tired, blocked and trapped. We fear being swallowed up, of losing our identity. I suppose it might be quicker than being slowly squashed under an elephant’s backside.

iAbacus

Dan O’Brien, my business partner, is young, creative, dynamic and rushed off his feet.  I am three of those and old.  He has run a small successful software company for 15 years. I had a successful senior career in education and in business as consultant, evaluator, writer and publisher.  I created a deceptively simple, improvement model for individual, team and organisation. So, Dan and I created an on-line version.

We launched “The iAbacus” in 2012 and were finalists in the BETT2014Awards [hosted by Jo Brand] on 22 January 2014.  There were lots of mice competing with us and the usual elephants. But before we announce the winner let’s have a look at the iAbacus focusing on school governance. 

We dream of developing this and moving into business generally. We see a huge potential for this “empowering personnel” approach applied to NHS and civil service personnel. Up to now the elephants have blocked the way, or grinned through the windows while they ate ice buns. Can elephants grin?

We didn’t win the Bett2014 Big Cheese but it was a great show – it makes people like us feel good.  Yes, coming back to the office was disappointing but we are nibbling away, on-line, working in education but, even in this field I know so well, customers can be sniffy too – “small is ugly and simple is simplistic; let’s go for the big suppliers”. 

New rules

Will the Cabinet Office’s new rules work?

 Not unless there is support for small outfits like ours who, intent on the day to day business, will struggle writing the bids and attending the selections. We’ll keep running and swerving around elephant bottoms but we need muscle power and finance for the advertising and lobbying. We need to elbow past the elephants, get an audience with buyers.  Is there anyone out there?  Echo…echo….echo…

Or, are there friendly elephants out there who could help us, encourage and include us?  Could the regulations persuade them?  How about a clause like the one when planning new houses?  Every housing project has to include a percentage of affordable homes. How about every IT contract having to include a percentage of SMEs?  

I want to one of them. I want to be a Trojan Mouse!

John Pearce is a freelance consultant, working across education, business and community. After a successful career in teaching and headship, he became Deputy Chief Inspector for Nottinghamshire County Council. He was a BETT2014 finalist for The iAbacus which he created with Dan O’Brien.

john@iabacus.co.uk   dan@iabacus.co.uk

BBC’s World at One focus on government IT.

Ex BP executive to run Major Projects Authority

By Tony Collins

John Manzoni is to join the civil service as Chief Executive of the Cabinet Office’s Major Projects Authority.

The former BP executive brings 30 years’ commercial experience to the job. He was  recently President and CEO of Canadian oil and gas company Talisman Energy Inc. He spent 24 years at BP, holding senior strategic and operational leadership roles at global, regional and local level. 

He was a member of the BP plc Main Board from 2003- 2007.  The Major Projects Authority was set up in 2011 with a mandate from the Prime Minister to turn around poor project management in Government. It reviews major projects and has the power to stop them in extreme cases.

Manzoni will need a stomach for polite confrontation if his Major Projects Authority is to continue to be effective. Some long-standing  executives in departments prefer to carry on without the influence – they call it interference – of the Cabinet Office. 

It may be that the only effective way the CEO of the Major Projects Authority can influence in the civil service is by heaping praise on departmental officials while recommending changes he hopes the department will take seriously.

The formidable David Pitchford was interim head of the Authority until he left last September.

Manzoni says: 

“Some of the largest and most complex projects can be found in Government and it’s the scale of the challenge that makes this role interesting. Working with Departments, and at the service of talented civil servants, the MPA has already delivered remarkable improvements.

“To me, the key to its continued success is the quality of project professionals at the centre and in departments. It always comes down to the people.

“If we get this right, it will be a sustainable agenda that is good for all seasons and all political persuasions. It’s hard to fight against the logic of spending large amounts of money more effectively and improving public services at the same time.”
Cabinet Office minister Francis Maude says: “John has an impressive record of leading global operations and delivering complex, challenging briefs…

“As part of this Government’s long-term economic plan we must to continue to improve the Civil Service’s management of major projects. Last year the Major Projects Authority saved hard-working taxpayers £1.7bn. I’m confident that with John’s leadership we can go even further and make a real difference to the delivery of these projects which matter to all of us.”
Danny Alexander, Chief Secretary to the Treasury adds: “The Major Projects Authority has real power to intervene in failing projects and stop taxpayers’ money being wasted, and it is already turning around our record of delivering Britain’s most important projects.

“John’s experience speaks for itself …”

Sir Bob Kerslake, Head of the Civil Service says: “Improved project delivery is a crucial part of our Civil Service Reform Plan- indeed, in the future, no one will lead a major project without completing extensive training at the Major Projects Leadership Academy.

“It is fantastic that John Manzoni is bringing his extensive experience to lead the next generation of Civil Service project managers.”

Stephen Kelly, Chief Operating Officer says “The MPA’s success lies in delivering quality outcomes on time within budget, and we are passionate to see MPA become the leading authority in world class project implementation.

“The fusion of private sector best practice with strong public service ethos is key to this future. The MPA has already had a strong start working with departments delivering major public projects and I have no doubt that John’s leadership and proven success will accelerate our delivery.”

BBC World at One’s focus on Government IT

By Tony Collins

The lead item on BBC R4’s World at One on Friday was about Government IT contracts.

On the programme were the government’s Chief Procurement Officer Bill Crothers, Cabinet Office minister Francis Maude, the chairman of the Public Accounts Committee Margaret Hodge, the UK IT Association, and me.

Some of the points made:

–  Bill Crothers gave an example of what he called “abuse” by some big IT suppliers. He said a young man who works for him lost his power cable. The supplier quoted £65 for a replacement. The price should have been £5 or £6.  When Crothers queried it, the supplier justified its price on grounds of security. Crothers could not believe that a power lead had security implications so he questioned the price again and received several pages of explanation from the supplier, which he did not read. Eventually the supplier “was good enough to reduce the price to £37”.

– HMRC was charged £30,000 for changing some text on its website.

– Francis Maude said a DWP team and a further 12 people from the Cabinet Office’s Government Digital Service had built – in only three months – a prototype of a digital solution to support the introduction of Universal Credit. The system cost just over £1m, he said. [Separately big IT suppliers at DWP have been paid £303m up to March 2013 for Universal Credit work.] Maude declined to predict the outcome of the “twin-track” work on the UC project.

– Some big legacy systems may soon need replacing – those that pay about £60bn a year in state pensions and collect nearly £100bn a year in VAT. “Those are going to be big projects,” said Margaret Hodge. “I don’t think we have seen the end of big projects, or the end of disasters.”

World at One in detail

Presenter Shaun Ley and BBC political correspondent Ross Hawkins focused on government IT because of an announcement by the Cabinet Office that it is drawing the line on “bloated and wasteful IT contracts”. The Cabinet Office was pitching its announcement as marking a “massive change,” said Hawkins.

Ley said Francis Maude announced the safeguards  in an attempt to ensure that IT contracts don’t become multi-billion pound failures. He said that the abandoned NPfIT had cost close to £10bn.

Hawkins quoted the UK IT Association as saying that  government did not know how to do deals with smaller suppliers. On the government’s relationship with big suppliers UKITA said the government was like a “battered wife or husband who doesn’t seem to know how to leave.”

Appalling

Hawkins said Crothers has the air of a man going to war. Crothers’ conclusion on the way things are at the moment:

“This is about the oligopoly, the cluster of big suppliers that have had it took good for too long. It’s reflective of monopolistic or oligopolistic behaviour.  It is not acting as if they are in hungry and in a competitive market.  That’s appalling.”

Universal Credit

Hawkins asked Francis Maude how confident he was that what was being put in place on Universal Credit would work.

“I hope it will work,” said Maude. “The digital solution was created by a team within DWP with a dozen or so GDS [Government Digital Service] staff assisting.

“They created a working prototype for a digital solution within 3 months at a cost of only a bit over £1m. That certainly can be basis of a successful long-term solution.”

Hawkins [to Maude] “I asked you whether you were confident the approach with DWP would work and you said you hoped it would. That suggests to me that maybe you are not (confident).”

Maude: “N0-one knows with these things. Anyone who says you are certain everything is going to succeed … the way we do things now is build something quickly, test it, prove it, test it with users, and so you can’t have certainty about any of these outcomes.”

Outsourcing failures

Hawkins said “We have had story after embarrassing story about outsourcing failures [such as the] government being charged for tagging dead people … now ministers  have an interest in coming out on the front foot and just for once being on the attack and having a whack at the IT companies.

“You don’t need to be a political genius to work out why they would like to do that rather than be endlessly explaining themselves after embarrassing stories in the papers.”

Ley (to me): “Is this the best way to deal with the problems government has experienced? The journalist Tony Collins has written widely  about project failures in IT in both the public and private sectors.”

I replied that big companies have sometimes charged a lot to make small software changes.  The Cabinet Office’s “red lines” were a good idea though they were a formalising of restrictions that had been in place some time.

The Cabinet Office doesn’t have the power to make changes happen because departments are accountable to Parliament for their spend and so don’t want much interference from the Cabinet Office. But the Cabinet Office is right to try and reduce the amounts spent on big projects.

Ley: “What will be the effect of breaking up contracts?”

I said I hoped the Cabinet Office’s restrictions would bring about a change in culture in departments against the assumption that big is beautiful. Big projects should be split into components which would give SMEs a greater involvement and could reduce the risks of projects failing.

More project disasters?

Hodge gave her reaction to the Cabinet Office’s restrictions in the context of the Universal Credit project.

“Francis Maude and Cabinet Office have been trying really hard to get some sense into the way that project has developed. But sadly the news we have had lately suggests to me that they have failed. It is about £400m so far on IT.

“What went wrong there was that the department [DWP] thought it [UC] was a big IT project instead of thinking:  we are going to be changing our business; we are going to get 6 benefits rolled into one. They [the DWP] have not written off that money [£303m] which is what my committee thinks they should have done, because they want to save face. Down the line I think we’ll see some disasters there.

“There are a lot of projects around  government, what are called legacy projects, where old systems need to be replaced . They are big projects – pensions in DWP where £60bn is given out a year;  VAT receipts  in HMRC where nearly £100bn is collected. Those are going to be big projects. I don’t think we have seen the end of big projects, or the end of disasters.”

Ley: “What about breaking them up into smaller projects? Won’t that reduce potential risks?”

Hodge: “The important thing is what Tony Collins was saying to you. What we find is that the skills don’t exist within departments, either to commission the IT properly or to manage the suppliers once they have the IT in place.

“We are about to examine the army recruitment contract – I think that is what we’ll find.  The MoD hasn’t got the skills to manage it.

Ley: “Do you welcome the ending of automatic contract extensions?”

“I warmly welcome that. This is a small step in the right direction. Having an expert as we have in Bill Crothers in the Cabinet Office is really important. What we haven’t got are skills in the departments. It is not like a business. If it was, Bill Crothers would probably run IT across the whole of government. Our departments run in silos. They haven’t got the skills. They have this demand for big, big programmes in the future and I don’t think we have seen, sadly, the end of IT disasters.”

Update

Thank you to Dave Orr for drawing my attention to an excellent piece on the World at One item by procurement expert Peter Smith who concludes:

“… There is a big issue – large suppliers have not covered themselves in glory, but small suppliers just can’t develop huge systems for DWP or MOD.

“The large suppliers must have a role, but we have to manage these contracts better. And the answer can’t just be a small hit squad in Cabinet Office. This needs real capability development across government, which we haven’t really seen as yet in a coordinated fashion.”

BBC World at One – Government IT contracts

Bill Crothers on BBC Radio 4 – suppliers get another good kicking

Are Govt IT-based project disasters over? Ask the Army

By Tony Collins

When senior civil servants know an IT-based project is in trouble and they’re unsure how bad things are, they sometimes offer their minister an all-encompassing euphemism to publicly describe the status of the scheme – teething.

Which may be why the defence secretary Philip Hammond told the House of Commons in November 2013 that the IT project to support army recruiting was having “teething” problems.

Now Hammond knows more, he says the problems are “big”. He no longer uses the “t” word. Speaking about the £440m 10-year Recruitment Partnering Project in the House of Commons this week Hammond said:

“Yes, there are big problems with the IT and I have told the House on repeated occasions that we have IT challenges…”

Only a few days ago Cabinet Office minister Francis Maude suggested that Government IT was no longer a byword for disaster, though he accepted there were still challenges.

In a speech on how he expected the UK to become the G8’s most digital government by next year (whatever that means) Maude said: “… it’s great news that DVLA is about to launch online driving records which can be used by anyone with a driving licence as well as by the insurance industry.

“Back in 2010 our digital offering was limited at best and government IT was a by-word for disaster … There are still challenges but with the help of the Government Digital Service I am determined that the UK will be the G8’s most digital government by next year.”

A few days later The Times reported on a leaked Gartner report on the army Recruitment Partnering Project. The report expressed concerns about the entire plan, including a poor project management team and delays that were allowed to spiral out of control.

It claimed that the Army’s recruitment division had failed to challenge MoD policy in 2011 that had apparently favoured the less suitable of the two competing bidders chasing the contract.

Hammond is said to be mulling over a £50m payout for Capita to build a new infrastructure for the recruiting system instead of trying to integrate it with systems supplied by the “Atlas” consortium under the Defence Information Infrastructure project. Hammond told the House of Commons this week:

“… there have been initial difficulties with that recruiting process as we transition to the new recruiting arrangements with Capita.

“In particular, we have encountered difficulties with the IT systems supporting the application and enlistment process. The decision to use the legacy Atlas IT platform was deemed at the time to be the quickest and most cost-effective way of delivering the new recruitment programme.

“An option to revert to a Capita hosting solution was included in the contracts as a back-up solution.

“I was made aware in the summer of last year that the Army was encountering problems with the integration of the Capita system into the Atlas platform. Since then we have put in place a number of workarounds and mitigation measures for the old IT platform to simplify the application process, and we have reintroduced military personnel to provide manual intervention to support the process.

“Having visited the Army’s recruitment centre in Upavon [Wiltshire] on 30 October, it became clear to me that, despite the Army putting in place measures to mitigate those problems in the near term, further long-term action was needed to fix the situation.

“It was agreed in principle at that point that the Atlas system was not capable of timely delivery of the Capita-run programme and that we would need to take up the option of reverting to Capita building a new IT platform specifically to run its system, which will be ready early next year.

“… we have already taken action to bring in a range of new initiatives that will make it progressively easier and quicker for applicants … the introduction this month of a new front-end web application for Army recruitment; a simplified online application form; more streamlined medical clearance processes …

“With an improved Army recruitment website, streamlined medicals and an increase in the number of recruiting staff, recruits should see a much-improved experience by the end of this month.

“.. we are looking at further ways of improving the management of the recruiting process in the intervening period before the introduction of the advanced IT system now being developed in partnership with Capita, which is expected to be deployed in February 2015…”

Vernon Croaker, Labour’s defence spokesman, said the recruitment project was an IT fiasco. He wondered why Hammond had initially described the problems as teething.

“Today we have learned [from newspapers] that the problems are even worse than anyone thought and still have not been fixed.

“Will the Defence Secretary tell the House which Minister signed off the deal and who has been responsible for monitoring it?

“… Will the Secretary of State also confirm that £15.5m has been spent building the existing flawed computer system behind the project? Finally, is it correct that this continuing disaster is costing taxpayers £1 million every month?…”

Croaker quoted a minister Andrew Robathan as telling MPs on 10 April 2013 that the “Recruiting Partnering Project with Capita…will lead to a significant increase in recruiting performance”.

Croaker said: “Is there any Member of this House, any member of our armed forces or, indeed, any member of the British public who still believes that?”

In March 2012 Capita announced that the Recruitment Partnering Project was valued at about £44m a year for 10 years and was expected to deliver benefits in excess of £300m to the armed forces. It would “release military recruiters back to the front line” said Capita.

Comment. Francis Maude is probably right: there don’t seem to be as many big IT-based project failures as in previous decades. But then the truth isn’t known because progress reports on big IT-related schemes are not published.

Indeed little would be known about the Capita Recruitment Partnering Project is not for the leaked report to The Times. Without the leak, public information on the state of the project would be confined to Hammond’s “teething problems” comment to MPs last November.

Internal and external reports on the state of the Universal Credit IT project continue to be kept secret.  It’s not even clear whether ministers are properly briefed on their big IT projects. Hammond almost certainly wasn’t last year. IDS was left to commission his own “red team” review of Universal Credit IT.

Perhaps the “good news” reporting culture in Whitehall explains why the NHS IT scheme, the NPfIT, continued to die painfully slowly for 7 years before senior officials and ministers started to question whether all was well.

Hammond is still getting wrong information. He described “Atlas” systems in the House of Commons as the “legacy IT platform”.

The Atlas contract for the Defence Information Infrastructure was awarded in 2005 for 10 years. It doesn’t even expire until next year. It may be convenient for officials to suggest that the reason Capita has been unable to link new recruitment systems into the DII network is because DII is old – legacy IT.  But the multi-billion pound Atlas DII project cannot be accurately described as “legacy” yet.

If ministers don’t get the truth about their big IT projects until serous problems are so obvious they can no longer be denied, how can Parliament and taxpayers expect to get the truth?

Lessons from NASA?

NASA put in place processes, procedures and rules to ensure engineers were open and deliberately adversarial in challenging assumptions. Even so it has had difficulties getting engineers to express  their views freely.

Diane Vaughan in her excellent book “The Challenger Launch Decision” referred to large organisations that proceeded as if nothing was wrong “in the face of evidence that something was wrong”.  She said NASA made a series of seemingly harmless decisions that “incrementally moved the space agency towards a catastrophic outcome”.

After the loss of Challenger NASA made many changes. But an investigation into the subsequent tragedy of the Columbia space shuttle indicated that little had actually changed – even though few of the top people who had been exposed to the lessons of Challenger were still in position.

If NASA couldn’t change when lives depended on it, is it likely the UK civil service will ever change?  A political heavyweight,  Francis Maude has tried and failed to get departments to be more open about progress or otherwise on their big IT-based projects.  Permanent secretaries now allow the out-of-date “traffic light” status of some projects to be published in the annual report of the Major Projects Authority. That is not openness.

The failure so far of the Recruitment Partnering Project, the routine suppression of information on technology-based scheme such as this, and the circumscribed “good news” briefings to ministers, suggest that government IT-based project failures are here to stay, despite the best intentions of the Cabinet Office, GDS and the Major Projects Authority.

Thank you to campaigner Dave Orr for his email on the recruitment project

Big 4 Universal Credit IT suppliers punished?

By Tony Collins

The  latest draft business case for Universal Credit suggests existing IT suppliers will have little to do with the “end-state digital solution” that is  due eventually to support the roll-out of UC.

The Department for Work and Pensions will use a mixture of its own and external people for the end-state digital solution.

Computer Weekly quotes part of the draft business case as saying:

“To extend the current IT solution we will be using a standard waterfall delivery approach largely using existing suppliers and commercial frameworks, in order to de-risk delivery and ensure UC continues to have a safe and secure introduction.

“The end-state digital solution will be delivered using an agile, and therefore iterative, approach as advocated by the Cabinet Office with significantly less reliance on the large IT suppliers delivering the current UC IT service.”

Politicalscrapbook.net picks up Computer Weekly’s report and says that Iain Duncan Smith “punishes Universal Credit IT suppliers“. 

Costs

Computer Weekly quotes the draft business case as putting the cost of the end-state solution at £106m – comprising external IT costs of £69m and in-house “Design and Build” team costs of £37m.

The total cost of UC IT is now put at £535m – down substantially on the £673m estimate in the DWP’s December 2012 UC business case.

UC project at “red” 

Yesterday the Guardian reported that Francis Maude and his team at the government digital service have objected to the twin-track approach to UC but were outflanked by “a majority” of other government ministers and project advisers, leaked minutes say.

The twin-track approach to UC IT means that the DWP and its main suppliers – HP, Accenture, IBM and BT – continue to develop existing systems (a blend of legacy and new technology) while a separate team develops a new “end-state” system for use by the end of 2017. It’s unclear how the two systems will differ. 

Computer Weekly quotes the latest draft business case as saying it is “unclear what the digital service will deliver and to what timescales”.

Due to the multitude of problems facing universal credit, the project has been coded “red” overall, according to the Guardian.

Comment

Computer Weekly has done well to gain sight of the latest draft business case for UC.

Whoever wrote the draft appears to accept the Cabinet Office’s case for departments to “move away from large ICT projects” and thus “reduce waste, provide a more flexible approach to complex business requirements that are likely to change over time and reduce the risk of project failures”. (National Audit Office, Universal Credit: early progress). 

But is the DWP simply telling the Cabinet Office what it wants to hear?  All the signs are that the big money at the DWP will continue to go to its main IT suppliers. 

The £106m agile “end-state digital solution” is a bonus system which may or may not materialise.  It is in essence a big, agile research project and the DWP is having trouble finding IT professionals to work on it.

If ever it’s a success it could start to replace existing UC IT in 2017 or beyond. But that may never happen. The DWP has already spent more than £300m on existing UC technology and is set to spend a lot more: around £90m. The DWP is unlikely to scrap it.

So HP, IBM, Accenture and BT are all but guaranteed a large income stream from the non end-state UC technology.

Even without the UC project the big 4 are guaranteed a large income from the DWP’s other work which includes:

– Personal Independence Implementation – 2.8bn 2011–2016
– Fraud and error programme – £770m  2012–2015
– Child maintenance group change 1.2bn 2009–2014
– Pensions reform Enabling Retirement Savings programme 1.04bn 2007–2018
– State Pension reform – single tier £114m 2012–2017
– Specialist Disability Employment programme – £203m 2012–2014

The big 4 will also continue to receive a large chunk of the DWP’s IT budget for maintaining and upgrading the existing software, hardware and networks.

Business cases are written by experts in the writing of Whitehall business cases.  Their main purpose is to provide a case for the Treasury to release funds for a project. They give current thinking on costs and benefits. The documents are revised when these change significantly.

So the statement in the UC draft business case that the new end-state digital solution will rely “significantly less” on existing UC IT suppliers means little: it is subject to change.

And the words “significantly less” are  unexplained. They may have no scientific basis. 

Worrying

The big 4 suppliers continue to be all-important to the DWP – and are so enmeshed that they decide at times how much they should be paid, suggests the NAO.

From its latest report on the UC project, the NAO comments on the DWP’s lack of control of suppliers :

– “In February 2013, the Major Projects Authority reported there was no evidence of the Department actively managing its supplier contracts and recommended that the Department needed to urgently get a grip of its supplier management.”

– “[The DWP has] limited IT capability and ‘intelligent client’ function leading to a risk of supplier self-review.”

– “[The DWP has] inadequate controls over what would be supplied, when and at what cost because deliverables were not always defined before contracts were signed.”

– “[The DWP has an] over-reliance on performance information that was provided by suppliers without Department validation.”

– ” … the Department did not enforce all the key terms and conditions of its standard contract management framework, inhibiting its ability to hold suppliers to account.”

So it would be naively optimistic to suppose that if the big 4 were to be frozen out of the end-state solution for UC that it would make much difference to their income from the DWP.      

UC in chaos or not?

A generous interpretation of all the available evidence on the UC project so far is that the DWP is working through, and understanding, the difficulties on an immensely complicated IT-enabled project.

And supporters of the twin-track approach could argue that two completely independent sets of teams are working in parallel and in discreet competition to produce the most successful system. One team comprises the big 4 using waterfall and the other a largely in-house team using agile.  Eventually one system will prevail, even if it’s 2020 or beyond that it handles securely online all types of claims. On completion the system will simplify benefit claims and cut the costs of administration.

A less generous interpretation of the available facts is that the UC IT project  is in chaos and that vast sums continue to be poured into a poorly formed strategy that nobody in government will concede is failing;  all parties are preoccupied with resolving problems as they arise and expecting irrationally that things will come good in the end.  Nobody should expect the full truth to emerge from those who have a deep interest in the project’s success including IDS and his permanent secretary Robert Devereux.

Howard Shiplee, head of the UC project, may still be getting his head around how chaotic things are. The highly capable David Pitchford, who headed UC  for a few months before he quit the civil service last year, came close to saying the project was in chaos. His Major Projects Authority said in February 2013 that the DWP needed to “rethink the delivery approach”, said the NAO.

Indeed the UC project shows many of the usual signs of a government IT-based project failure:

– major changes in the basic assumptions between the business case of December 2012 and the latest draft business case
– excessive secrecy (keeping secret a succession of internal and external reports on the project).
– defensiveness (continued DWP claims that problems are historic)
– a high turnover of leaders
– a culture of good news that “limited open discussion and stifled challenge”, said the NAO
– a lack of control of suppliers (NAO)
– repeated delays
– suppliers that get paid regardless of whether their systems are contributing to a  successful project.

To me things look chaotic but I hope I’m wrong. I’d like UC IT to work. IDS and Shiplee will probably know the whole truth – and they are still in post, to date.  If Shiplee leaves the project before the general election that could be an indication of how bad things really are.   

Top 5 posts on this site in last 12 months

Below are the top 5 most viewed posts of 2013.  Of other posts the most viewed includes “What exactly is HMRC paying Capgemini billions for?” and “Somerset County Council settles IBM dispute – who wins?“.

1) Big IT suppliers and their Whitehall “hostages

Mark Thompson is a senior lecturer in information systems at Cambridge Judge Business School, ICT futures advisor to the Cabinet Office and strategy director at consultancy Methods.

Last month he said in a Guardian comment that central government departments are “increasingly being held hostage by a handful of huge, often overseas, suppliers of customised all-or-nothing IT systems”.

Some senior officials are happy to be held captive.

“Unfortunately, hostage and hostage taker have become closely aligned in Stockholm-syndrome fashion.

“Many people in the public sector now design, procure, manage and evaluate these IT systems and ignore the exploitative nature of the relationship,” said Thompson.

The Stockholm syndrome is a psychological phenomenon in which hostages bond with their captors, sometimes to the point of defending them.

This month the Foreign and Commonwealth Office issued  a pre-tender notice for Oracle ERP systems. Worth between £250m and £750m, the framework will be open to all central government departments, arms length bodies and agencies and will replace the current “Prism” contract with Capgemini.

It’s an old-style centralised framework that, says Chris Chant, former Executive Director at the Cabinet Office who was its head of G-Cloud, will have Oracle popping champagne corks.

2) Natwest/RBS – what went wrong?

Outsourcing to India and losing IBM mainframe skills in the process? The failure of CA-7 batch scheduling software which had a knock-on effect on multiple feeder systems?

As RBS continues to try and clear the backlog from last week’s crash during a software upgrade, many in the IT industry are asking how it could have happened.

3) Another Universal Credit leader stands down

Universal Credit’s Programme Director, Hilary Reynolds, has stood down after only four months in post. The Department for Work and Pensions says she has been replaced by the interim head of Universal Credit David Pitchford.

Last month the DWP said Pitchford was temporarily leading Universal Credit following the death of Philip Langsdale at Christmas. In November 2012 the DWP confirmed that the then Programme Director for UC, Malcolm Whitehouse, was stepping down – to be replaced by Hilary Reynolds. Steve Dover,  the DWP’s Corporate Director, Universal Credit Programme Business, has also been replaced.

4) The “best implementation of Cerner Millennium yet”?

Edward Donald, the chief executive of Reading-based Royal Berkshire NHS Foundation Trust, is reported in the trust’s latest published board papers as saying that a Cerner go-live has been relatively successful.

“The Chief Executive emphasised that, despite these challenges, the ‘go-live’ at the Trust had been more successful than in other Cerner Millennium sites.”

A similar, stronger message appeared was in a separate board paper which was released under FOI.  Royal Berkshire’s EPR [electronic patient record] Executive Governance Committee minutes said:

“… the Committee noted that the Trust’s launch had been considered to be the best implementation of Cerner Millennium yet and that despite staff misgivings, the project was progressing well. This positive message should also be disseminated…”

Royal Berkshire went live in June 2012 with an implementation of Cerner outside the NPfIT.  In mid-2009, the trust signed with University of Pittsburgh Medical Centre to deliver Millennium.

Not everything has gone well – which raises questions, if this was the best Cerner implementation yet,  of what others were like.

5) Universal Credit – the ace up Duncan Smith’s sleeve?

Some people, including those in the know, suspect  Universal Credit will be a failed IT-based project, among them Francis Maude. As Cabinet Office minister Maude is ultimately responsible for the Major Projects Authority which has the job, among other things, of averting major project failures.

But Iain Duncan Smith, the DWP secretary of state, has an ace up his sleeve: the initial go-live of Universal Credit is so limited in scope that claims could be managed by hand, at least in part.

The DWP’s FAQs suggest that Universal Credit will handle, in its first phase due to start in October 2013, only new claims  – and only those from the unemployed.  Under such a light load the system is unlikely to fail, as any particularly complicated claims could managed clerically.

 

Is £40m write-off on a big software project normal?

By Tony Collins

On BBC R4’s “Week in Westminster” on Saturday morning (14/12/13)  guest presenter Isabel Hardman of The Spectator spoke to Conservative MP Richard Bacon and me about big government projects that go wrong.

Hardman mentioned that Bacon has co-written a book  on government failures Conundrum: Why every government gets things wrong and what we can do about it.

Referring to write-offs so far of about £40m on Universal Credit, Hardman asked me whether it was normal for such a write-off on a big project.

I said it wasn’t. The work and pensions secretary Iain Duncan Smith has said it was. When questioned by MPs of the work and pensions committee on 9 December, IDS implied that it was not unusual to write-off a third on large software-based projects. He suggested that research by Forrester supported this view.

Software coding for Universal Credit has cost about £120m so far (excluding hardware, infrastructure, consultancy or other IT-related costs). So IDS suggested that a write off of £40m was only about a third of the software coding costs.

But I haven’t seen any evidence that suggests write-offs of a third of the software costs on a big project are typical.   

I replied to Hardman that although there has been much trial and error on Universal Credit IT, £40m is a lot to write off.

[Trial and error included an attempt, from 2011 onwards, to adopt an agile approach but the National Audit Office said the DWP “experienced problems incorporating the agile approach into existing contracts, governance and assurance structures”. The NAO added that the Cabinet Office “did not consider that the Department (DWP) had at any point prior to the reset [Feb-May 2013]  appropriately adopted an agile approach to managing the Universal Credit programme”. The DWP has now introduced what it calls Agile 2.0, a hybrid approach incorporating elements of  agile with waterfall, though agile purists say it is impossible to combine the two.]

I told Hardman that the write-offs were largely because the DWP was unclear at the outset what the software was supposed to do.”With big IT projects it’s a bit like designing a bridge and you know where one side begins but you’re not sure where the other side ends. They have been learning as they go along and that’s probably why there have been large write-offs,” I said.

Hardman asked Richard Bacon whether it was normal to set out on these big projects without knowing where the bridge was going. Bacon agreed, citing the NPfIT which had led to large write-offs on failed work for England-wide electronic patient records. He said it was not at all abnormal for ministers to set off on big projects without knowing where they were going.  

The good news?

I told Hardman that IDS was at least well informed. He now has the NAO scrutinising the project as well as his own external consultants and the independently-minded Howard Shiplee as head of the project.

But I didn’t think UC would be complete until 2020 at the earliest given that the last big computerisation of benefit systems, Operational Strategy, took about 10 years to complete. Hardman said: “That would be a humiliation for IDS surely?”

I replied that IDS may not even be in politics in 2017. I also said that UC will probably not bring the financial benefits predicted, to judge from the last big computerisation of benefits.  But UC has wide support. Perhaps, I said, it has to work … eventually. 

BBC R4 Week in Westminster – 14/12/13

Universal Credit: more IT uncertainties

By Tony Collins

Shortly after IDS was in the House of Commons yesterday defending his handling of the Universal Credit project – taking an all is well approach – the National Audit Office issued a report that drew attention to the scheme’s uncertainties, write-offs on IT so far of £41.3m, and the five-year depreciation of a further £91m spend on IT that may not be used after the migration from legacy, or transitional, UC systems to in a new “digital” solution.

The legacy Universal Credit  IT infrastructure is a blend of existing DWP IT and technology adapted to UC.

The DWP had originally expected to depreciate the £91m over 15 years but, suggests the NAO, the legacy Universal Credit IT infrastructure may be of little use after 2017/2018.   

Says the NAO:

“…  the underlying issue [is] that the Department has spent £91.0 million on assets that will only support a limited service for 5 years, with clear consequences for public value.”

On what the NAO report calls the “longer-term programme uncertainties” it says that the “overall cost of developing assets to support Universal Credit is subject to considerable uncertainty”.

It adds:

“The Department acknowledges  … that there is uncertainty over the useful economic life of the existing Universal Credit software pending the development of the alternative digital solution and uncertainty over whether Universal Credit claimants will be able to migrate from the current IT infrastructure to the new digital solution by December 2017.”

The NAO’s report on the DWP’s 2012/2013 accounts also notes the uncertainties with the new digital solution. Says the NAO:

“At this early stage in its development, there are uncertainties over the exact nature of the digital solution, and in particular:

– How it will work;

– When it will be ready;

– How much it will cost; and

– Who will do the work to develop and build it.

A Ministerial Oversight Group has approved a spend of between £25m and £32m on the new digital UC solution up to November 2014. DWP officials and suppliers plan to build a core digital service that will deliver to 100 people by then, after which it will assess the results of that work and consider whether to extend the service to increasing numbers.

The NAO suggests that some of the money spent on the new digital solution may also end up being written off.  Says its report:

“As the Department develops the digital solution, so it will start to recognise some of the costs incurred as assets. Without clear and effective management, in the future the Department may also find it needs to impair some of these new digital assets.”

At a hearing of the Work and Pensions Committee on Monday Iain Duncan Smith depicted the write-off of £40m on UC software code so far as normal for any large organisation in the private or public sector that embarks on a major software-based programme.  IDS said that private sector organisations typically write off a third of the money spent on software on a large project. About £120m has been spent on writing UC software code so far.

Amyas Morse, head of the NAO,refers in his report to the “considerable sums that the Department is proposing to invest in a programme where there are significant levels of technical, cost and timetable uncertainty”.

He adds:

“I reiterate both the conclusion and recommendations from my report in September. The Department has to date not achieved value for the money it has incurred in the development of Universal Credit, and to do so in future it will need to learn the lessons of past failures …”

In a short debate on UC in the House of Commons yesterday Rachel Reeves, Shadow Work and Pensions secretary, suggested Iain Duncan Smith was in denial about being in denial.  She put points to him he did not answer directly.

She said that IDS had told the House of Commons on 5 September 2013 that UC will be delivered in time and on budget. On 14 October IDS made the same claim. Reeves said:

“How on earth can this be on time when in November 2011 he [IDS] said:  ‘All new applications for existing benefits and credits will be entirely phased out by April 2014.’

“We have now learned that this milestone will only be reached in 2016. Will the secretary of state confirm that this is a delay of 2 years? … How can the secretary of state say that Universal Credit will be on budget when even by his own admission £40.1m is being written off on IT [software code]? What budget heading was that under?”

Reeves said IDS also revealed on Monday that another £90m will be written off by 2018. She added:

“ …The underlying problem is surely that the secretary of state has not resolved key policy decisions before spending hundreds of millions of pounds on an IT system… the secretary of state is in denial. Doubtless he’ll deny he is in denial….

IDS replied:

“ I said all along and I repeat: this programme essentially [jeers] is going to be on time. By 2017 some 6.5m people will be on the programme receiving benefits.”

He added that UC will roll out without damaging a single person. “The waste we inherited was the waste of people who didn’t listen, rushed programmes and implementing them badly.”

Dame Anne Begg, chair of the Work and Pensions Committee, said that IDS promised UC would be digital by default. “It isn’t,” she said.

“He promised that all new claims would be on UC by May 2014. They won’t…  So why should anyone believe him when he says that delivery of UC is now on track?”

IDS replied: “The proof of this will be as we roll it out…”

Comment

IDS is doing what he has to do: defend the UC project at all costs; and the NAO is doing what it needs to do: highlight the uncertainties and wasted spending.  If IDS admits to his doubts and concerns the opposition will jump on him. At least he is not being kept in the dark any longer by his senior civil servants.  He has his own reliable information – via Howard Shiplee – and from the NAO.  In 2011 he commissioned his own independent “red team” review which led to the pilot Pathfinder projects.

But the uncertainties highlighted by the NAO’s report today could be said to tacitly confirm that the transfer of all relevant claimants to UC project is unlikely to be complete before 2019/2020 at the earliest.  That’s probably not something anyone in government could own up to before the 2015 general election.

And even his advisers may not tell IDS that big government IT projects can be defined by the exceptions. IDS told MPs yesterday that Pathfinder projects indicated that 90% of people are claiming universal credit online and 78% are confident about their ability to budget with monthly payments. That’s 10% who don’t claim online and 22% who may not be able to manage with monthly payments. Will the high number of exceptions prove a show-stopper?

There’s a long way to go before officials and ministers can have confidence in UC IT. But, unlike the NPfIT which had little support in the NHS, most of those involved in the UC project want it work. That could make all the difference. 

Universal Credit to be partly online

By Tony Collins

At yesterday’s Work and Pensions Committee hearing Howard Shiplee, Director General for Universal Credit, confirmed what many have been saying:  that UC will not be an entirely online process.

He said claimants will have to prove who they say they are. He didn’t say how but one suggestion is that claimants may have to produce documents at an interview, and may have to prove changes in circumstances.

This would make online security for UC – which has been a major sticking point –  easier to design.  

Shiplee told MPs yesterday:

“From a security point of view to have everything digital is not at this stage a sensible or appropriate solution.

“It will take some considerable time to get to a totally online system. In fact nobody is operating the types of system we are talking about which are disbursing large sums of money. Nobody is using a totally online approach. You have to prove who you are. You have to prove what you are doing when you change circumstance. If you want to open a bank account you have to go and present yourself.

“I have talked to a lot of financial institutions about this and that is exactly where they are coming from as well.”

Dame Anne Begg, chair of the committee, asked when it was decided that the original approach of “digital by default” was wrong – a “false promise that was never going to be delivered”.

Shiplee replied:

“It is very difficult to talk about promises. There is nothing wrong with having aspirations. If people don’t have aspirations to achieve things there will be no progress. Perhaps that was an aspiration a little too far at a stage in time.”

Another MP, Stephen Lloyd, Liberal Democrat, asked Shiplee about alleged interference of Universal Credit by the Cabinet Office (which is anxious to ensure that UC is not another government IT-related disaster). Lloyd asked if there is any truth in the suggestion that if the Cabinet Office doesn’t stop interfering Shiplee will quit.

Shiplee did not confirm or deny. He said:

“I cannot comment on tittle tattle that I haven’t heard. What I can comment on is that occasionally one has disagreements with people and one has to get on with things. I am charged with having a sense of urgency about these things. I make no excuse for that. There are no other issues that are holding me up…”

Asked by Lloyd on a scale of 1-10 how confident he is that UC will be delivered, and delivered in scale, with the huge volumes intended Shiplee replied:

“I have never been keen on one to tens so I will just give it to you straight. I believe UC can be delivered in the way that has been suggested.

“What we are talking about is automating a system in terms of technology but what in many ways is much more important is the culture change, the change in the way our business operates. All of these that tend to get completely ignored in these sorts of discussions.

“The technology is an enabler but many of the challenges we have not fully faced yet we will face as the business is reconfigured, as tens of thousands of our staff are retrained …there are a whole series of challenges. But can it be delivered? The answer is that there is no doubt in my mind.”

Will it be delivered?

“I believe it will be. It has to be delivered.”

Universal Credit project to abandon digital by default – Brian Wernham’s blog

Will truth ever be told when things go wrong?

By Tony Collins

Cabinet Office minister Francis Maude has criticised civil servants who don’t always tell ministers what is going on in their departments. He used the Universal Credit project as an example.

He told the Financial Times: “There were a lot of failures in DWP and it isn’t good that it took a review commissioned . . . by the secretary of state to disclose what was going on.”

He added:

“You’ll find a lot of ministers don’t know a lot of things going on in the department because there’s no way you’ll find out.”

Maude’s comments touch on a common factor in IT-related project disasters in government – that ministers get mostly “good news” from their officials, and learn little or nothing about the seriousness of problems until a debacle is only too apparent to be denied.

But can ministers or the boards of large private companies ever expect their senior staff to be the bearers of bad news?

The Performing Right Society did not find out the truth about its failing IT-based project until it appointed a new head of IT who had no emotional equity in what had gone on before. [Crash – chapter 1)

The National Audit Office report “Universal Credit: early progress” referred to a “good news” culture at the Department for Work and Pensions that “limited open discussion of risks and stifled challenge”.

Ministers in charge of the Rural Payments Agency’s Single Payment Scheme said they were kept in the dark about the seriousness of IT-related problems. “When delays occurred, many stakeholders only found out at the last minute,” said a report of the Public Accounts Committee.

“Conspiracy of optimism”

The PAC report of March 2007 is worth a further mention:

“Lord Bach [minister in charge of the Single Payment Scheme] told us that he felt very let down by the advice he had received from the RPA [Rural Payments Agency], upon whom he said the Department relied very heavily in these circumstances, and the “conspiracy of optimism” on the part of the Agency.”

Lord Bach told MPs that he kept being told by officials that all was well.

“I frankly have to say that I do not think that that was satisfactory from senior civil servants whose job is to tell ministers the truth.”

Let down by civil servants – Universal Credit

Now the FT reports that Francis Maude has “entered the controversy over the implementation of the government’s universal credit scheme”. Maude told the FT he believed that Iain Duncan Smith, the work and pensions secretary, had been let down by his civil servants.

Maude said senior civil servants in charge of projects should tell ministers bluntly if they felt they were being misdirected and insist on a formal “letter of direction” to show that they had raised their objections. If they did not, they should be accountable for failings on their watch.

Maude did not comment directly on whether Robert Devereux, the top official in Mr Duncan Smith’s department, should take the rap for the much-criticised implementation of universal credit, but said: “I think everybody has to take responsibility for what they were part of”.

SROs accountable to MPs?

He suggested that civil servants who are in charge of big projects, known as senior responsible owners (SROs), should account directly to parliament, which would “toughen the relationship with ministers” and give officials a greater incentive to challenge developments they believed were wrong.

He said: “If you have an SRO who knows that he or she is going to be hauled up in front of select committees and interrogated . . . then I think you’re much more likely to have what is a very healthy thing in our system which is push-back. . . There’s a great phrase ‘speaking truth unto power’ and it’s very important – it doesn’t happen enough.

He added: “I’ve never had a civil servant come to me and say ‘Would you like us to stop doing this?’ The answer might easily be, ‘yes’.”

Comment:

Do ministers and boards of large private companies always have to commission their own independent reports to find out if their organisation’s biggest IT-based projects are failing? Probably.

The problem is not one of lying. Civil servants tend not to lie. Neither do senior executives when reporting to their boards. But the sin of omission – the art of not telling the truth while not lying – is well practiced in public life.

A succession of IT-based project disasters in the US, Australia and the UK show that truth is the first casualty of any large failing IT-based project.

Barnet Council and Capita

It’s isn’t just IT-based projects that bring out the sin of omission. Outsourcing deals do too. Barnet Council’s outsourcing deal to Capita is mired in controversy over truth.

Why did Barnet’s officials give Capita £16m after saying that the council had no spare cash, and that Capita would make the necessary upfront IT investments?

Officials have given a long-winded explanation which is a little like the drawn-out, incomprehensible explanation a six year-old may give in the playground when teacher asks why he took his friend’s bar of chocolate.

Liverpool LDL, BT and excessive mark-ups?

Liverpool Direct Ltd, a joint venture between Liverpool council and BT, is also mired in a controversy over truth. According to the Liverpool Daily Post, Local Government Minister Brandon Lewis has questioned whether LDL is proving value for money. There are allegations of excessive mark-ups on IT and services supplied by BT to the council.

It seems that BT makes a mark-up on what it supplies to LDL and LDL makes a further mark-up on what it supplies to the council.

But a council spokesperson said: ““The mark up incorporates a calculation of the cost of setting up a particular piece of hardware or software by LDL. The important figure is the profit after tax per item which is much lower, and on some items, LDL actually makes a loss.”

The minister said Liverpool Council needed to open up its books if it wants to insist it gets value for money from the BT deal. Will Liverpool Council open up?

Hardly.

Politicise parts of the civil service?

There is a strong argument for politicising the top echelons of the civil service so that ministers are not so reliant on officials who are thought to be neutral but evidence shows can be biased towards good news and suppressing the bad.

Ministers and boards of large companies do not need various versions of the truth when things go wrong. They need their own version.

As Richard Nixon said when accepting the presidential nomination in 1968 [pre-Watergate]:

“Let us begin by committing ourselves to the truth—to see it like it is, and tell it like it is—to find the truth, to speak the truth, and to live the truth.”

Doubtless Nixon believed it when he said it. Just as countless officials and executives in public and private life believe they are speaking the truth when they ministers and boards on their big IT-based projects. It may be the truth. But how much of it are they telling?

Update:

In a tweet BrianSJ3 makes a great suggestion: Genchi Genbutsu – “go and see for yourself” he says.