Category Archives: openness and transparency

Croydon trust plans “high-risk” Cerner go-live in secret

By Tony Collins

NHS trusts have gone live with Cerner Millennium with mixed success. Eight trust implementations went seriously awry. A list is at the end of this post.

The flawed go-lives have meant that hospital managers have lost track, cumulatively, of thousands of patients and found that treatments,  including those for cancer, were delayed or care pathways interrupted. At times medical notes have not been available, or clinicians have been given the wrong notes.

In July 2008 E-Health Insider reported that the deployment of a national programme care records system at Milton Keynes Hospital NHS Foundation Trust “developed into an untenable situation which resulted in near melt down of the organisation”.

One of the lessons from the problematic go-lives is that trusts, when they have reported on the difficulties later, have said they underestimated the risks.

In particular they regarded the patient records system as mainly administrative with no risks to the health and care of patients.  Yet it is possible for incidents arising from flawed patient record implementations to be judged “clinical”.

Is Croydon Health Services NHS Trust, which includes the former Mayday hospital, about to repeat this same mistake – of regarding the risks as non-clinical?

The Trust is due to go live this weekend with the start of one of the largest patient record go-lives in the UK.  The deployment is being run under the NPfIT, which, in the capital, is now called the London Programme for IT. The plans are to install Millennium at Croydon University Hospital (formerly Mayday) and at some community sites.

The Trust says its preparations are designed to ensure a safe and effective deployment that will replace systems that are more than 20 years old and lack “many of the functions one expects in the modern healthcare digital age”.

But the signs are, from the trust’s board papers, that the risks of a flawed implementation are being seen largely as financial and administrative. For patients it appears that the worst that is envisaged is a “poor experience”.  

Have the risks to patients been properly flagged to the board’s directors?

I looked through Croydon’s most recently published board papers to see how well the trust’s directors have been kept informed of the risks of the go-live and could see almost no mention of Cerner – except a risk that income to the Trust could be affected if it is unable to produce timely reports. There is no specific mention of risks to patients.

Given the history of failed implementations of Cerner Millennium under the NPfIT, I asked  Croydon Health NHS Trust what directors have been told about the risks.

This was the trust’s reply:

“CRS Millennium has featured regularly on the Corporate Risk Register presented to each Part 1 Board meeting.

“In addition, implementation has received detailed confidential consideration at Part 2 of Board meetings, (which is why you won’t find it in our public board papers).”

I then put it to the trust that I was not sure why, in a new era of openness and transparency in the NHS,  that board discussions should be in private on a matter that could affect large numbers of patients to judge from past implementations at other trusts. The spokesperson – the interim stakeholder relations manager – made no further comment.

Richard Granger,  when head of the NPfIT, was quoted as saying he was ashamed of some of the Cerner deployments . Granger quit the programme in January 2008 – and since then several more Cerner deployments at trusts have gone badly wrong, at North Bristol NHS Trust, for example.

After the NPfIT go-live of Cerner at the Nuffield Orthopaedic Centre, the National Audit Office, at the request of a member of the Public Accounts Committee Conservative MP Richard Bacon, investigated and produced a public report on the lessons learned.

The Nuffield go-live was in December 2005. Since then managers at all trusts that have gone live with Cerner have claimed they have learned those lessons.

Comment:

It’s true that Croydon Trust’s risk register has shown “red” for the Cerner implementation. It is indeed deemed “high risk”. But how many of its board directors will understand the nature and substance of the risks to patients from a graphic?

It’s easy for the trust to say that board directors have been informed through confidential discussions but how would anyone outside the trust be able to judge whether that’s true?

Trust boards can never be held fully accountable after a patient record go-live goes wrong. They hold their own investigations or sometimes commission inquiries by consultants known to them, and the final reports usually indicate that no patients have been harmed.  Even after a trust has lost track of thousands of patient appointments for more than a year, it has later reported that in the end all was well.

As trust boards are not voted in and out by the public they have a special duty to ensure they are fully informed on things that can go wrong. Is Croydon Health’s board fully informed on the risks of the Cerner go-live? I doubt it.  

Some flawed NHS patient record go-lives:

Barts and The London

Royal Free Hampstead

Weston Area Health Trust

Milton Keynes Hospital NHS Trust

Worthing and Southlands

Barnet and Chase Farm Hospitals NHS Trust

Nuffield Orthopaedic

North Bristol.

St George’s Healthcare NHS Trust

Lorenzo:

University Hospitals of Morecambe Bay NHS Foundation Trust

Birmingham Women’s Foundation Trust

NHS Bury

Is this a reason some council and NHS scandals stay hidden for years?

By Tony Collins

Six years into Southwest One’s joint venture between IBM and three public authorities, the outsourced service is not a big success.  

Somerset County Council, one of the joint venture’s partners, has been in dispute with IBM, the major shareholder in Southwest One. It cost the county council £5.9m to settle, including £800,000 in costs when bringing back staff who had been outsourced.

The joint venture’s SAP-based “transformation” led to complaints of poor quality of service by some of Somerset’s finance users; the venture has consistently made losses and on the matter of savings, Somerset Cabinet member for resources, David Huxtable, said there have been some but added:

“It was a very complex contract and lots of the savings were predicated on an ever-increasing amount of money being put into public services and we know in the last four years that has gone into reverse.”

Now IBM has sold its low-margin customer care outsourcing unit which could affect the future of Southwest One.

Yet a smaller partner in Southwest One, Taunton Deane Borough Council, describes the relationship as a “success”. Reports to Taunton Deane’s councillors on Southwest One are remarkably positive.

Dave Orr an IT specialist who used to be work for Somerset County Council and has kept a close eye on Southwest One since it was formed in 2007 has drawn my attention to Taunton’s latest reports on the joint venture. When read quickly Taunton’s reports are upbeat, almost breathless with praise for the joint venture.

Below are excerpts from two reports that have been written for today’s meeting of Taunton Deane’s Corporate Scrutiny Committee.  The first is a “Procurement Transformation Update”, report to the council by Southwest One’s Chief Procurement Officer.

There are no hints of any difficulties on the contract except a comment that cutting spending will make it harder to achieve procurement savings. From Southwest One’s report to Taunton:

“Executive Summary

“As at 31/07/13, in excess of £1.8m [report’s emphasis] savings have been delivered to the Council through signed-off procurement-related initiatives brought about by Southwest One’s Strategic Procurement Service. This is up from £1.59m when last reported in January 2013.

“A further £1.364m of savings are scheduled to be delivered from these signed-off initiatives during the life of the current Southwest One contract, which expires in 2017.

“Multiple projects continue to be progressed by Southwest One Strategic Procurement Service which are expected to significantly add to the pipeline of savings. These Include initiatives for a new pool & spa at Blackbrook; Waste; Insurance; various small scale initiatives within the DLO/HPS areas .”

A second report for Taunton’s Corporate Scrutiny Committee “SouthwestOne Partnership Update report” is written jointly by a team at Taunton council and the CEO of Southwest One. Again it’s upbeat and summarises Southwest One’s performance over the last six months.

“Service delivery for TDBC, viewed in the round, is broadly on track. The majority of services perform well or extremely well (eg Customer Services). We do have concerns in some areas and we are working closely with the services in question to remedy the issues. “

The report says that the shared service model in conjunction with larger authorities provides Taunton with “much needed resilience” (report’s underlining) in service delivery, although “this has been impacted to a certain extent by changes made recently to the contract by the other partners”.

Additionally, “our secondee staff to SWO benefit from ‘assured employment’, which was offered by IBM”.

A survey of staff in June 2013 “saw marked improvements in staff morale and communication”.

Sickness absence for the financial year to the end of March 2013 was slightly down to about 9 days per full-time employee though up a little more recently.

Appendices – now for the problems

It’s only when councillors come to the report’s appendices that they will see some detail of the problems. But how many councillors will scrutinise a report’s appendices? From the Taunton report’s appendices:

“There are service and capacity issues. The helpdesk move caused significant problems, leading to an increased number of issues being raised with the Client Team from TDBC [Taunton Deane Borough Council] staff. We are closely monitoring the plan SWO [Southwest One] have put in place to fix these issues.

“Project delivery capacity and project scheduling continues to cause concern, with improved governance within TDBC highlighting this problem more acutely. Our issue tracker is currently tracking 11 escalated issues with SWOne, 6 of them with a Red RAG status.

“ SRM (Supplier Relationship Management) performance in SAP continues to be well below the required level despite the amount of focus it is receiving from SWOne. Work on a revised governance process for the SAP system is underway and looks likely to deliver a more controlled SAP Change process.”

The most serious problem – and it is not mentioned until the penultimate page of the report’s appendices – is that savings will be nowhere near the original target of £10m.

“This is red, tracked against the original [savings] £10m target. To date £2.8m has been signed-off and it is not yet clear how the lower target of £5.7m will be achieved as there are fewer savings opportunities and initiatives emanating from SWO…”

From the small print of Taunton Deane’s report it is possible to work out that the cost of the council’s SAP implementation was supposed to have been paid off by savings but hasn’t. Indeed a debt of nearly £1m is still incurring interest.

Comment

Perhaps it’s unfair to pick on Taunton Deane’s reports to councillors. The positive tone is little different to dozens, perhaps hundreds, of NHS, council and central government board reports I have read over two decades.

If you’re a director of a public authority your job is probably made harder if you’re getting self-vindicating internal reports on the organisation’s progress. It would be more helpful if management reports were neutral and objective, framed by unvarnished facts.

When you hire a roofing company and it reports back on the finished job, you want to know about the tiles that leave a gap or are loose, not the ones that fit nicely.

NHS trust reports can often be particularly one-sided, often of the type that say:

“We had 3 fatalities on the main staircase last month because of a ruptured floor lining but the overall accident rate in that part of the building is down over the last 3 years and our falls rate overall is 3% below the average for the NHS as a whole.

“Our contractor confirms that the floor lining is within KPI requirements and a repair will be effected shortly.”

It appears that those who write board reports for public authorities feel an obligation to motivate and inspire, to leave the reader feeling good, to clothe bad news in layers of good news, omit it altogether or put it in the appendix hardly anyone reads.

Is this one reason so many outsourcing and NHS scandals stay hidden for years? 

Will Universal Credit ever work? – NAO report

By Tony Collins

Today’s National Audit Office report Universal Credit: early progress is one of most excoriating the NAO has published on a government IT-enabled project or programme.

Iain Duncan Smith, secretary of state for work and pensions, has already responded to the NAO report by implying it is out of date and that the problems are in the past. This is a standard government response to well researched and highly critical NAO reports.

But the authors of the NAO report have pointed to some UC problems that are so fundamental that it may be difficult for any independent observer to credibly regard the project’s problems as historic. Says the NAO:

“The Department [DWP] is unable to continue with its ambitious plans for national roll-out until it has agreed the future service design and IT architecture for Universal Credit.”

So can the UC project ever be a success if, years after its start, there is no agreed design or IT architecture? Says the NAO

“The Department may also decide to scale back the complexity and ambition of its plans.”

Although the DWP has spent more than £300m on UC IT, mostly with the usual large IT suppliers, complex claims cannot yet be handled without manual work and calculations.

In February 2013, the Cabinet Office’s Major Projects Authority reviewed Universal Credit and raised “serious concerns about the programme’s progress”, says the NAO report. “The review team was concerned that the pathfinder [pilot project] could not handle changes in circumstances and complex cases which had to be dealt with manually, and that this meant the pathfinder could not be rolled out to large volumes.”

The Independent says the DWP gave false assurances on the project’s progress. The Daily Mail says the scheme has got off to a “disastrous start”.

The NAO’s main findings:

 Is £303m spent on IT value for money?

 “At this early stage of the Universal Credit programme the Department has not achieved value for money. The Department has delayed rolling out Universal Credit to claimants, has had weak control of the programme, and has been unable to assess the value of the systems it spent over £300m to develop [up to the end of March 2013].

“These problems represent a significant setback to Universal Credit and raise wider concerns about the Department’s ability to deal with weak programme management, over-optimistic timescales, and a lack of openness about progress.”

A projected IT overspend of £233m?

The NAO puts the expected cost of implementing Universal Credit to 2023 at £2.4bn. The spend to April 2013 is £425m, including £303m on the IT. The planned IT investment in the current spending review period from the May 2011 business case was £396m, but the December 2012 business case puts the planned IT investment in the current review period at £637m – and increase of £233m, or 60%. The DWP wants to make changes elsewhere in its budgets to accommodate the extra IT spend.

Ministers and DWP spokespeople have said repeatedly that the project is within budget.

Some of the IT spend breakdown

– Core software applications including a payment management component  – £188m

– Interface with HMRC real time information – £10m

– Case management module – £6m

– Licences – £31m

– Supplier support – £26m

– Hardware, telephony and changes to old systems – £50m

– Departmental staff costs on the Business and IT Solution team – £29m.

– Staff contractors provided by suppliers to support departmental staff  – £26m.

Main IT suppliers – spend to end of 2012/13

– Accenture. Software design, development and testing including: interview system; evidence capture, assessment and verification; and staff contractors – £125m

– IBM. Software design, development and testing including: real time earnings; process orchestration and payment management; and staff contractors – £75m

– HP. Hardware and legacy system software, and staff contractors – £49m

– BT. Telephony. It also supplied specialist advice on agile development methods – £16m

A further £9m was spent on live system support costs provided by HP; bringing total spending with suppliers to £312m, says the NAO.

 Is the IT high quality or not?

The NAO report suggests there may be conflicting views between those in DWP who believe the IT is high quality and others who are not so sure.

“The Department believes that the majority of the built IT is high quality, but has not been fully developed and cannot support scaling up the programme as it stands. Some assessments have commented that systems are inflexible or over-elaborate.”

Will the IT support a national roll-out?

The NAO says it’s uncertain that the IT can support full national roll-out of Universal Credit without further work and investment.

“The Department does not yet know to what extent its new IT systems will support national roll-out. Universal Credit pathfinder systems have limited function and do not allow claimants to change details of their circumstances online as originally intended. The Department does not yet have an agreed plan for national roll-out and has been unclear about how far it will build on pathfinder systems or replace them.”

Will timetable and scope have to change further?

“The Department will have to scale back its original delivery ambition and is re-assessing what it must do to roll-out Universal Credit to claimants. The current programme team is developing new plans for Universal Credit. Our experience of major programmes supported by IT suggests that the Department will need to revise the programme’s timing and scope, particularly around online transactions and automation.”

Over-optimism?

“It is unlikely that Universal Credit will be as simple or cheap to administer as originally intended. Delays to roll-out will reduce the expected benefits of reform…”

Rushed?

“ The ambitious timetable created pressure on the Department to act quickly…”

Open to fraud?

“The Department’s current IT system lacks the ability to identify potentially fraudulent claims. Within the controlled pathfinder environment, the Department relies on multiple manual checks on claims and payments. Such checks will not be feasible or adequate once the system is running nationally.

“Without a system in place, the Department will be unable to make the savings it had planned, by reducing overpayments from fraud and error. In December 2012, it estimated these savings to be worth £1.2 billion per year in steady state.”

Separately the NAO states that there have been “unanticipated security problems from putting transactions online”. The DWP may now scale back all that was planned to be online.

In January 2013 the technical director of CESG and other reviewers said that the UC security solution was “over-complex” and could have conflicted with DWP plans to encourage people to claim online.

Delay in national roll-out

“The Department has delayed rolling out Universal Credit nationally. The Department will not introduce Universal Credit for all new out-of-work claims nationally from October 2013 as planned. Instead it will add a further six pathfinder sites from October 2013

 “Pause UC immediately”

In early 2013 the Cabinet Office’s Major Projects Review Group noted that the Department had not addressed issues with governance, management and programme design despite their having been raised in previous reports. The Authority “recommended that the Universal Credit programme be paused immediately”.

All  post-2015 plans under review

The original plans were for UC roll-out to finish by late 2017. All statements by officials and Iain Duncan Smith have confirmed this 2017 deadline. In fact, says the NAO, all milestones beyond the start of 2015 are “currently under review” including:

• National roll-out of all new claims

• Closedown of tax credits new claims

• Roll-out of Pension Credit Plus on Universal Credit platform

• Completion of claimant migration

The NAO says the DWP has considered completing the roll-out beyond 2017.

Complete rethink needed

 The Cabinet Office’s Major Projects Authority reviewed and reported on Universal Credit in February 2013. The Authority’s found that:

“Universal Credit Programme needs a complete rethink of the delivery approach together with streamlining potentially over-elaborate solutions.”

A separate review of the project by Capgemini in January 2013 and a “Reset IT stocktake” in April 2013 concluded that the UC “architecture is of limited extensibility”.

Pathfinders of limited value

“The pathfinder lacks a complete security solution. Claimants cannot make changes in circumstances online. This increases the need for manual work as changes must be made by telephone. The pathfinders also require more staff intervention than planned, because of reduced automation and links between systems.”

100 day planning period

 “In May 2013, the Department appointed the current senior responsible owner [Howard Shiplee] to lead the Universal Credit programme. The team is now conducting a ‘100-day planning period’, which will end at the end of September 2013. The Department will then submit a new business case to HM Treasury, and ask for ministerial sign-off for delivery plans in late 2013.”

Secrecy – even internally?

“The reset took place between February and May 2013. The reset team included departmental, Cabinet Office and Government Digital Services staff. The reset team developed an extensive set of materials as part of a ‘blueprint’ covering design and implementation, and 99 detailed recommendations. The reset team shared the blueprint with the Department’s Executive Team who approved it at each stage of its development. The Department shared the blueprint with a small number of people but did not initially share it widely.”

A £34m write-off – so far

“The Department has acknowledged that it needs to write off some of the value of its Universal Credit IT assets. By the end of 2012-13, the Department had spent £303m on its IT systems and created assets which it valued at £196m – a difference of £107m. But the DWP has decided to write-off £34m – 17% – though it may increase the size of the write-off later.

“The Department is conducting further impairment reviews of the value of its Universal Credit IT assets before finalising its 2012-13 accounts.” The £34m write-off was based on a “self-assessment which it asked its suppliers to conduct”.

Number of claimants well below planned level

“In its October 2011 business case, the Department expected the Universal Credit caseload to reach 1.1 million by April 2014, but reduced this to 184,000 in the December 2012 business case.”

Planned savings down by nearly £500m

“The cost to government of implementing Universal Credit will be partly offset by administrative savings. In December 2012, the Department estimated that a three-month delay in transferring cases from existing benefits to Universal Credit would reduce savings by £240m in the current spending review period and by £247m after April 2015.”

 Anyone know who decided on October 2013 for planned UC roll-out?

 “The Department was unable to explain to us why it originally decided to aim for national roll-out from October 2013. It is not clear whether the Department gave decision-makers an evaluation of the relative feasibility, risks and costs of this target date.”

 Agile … with a 1,000-strong team?

“In 2010, the Department was unfamiliar with the agile methodology and no government programme of this size had used it. The Department recognised that the agile approach would raise risks for an organisation that was unfamiliar with this approach. In particular, the Department

• was managing a programme which grew to over 1,000 people using an approach that is often used in small collaborative teams;

• had not defined how it would monitor progress or document decisions;

• needed to integrate Universal Credit with existing systems, which use a waterfall approach to managing changes; and

• was working within existing contract, governance and approval structures.

“To tackle concerns about programme management, the Department has repeatedly redefined its approach. The Department changed its approach to ‘Agile 2.0’ in January 2012. Agile 2.0 was an evolution of the former agile approach, designed to try to work better with existing waterfall approaches that the Department uses to make changes to old systems.

“After a review by suppliers raised concerns about the achievability of the October 2013 roll-out the Department then adopted a ‘phased approach’ and created separate lead director roles for the pathfinder (phase 1), October roll-out (phase 2) and subsequent migration (phase 3).

“The Cabinet Office does not consider that the Department has at any point prior to the reset appropriately adopted an agile approach to managing the Universal Credit programme.”

Anyone know how UC is meant to work?

The source of many problems has been the absence of a detailed view of how Universal Credit is meant to work. The Department has struggled to set out how the detailed design of systems and processes fit together and relate to the objectives of Universal Credit.

“This is despite this issue having been raised repeatedly in 2012 by internal audit, the Major Projects Authority and a supplier-led review. This lack of clarity creates problems tracking progress, and increases the risk that systems will not be fit for purpose or that proposed solutions are more elaborate or expensive than they need to be…

“The Department was warned repeatedly about the lack of a detailed ‘blueprint’, ‘architecture’ or ‘target operating model’ for Universal Credit. Over the course of 2011 and the first half of 2012, the Department made some progress but did not address these concerns as expected.

“By mid-2012, this meant that the Department could not agree what security it needed to protect claimant transactions and was unclear about how Universal Credit would integrate with other programmes. These concerns culminated, in October 2012, in the Cabinet Office rejecting the Department’s proposed IT hardware and networks.

“ Given the tight timetable, unfamiliar programme management approach and lack of a detailed operating model, it was critical that the Department should have good progress information and effective controls. In practice the Department did not have any adequate measures of progress.”

High turnover among IT leaders?

“Including the reset and the current director general for Universal Credit, the programme has had five different senior responsible owners since mid-2012.

“The Department has also had high turnover in important roles other than the senior responsible owner. The Department has had five Universal Credit programme directors since 2010.”

The NAO said that the director of Universal Credit IT was “removed from the programme in late 2012 and the Department has replaced the role with several roles with IT responsibilities”. During and since the ‘reset’ the Government Digital Service has helped to redesign the systems and processes supporting transformation.

Good news culture and a fortress mentality

“The culture within the programme has also been a problem…Both the Major Projects Authority and a supplier-led review in mid-2012 identified problems with staff culture; including a ‘fortress mentality’ within the programme. The latter also reported there was a culture of ‘good news’ reporting that limited open discussion of risks and stifled challenge.”

“Inadequate control of suppliers”

The Department had to manage multiple suppliers. Three main suppliers – Accenture, IBM and HP – developed components for Universal Credit. The Department commissioned IBM to act as an Applications Development Integrator from January 2012, providing some oversight and overall management of IT development, but creating risks of supplier self-management.

The NAO found that there were inappropriate contractual mechanisms; charges were on the basis of time and materials, leaving the majority of risks with the Department. The NAO said there were “inadequate controls over what would be supplied, when and at what cost because deliverables were not always defined before contracts were signed.”

There was “over-reliance on performance information that was provided by suppliers without Department validation”. And weak contractual relationships with suppliers meant that the DWP “did not enforce all the key terms and conditions of its standard contract management framework, inhibiting its ability to hold suppliers to account”

Said the NAO:

“Various reviews have criticised how the Department has managed suppliers. In June 2012, CESG reported the lack of an agreed, clearly defined and documented scope with each supplier setting out what they should provide. This hampered the Department’s ability to hold suppliers to account and caused confusion about the interactions between systems developed by different ones. In February 2013, the Major Projects Authority reported there was no evidence of the Department actively managing its supplier contracts and recommended that the Department needed to urgently get a grip of its supplier management.”

Suppliers paid without proper checks

“The Department has exercised poor financial control over the Universal Credit programme. The Department commissioned an external review in early 2013 of financial management in Universal Credit. The review found several weaknesses including poor information about the basis for supplier invoices, payments being made without adequate checks and inadequate governance and oversight over who approved spending. The review team checked a sample of invoices against the timesheets of suppliers and found no evidence of inappropriate charging, although timesheet information is not complete and cannot be linked to specific activity…”

The NAO went on to emphasise that there was “insufficient review of contractor performance before making payments. “On average six project leads were given three days to check 1,500 individual timesheets, with payments only stopped if a challenge was raised.”

The NAO added that inadequate internal challenge of purchase decisions meant that ministers had “insufficient information to assess the value for money of contracts before approving them”.

50 people on the UC programme board

“The programme board acts as the programme’s main oversight and decision-making body… The programme board has been too large and inconsistent to act as an effective, accountable group. Over the course of 2012, the programme board had 50 different people attending as core members…

“The board did not have adequate performance information to challenge the programme’s progress. In particular, while the board had access to activity measures for IT system development, it could not track the actual value of this activity against spending.

“In the absence of such measures of progress, the board relied on external reviews to assess progress. Such external reviews were not sufficiently frequent for the board to use them as a substitute for timely, adequate management information.”

Programme board disbanded

 “… during the reset [Feb-May 2013], [the DWP] suspended the programme board entirely.

Failure to act on recommendations

“From mid-2012, it became increasingly clear that the Department was failing to address recommendations from assurance reviews… the key areas of concern raised by the Major Projects Authority in February 2013 had appeared in previous reports.

“From mid-2012, the underlying concerns about how Universal Credit would work meant that the Department could not address recommendations from assurance reviews; it failed to fully implement two-thirds of the recommendations made by internal audit and the Major Projects Authority in 2012. Without adequate, timely management information, the Department relied on periodic external assurance reports to assess progress.”

Ceasing work for national roll-out

“By late 2012, the Department had largely stopped developing systems for national roll-out and concentrated its efforts on preparing short-term solutions for the pathfinder…”

Slippery Parliamentary answers

The NAO lists almost imperceptible changes in the language of Parliamentary answers on Universal Credit.

In 2011 the DWP said in a Parliamentary answer that “all new applications” for out-of-work financial help would be treated as a UC claim; and in November 2012 the DWP said in a Parliamentary reply that in October 2013 it would start to migrate claimants from the old system to the new. But by June 2013 the DWP’s line had changed. By then it was saying in a Parliamentary reply that Universal Credit will “progressively roll-out” from October 2013 with all those who are entitled to UC claiming the new benefit by 2017. In fact all new applications for out-of-work help are not being treated as a UC claim. The NAO says that new claimants in the pathfinder must be “single, without children, newly claiming a benefit, fit for work, not claiming disability benefits, not have caring responsibilities, not be homeless or in temporary accommodation, and have a valid bank account and National Insurance number”.

Will UC ever work?

“ …it is still entirely feasible that it [UC] goes on to achieve considerable benefits for society. But to do so the Department will need to learn from its early mistakes.

“As it revises its plans the Department must show it can: exercise effective control of the programme; develop sufficient in-house capability to commission and manage IT development; set clear and realistic expectations about the timescale and scope of Universal Credit; and, address wider issues about how it manages risks in major programmes.”

**

Margaret Hodge MP, Chair of the Public Accounts Committee, says of the NAO report:

“The Department for Work and Pensions has made such a mess of setting up Universal Credit that the Major Projects Authority had to step in to rescue the programme.

“DWP seems to have embarked on this crucial project, expected to cost the taxpayer some £2.4bn, with little idea as to how it was actually going to work.

“Confusion and poor management at the highest levels have already resulted in delays and at least £34m wasted on developing IT. If the Department doesn’t get its act together, we could be on course for yet another catastrophic government IT failure.

“This damning indictment from the NAO gives me no confidence that we will see the £38 billion of predicted benefits between 2010-11 and 2022-23. Vulnerable benefit claimants need a secure system they can rely on.”

NAO report – Universal Credit: early progress

Why does truth on Universal Credit emerge only now?

By Tony Collins

For nearly a year the Department for Work and Pensions, its ministers and senior officials, have told Parliament that Universal Credit IT is on track and on budget.

Together with DWP press officers, they have criticised parts of the media and some MPs for suggesting otherwise.

Now the truth can be held back no longer: the National Audit Office is expected tomorrow to report on UC’s problems. Ahead of that report’s publication, and perhaps to take the sting out of it, work and pensions secretary Iain Duncan Smith has allowed Howard Shiplee, the latest DWP lead on delivery of UC, to own up to the project’s difficulties.

IDS has given permission for Shiplee to write an article for the Telegraph on the UC project. Every word is  likely to have been checked by senior DWP communications officers.

It’s the first time anyone on the UC project has publicly acknowledged the project’s difficulties though, as with nearly every government response to critical NAO reports, the administration depicts the problems as in the past. Shiplee’s article says

“… it’s also clear to me there were examples of poor project management in the past, a lack of transparency where the focus was too much on what was going well and not enough on what wasn’t and with suppliers not managed as they should have been.

“There is no doubt there have been missteps along the way. But we’ve put that right…

“I’m not in the business of making excuses, and I think it’s always important to acknowledge in any project where things may have gone wrong in order to ensure we learn as we go forward.

“To that end, the key decision taken by the Secretary of State to reset the programme to ensure its delivery on time and within budget has been critical.

“When David Pitchford arrived from the Major Projects Authority earlier this year, at the Secretary of State’s request, he began this process in line with those twin objectives…

“I’ve also ensured that as a programme we have a tight grip on our spending, and I have put in place a post for a new Director who will be dedicated to ensuring that suppliers deliver value for money. I am confident we are now back on course and the challenges are being handled.”

Parliament has a right to ask why nearly every central government IT project that goes wrong – whatever the government in power – is preceded for months and sometimes years in the case of the NPfIT by public denials.

From the over-budget and fragmented Operational Strategy project for welfare benefits in the 1980s, to the repeatedly delayed and over budget air traffic control IT at the New En Route Centre at Swanwick, Hampshire, and the abandoned Post Office “Pathway” project in the 1990s, to the failed National Programme for IT – NPfIT –  in the NHS in the last decade, ministers and senior officials were telling Parliament that all was well and that the project’s critics were misinformed. Until the facts became only too obvious to be denied any longer.

These are some of the reassurances ministers and DWP officials have been giving Parliament and the media about the UC project. None of their statements has given a hint of the  “missteps along the way” that Shiplee’s article refers to now.

House of Commons, 20 May 2013

Universal Credit (IT System)

Clive Betts (Lab): What assessment he [the secretary of state for work and pensions] has made of the preparedness of the universal credit IT delivery system.

Iain Duncan Smith: The IT system to support the pathfinder roll-out from April 2013 is up and running…

Betts: I thank the Secretary of State for that answer, but will he confirm that three of the pathfinders are not going ahead precisely because the computer system is not ready? …

Duncan Smith: The hon. Gentleman is fundamentally wrong. All the pathfinders are going ahead. The IT system is but a part of that, and goes ahead in one of the pathfinders. The other three are already testing all the other aspects of universal credit and in July will, essentially, themselves roll out the remainder of the pathfinder, and more than 7,000 people will be engaged in it. All that nonsense the hon. Gentleman has just said is completely untrue.”

**

BBC – 9 Sept 2012

 “A Department for Work and Pensions spokeswoman said: “Liam Byrne [Labour] is quite simply wrong. Universal Credit is on track and on budget. To suggest anything else is incorrect.”

**

Iain Duncan Smith, House of Commons, 20 May 2013

“This [Universal Credit] system is a success. We have four years to roll it out, we are rolling it out now, we will continue the roll-out nationwide and we will have a system that works—and one that works because we have tested it properly.”

Howard Shiplee – FT July 2013

“… Howard Shiplee, who has led UC since May, denied claims from MPs that the original IT had been ‘dumped’ because it had not delivered. ‘The existing systems that we have are working, and working effectively,’ he said. He added, however, that he had set aside 100 days ‘not to stop the programme, but to reflect on where we’ve got to and start to look at the entire total plan’.”

**

DWP spokesperson 16 August 2013

“… a DWP spokesperson said: “The IT supporting Universal Credit is working well and the vast majority of people are claiming online.”

**

Howard Shiplee Work and Pensions Committee, House of Commons, 10 July 2013.

“…The pathfinder, first of all, has demonstrated that the IT systems work…”

Mark Hoban, DWP minister, House of Commons, 6 March 2013.

The shadow Secretary of State has been touting this story for months. No it has been longer than that. The last outing was in today’s Guardian. I want to make it clear that nobody has walked off the project; all the contractors are in place and the project is on schedule to be delivered at the end of April. Now, if he thinks the idea is good in theory, it is about time he supported it. It is working and the contractors are in place, doing the job and ensuring that the pilots will be up and running at the end of April.”

[Hoban’s response was to a question on whether personnel or contractors at Accenture, Atos Origin, Oracle, Red Hat, CACI or IBM UK had been stepped down, or in any way notified by the Department, that they were to suspend work on Universal Credit. The main IT contractors for UC are Accenture, Hewlett Packard and BT plus input from Agile specialists Emergn. The DWP awarded UC IT contracts without any specific open competitive tender.]

Comment

On this site various posts have questioned whether Iain Duncan Smith has been getting the whole truth on the state of the UC IT project. He repeatedly went before MPs of the Work and Pensions Committee and gave such confident reassurances on the state of the UC project that it was difficult to believe that he knew what was really going on.

What we now know about the UC project’s “missteps along the way” shows, if nothing else, how gullible ministers are in believing their officials.

It is hard or impossible to believe that officials would lie but it is probable they would tell their ministers what they want to hear – and IDS has been in no mood to hear about problems.

Every big IT-based project in government that is failing ends up in a pantomime. From the back of the auditorium the media and MPs shout out when they receive leaks about problems. “Look behind you – there’s chaos,” they call out to departmental ministers and officials who don’t look behind them and reply “Oh no there isn’t!”

One reason this pantomime is repeated over decades is that independent reports on the progress or otherwise on big IT-based projects and programmes in central government are kept under departmental lock and key.  Even FOI requests for the keys consistently fail

So it’s usual for ministers and officials to answer media and Parliamentary questions about departmental projects without fear of authoritative contradiction.

Until the NAO is in imminent danger of publishing  a revealing report.

Perhaps it’s a lack of openness and accountability that contributes to IT-enabled change projects in central government going seriously awry in the first place.

With openness would come early and public recognition of a scheme that’s too ambitious to be implementable. With secrecy and the gung-ho optimism that seems to pervade projects like Universal Credit many on the project pretend to each other and perhaps even themselves that it’s all doable, while money continues to be thrown away.

When will the pantomime of misinformation and long-delayed revelation stop? Perhaps when Whitehall becomes genuinely open and accountable on the progress or otherwise of its IT-enabled projects. In other words: never.

Thank you to David Moss for drawing my attention to Howard Shiplee’s article in the Telegraph.

Time for truth on Universal Credit

Millions of pounds worth of secret DWP reports

Universal Credit IT working well claims DWP

By Tony Collins

Staff in job centres working on Universal Credit system are writing jobseekers’ personal information down on paper because their IT systems are so “clunky and cumbersome”, Dame Anne Begg, chair of the Commons’ Work and Pensions Committee, told Civil Service World.

“When we visited the Bolton Jobcentre Plus the IT system seemed clunky and cumbersome,” Begg said. Staff making appointments for UC applicants at the Bolton pilot scheme “had to write out some of the [jobseekers’] personal details, just to transfer them from one computer system to another. That’s something that we would have expected to be ironed out.”

The handwriting of jobseekers’ details “could lead to transposing errors”, she said.  Further, the Universal Credit IT system doesn’t allow jobseekers to save their data midway through an online application, Begg said.  She warned that this will penalise those who don’t own computers, who will have to remember to take all of their personal details in one batch to open access computers such as those at local libraries.

But a spokesperson for the Department for Work and Pensions said:

“The IT supporting Universal Credit is working well and the vast majority of people are claiming online. Making a claim to Universal Credit in one session… helps ensure the security of a claimant’s information.”

Last month a leaked survey of staff at the Department of Work and Pensions who are working on Universal Credit programme found dishonesty, secrecy, poor communications, inadequate leadership and low morale.

Computer Weekly reports that the DWP placed just 0.5% of its Universal Credit IT spending directly with SMEs, and that the department’s major suppliers – Accenture, Atos, BT, IBM, Capita, HP and SCC – subcontracted little to SMEs. “The Universal Credit supply chain flowed downstream mostly to multinational technology suppliers such as Oracle, Nuance, Genband and RedHat.” Most Universal Credit IT spending has gone to Accenture, IBM and HP: £57m, £41m and £34m respectively, between January 2011 and May 2013.]

Comment

While keeping secret internal reports on the Universal Credit IT project, and while all the signs are that Universal Credit’s IT is in trouble – it’s easier to handle claims at least in part by hand – the DWP’s senior officials, spokespeople and Iain Duncan Smith are telling the public and Parliament that all is well.

Perhaps the next logical step is that they come onto the public stage in costume to tell us nursery tales, while playing stock characters who sing, dance, and perform skits. Maybe then they’ll be more believable.

The story of Southwest One

By Tony Collins

Dave Orr worked in a variety of IT and project management roles for Somerset County Council and retired in 2010. For years he has campaigned with extraordinary tenacity to bring to the surface the truth over an unusual joint venture between IBM, Somerset County Council, a local borough council and the local police force.

Now he has written an account of the joint venture and the lessons. It is published on the website of procurement expert Peter Smith.

Orr questions whether Southwest One was ever a good idea, since it was formed in 2007.

The deal has not made the savings intended, a SAP implementation went awry, the contract has been mired in political controversy and criticism, Southwest One has repeatedly lost money, and many of the transferred staff and services have returned to the county council, and some services returned to the borough council. IBM and the county council have ended up in a legal dispute that cost the county council £5.5m to settle. Southwest One was not exactly the partnership it set out to be.

The contract may show how an outsourcing deal that doesn’t have the support of the staff being transferred is flawed fundamentally from the start (which is one reason few people will be surprised if a 10-year £320m deal for Capita to run Barnet Council’s new customer service organisation [NSCSO]  ends in tears).

These are some of Orr’s points:

–  Like other light-touch regulators, the Audit Commission repeatedly gave Southwest One positive reports, without ever qualifying the accounts, even as problems with SAP implementation mounted in 2009 and procurement savings were not being made in line with forecasts.

 – The contract called for transformation based upon ‘world-class technologies’, yet all of the IT Service was placed into Southwest One with no IT expertise back in the Somerset County client (until after a poor SAP implementation in 2009). Was the lack of retained IT skills in the Somerset County client behind the formal acceptance of a badly configured SAP implementation?

– Large scale outsourcing over a long contract of 10 years or more requires an ability to foresee the future that is simply not possible to capture in a fixed contract. In a 10-year contract, there will be three changes of national government and three changes of local government. That is a great deal of unpredictable change to cope with via a fixed, long-term contract.

– Local Government will always be at a disadvantage in resources and skills, to a large multi-national contractor like IBM, when it comes to negotiating, letting and managing a complex multi-service contract.

– What was the culture of Southwest One (75% owned by IBM)? Was it private, public or a hybrid? The management culture remained firmly IBM, yet the councils and police workforces were seconded and remained equally firmly public sector rooted. There is such a thing as a public service ethos. In fact, Southwest One was run like a mini-IBM based upon global divisions, complete with IBM standard structures and processes. Southwest One seconded employees were not allowed anything like a full access to IBM internal systems, thus creating additional complexity, as “real” IBM employees relied entirely upon on-line systems.

–  Mixed teams in a single shared service were hard to amalgamate. This meant the IBM managers of Southwest One never really gained the sort of command & control of the multi-tier workforces that their bonus-oriented model needs to function. “I doubt that IBM would ever again contemplate the seconded staff model over the TUPE transfer model,” says Orr.

– Somerset County Council ran with a “thin” client management team that, in Orr’s view, did not have sufficient expertise or enough staff resources to effectively manage this complex contract with IBM. The councils relied upon definitions of “partnership” that meant one thing to the councils’ side and quite another thing to IBM, says Orr.

– In Southwest One, Somerset County Council handed their entire IT Service over lock, stock and barrel. “Can you really consider IT as wholly a ‘back office’ service? Many successful private Companies see IT as a strategic service to be kept under their own control.”

– The real savings might have been found in optimising processes in big departments (like Social Care, Education, Highways) that lay outside of Southwest One’s reach. “The focus on IT rather than service processes was another flaw in the model.”

Orr  concludes that nobody who played a major part in the Southwest deal has in any way been held to account for what has gone wrong.

Southwest One – the complete story from Dave Orr

Universal Credit – good for its IT suppliers?

By Tony Collins

The DWP is conceding in its own tangential way that the IT for Universal Credit is not up to scratch; and an article in the Daily Telegraph suggests that Universal Credit this year (and perhaps well beyond) will handle so few claimants that the calculations for the time being could be done by hand, or on a spreadsheet, and not automatically by IT systems. The Register, through anonymous sources, has confirmation of this.

The FT says there will be a progressive national rollout of the coalition’s welfare reform in just six additional jobcentres which it said was the “latest sign the project is falling behind schedule”. It added that a significant shake-up of the IT underpinning universal credit is under way. 

The DWP said David Pitchford, the Whitehall troubleshooter who took over the running of Universal Credit for three months, had been asked to “review” the IT and ministers had “accepted his recommendation that they should explore enhancing the IT for universal credit working with the government digital service”.

“Advancements in technology since the current system was developed have meant that a more responsive system that is more flexible and secure could potentially be built,” said the DWP.

The FT quoted Howard Shiplee, who has led the Universal Credit  project since May, as denying claims from MPs that the original IT had been dumped because it had not delivered. “The existing systems that we have are working, and working effectively,” he said.

He added that he had set aside 100 days not to stop the programme, but to reflect on where it has got to and start to look at the entire total plan.

Iain Duncan Smith, the work and pensions secretary, doesn’t concede that the  timetable for the implementation of Universal Credit has changed. He told the work and pensions committee on Wednesday that numbers of claimants would ramp up during 2014 and he insisted that all claimants would be on the system by 2017, as originally planned.

“We get fixated on things like IT; the reality is it’s about a cultural shift,” Duncan Smith told MPs.

Comment

Iain Duncan Smith makes it clear that his DWP staff and suppliers, with the help of HMRC, are implementing Universal Credit with extreme care. Labour’s  work and pensions spokesman Liam Byrne says the Universal Credit project is a shambles. The truth is hard to fathom.

For years the DWP has rejected press reports that the IT for Universal Credit was in trouble. It is able to do without fear of authoritative contradiction because it keeps secret all its consultancy reports on the state of the Universal Credit project, despite FOI requests.

The Cabinet Office minister Francis Maude and his officials talk much about the need for openness and transparency. Isn’t it time they persuaded DWP officials to release their internal and external reports on the detailed challenges faced by suppliers and civil servants on Universal Credit and other major government IT projects?

All big government IT projects are characterised by secrecy and defensiveness, although a little information about them is in the vague and subjectively-worded Major Projects Authority annual report.

One by-product of departmental defensiveness and secrecy is that the IT suppliers – in Universal Credit’s case HP, IBM and Accenture – are likely to continue to be paid even if the project is halted and redesigned. It’s probable the suppliers would argue that they have successfully done what they were asked to do in the contract. Who knows what the truth is?

The DWP is in effect protecting its suppliers from public and parliamentary scrutiny. It has been this way for decades and nothing has changed.

Report on status of big Gov’t projects to be published at last

By Tony Collins

The Telegraph reports that the Cabinet Office’s Major Projects Authority is about to publish its first annual report – and it will reveal the status of schemes that include Universal Credit, says the article.

The Cabinet Office said in 2011 that the MPA’s annual report would be published by the end of December that year. In 2012 Sir Bob Kerslake, head of the civil service, told the Public Accounts Committee’s Conservative MP Richard Bacon that the MPA’s annual report would be published in June 2012.

But senior departmental  civil servants have objected repeatedly to the red-amber-green “traffic light” status of projects being published, which contradicts the wishes of Kerslake and Francis Maude, the Cabinet Office minister.

One reason for the delay in publishing the MPA annual report is that Maude and Kerslake have been weighing objections to the reporting of the red-amber-green status against the need for departmental cooperation to implement civil service reforms.

From the Telegraph article it appears that Maude has persuaded (or forced) departmental heads to accept the publication of the traffic light status on big and risky projects. The Major Projects Authority reviews IT and other projects costing more than £50m.

The Telegraph says the MPA annual report will reveal Government troubleshooters’ concerns about multi-billion pound projects like the Universal Credit.

The article says the MPA annual report will show that about a third of projects it has reviewed are late or over budget. Says the Telegraph: “Government sources said that the MPA will show that management of big projects has improved significantly since 2010, when two-thirds of programmes were in trouble.

“But the report, expected later this month, will confirm that Whitehall ‘still has a long way to go’ to improve its handling of major projects, a source said.”

The article adds that publication of the annual report “follows a lengthy internal struggle between ministers and civil servants about the disclosure of problems with big Government schemes”.

Some ministers, says the article, are privately concerned that civil servants are bad at managing big, expensive projects but repeatedly cover up their failings and refuse to tell ministers about problems.  Disclosing “candid” assessments about big projects will improve management, ministers believe.

The Telegraph says that a “new publication scheme that will start later this month” will publicly rate each project at red, amber, or green. 

Each central department will be told to publish details of its major projects every six months, including the red-amber-green ratings and the data behind them, says the article.

The Telegraph quotes as a coalition source as saying: “Releasing a candid report about Whitehall’s major projects is a big and brave step for Government…”

Management of big projects better but still generally poor? 

Lord Browne, a lead non-executive in the Cabinet Office and the man appointed to recruit business leaders to Whitehall departmental boards, has criticised the management of major projects as “worryingly poor”.

He said that insufficient attention was given to identifying risks in the planning stage, and that there had been a “consistent failure” to appoint leaders with the right skills and experience.

Browne said the creation of the Major Projects Authority (MPA) in the Cabinet Office in 2011 had improved their delivery, but “nobody ever intervenes in a poor project soon enough” and that warning signs were often ignored or under-reported.

He called for an “ongoing and rigorous review process with real teeth” which would monitor measures of progress and call “time out” on failing projects, allowing them either to be fixed or stopped.

Browne said the government could learn from the private sector, where projects are scrutinised to a “very high standard” before work begins. In line with this, he suggested that the MPA should have a strengthened “stage-gate approval process” to ensure that projects achieve objectives.

He said that projects should not be allowed to begin until a team with the right skills – including a leader who had previously delivered a large, complex project – had been identified.

He also suggested that the MPA nominate leaders and veto unsuitable candidates. He said that expensive projects should “never be seen as a personal development opportunity”.

He advocated using pay, benefits and bonuses to give team members incentives to work on the project “until appropriate milestones are reached”. This, Browne said, had been key to the success of major projects delivered by the private sector.

Departments still sceptical of Maude’s reforms?

Meanwhile the FT has reported that Maude’s attempts to inject commercial acumen into Whitehall by putting leading business figures on departmental boards is failing to live up to its billing, with some departments rarely consulting their external non-executive directors.

The FT says that the Treasury department’s supervisory board met only once in the year to April 2012, according to a report by Insight Public Affairs, a consultancy. The energy department’s board met twice, compared to 15 meetings in the transport department, reflecting the inconsistent involvement of non-executive directors.

John Lehal, managing director of Insight Public Affairs, said the ad hoc manner in which departments held board meetings reflected the need for greater accountability – as underlined by the Treasury’s failure to engage its non-executives.

Comment

At long last the Major Projects Authority, under the straight-talking Australian David  Pitchford, will publish its annual report; and it may contain more detail on major projects than has been published by any government.

As departments fear public embarrassment more than any other sanction, publication of the traffic light status of projects – with the underlying detail – should genuinely discourage the starting of ill-considered projects.

Although the MPA annual report is much delayed Maude has succeeded in getting agreement for it to be published. Provided it contains enough detail to allow the status of projects to be judged by armchair auditors, it should begin to make a real difference.

Telegraph article

Another Universal Credit leader stands down

By Tony Collins

Universal Credit’s Programme Director, Hilary Reynolds, has stood down after only four months in post. The Department for Work and Pensions says she has been replaced by the interim head of Universal Credit David Pitchford.

Last month the DWP said Pitchford was temporarily leading Universal Credit following the death of Philip Langsdale at Christmas. In November 2012 the DWP confirmed that the then Programme Director for UC, Malcolm Whitehouse, was stepping down – to be replaced by Hilary Reynolds. Steve Dover,  the DWP’s Corporate Director, Universal Credit Programme Business, has also been replaced.

A DWP spokesman said today (11 March 2013),

“David Pitchford’s role as Chief Executive for Universal Credit effectively combines the Senior Responsible Officer and Programme Director roles.  As a result, Hilary Reynolds will now move onto other work.” She will no longer work on UC but will stay at the DWP, said the spokesman.

Raised in New Zealand, Reynolds is straight-talking. When she wrote to local authority chief executives in December 2012, introducing herself as the new Director for the Universal Credit Programme, her letter was free of the sort of jargon and vague management-speak that often characterises civil service communications.  It is a pity she is standing down.

Some believe that Universal Credit will be launched in such a small way it could be managed manually. The bulk of the roll-out will be after the next general election, which means the plan would be subject to change. Each limited phase will have to prove itself before the next roll-out starts.

Reynolds’ letter to local authorities suggests that the roll-out of UC will, initially, be limited.  She said in her letter,

“For the majority of local authorities, the impact of UC during the financial year 2013/14 will be limited. .. Initially, UC will replace new claims from single jobseekers of working age in certain defined postcode areas.

“From October 2013 we plan to extend the service to include jobseekers with children, couples and owner-occupiers, gradually expanding the service to locations across Great Britain and making it available to the full range of eligible working age claimants …by the end of 2017.”

Some IT work halted? 

Accenture, Atos Origin, Oracle, Red Hat, CACI and IBM UK have all been asked to stop work on UC, according to shadow minister Liam Byrne MP, as reported on consultant Brian Wernham’s blog.

Wernham says that Minister Mark Hoban did not rebut Byrne’s statement but said that HP was committed to carrying on with the project. HP is responsible for deployment of a solution, not development, says Wernham’s agile government blog.

Comment

The DWP says that Pitchford has taken over from Reynolds – but separately the DWP had confirmed that Pitchford was leading UC temporarily and that Reynolds had a permanent job on the programme. Pitchford’s usual job is running the Major Projects Authority in the Cabinet Office.

All the changes at the DWP, and the reported halting of work by IT contractors, imply that the UC project is proving more involved, and moving more slowly,  than initially thought. It’s also a reason for the DWP to continue to refuse FOI requests for internal reports that assess the project’s progress.

Perhaps the DWP doesn’t want people to know that the project is on track for such a limited roll-out in October that it could be managed, in the main, by hand. With the bulk of the roll-out planned for after the next general election Labour may be denied the use of UC as an effective electoral weapon against the Conservatives. In other words, the riskiest stage of UC is being put off until 2016/17.

 Francis Maude, who is worried that UC will prove an IT and electoral disaster, has his own man, David Pitchford, leading the project, if only temporarily. Meanwhile UC project leaders from the DWP continue to last an extraordinarily short time. Reynolds had been UC programme director for only four months when she stood down. Pitchford is in a temporary role as the programme’s head, and Andy Nelson has recently become the DWP’s Chief Information Officer.

So much for UC’s continuity of leadership.

The truth about the project hasn’t been told. Isn’t it time someone told Iain Duncan Smith what’s really happening – Francis Maude perhaps?

Cornwall Council rushes to sign BT outsourcing deal before elections

By Tony Collins

Cornwall council logoCornwall Council was a model of local democracy in the way it challenged and then rejected a large-scale outsourcing plan. Now it has gone to the other extreme.

Amid extraordinary secrecy the Council’s cabinet is rushing through plans to sign a smaller outsourcing contract with BT – a deal that will include IT – before the May council elections.

Councillors who have been given details are not allowed to discuss them. No figures are being given on the costs to the council, or the possible savings. The Council’s cabinet is not releasing information on the risks.

Councillors are being treated like children, says ThisisCornwall. Documents with details of the BT outsourcing plans have to be handed back by councillors, and cabinet papers are being printed individually with members’ names as a watermark, on every page, to guard against copying and to help identify any whistleblowers.

The council’s Single Issue Panel has a timetable for the IT outsourcing plan.

– Recommendation to Cabinet to approve release of ITT – 27 February 2013

– Evaluation of bid – March 2013

– If contract awarded, commencement of implementation work – April 2013

– Staff transfer date – July 2013

The SIP report emphasises that the timetable for signing a deal is tight. “Evidence received is that there is little room for slippage in the timetable, but that potential award of contract is achievable by the end of March 2013… It is expected that a contract could be ready to be issued as part of the ITT [invitation to tender] pack by early in the week commencing 4 March 2013.”

The SIP report concedes that the plan is “fast moving”.

In the past, the SIP group of councillors has been open and challenging in its reports on the council’s plans with BT (and CSC before the company withdrew from negotiations). Now the SIP’s latest report is vague and unchallenging. The risks are referred to in the report as a tick-box exercise. Entire paragraphs in the SIP report appear to have little meaning.

“Risk log and programme timelines are reviewed and updated on a regular basis… 

“The Council and health partners have been working on and have reached agreement on their positions in relation to commercial aspects in the contract and their expectations have been part of the dialogue with BT.”

“Previous concerns of the Panel relating to the area of new jobs have been addressed with BT in contract discussions and contract clauses have been revised to reflect this…”

It is also unclear from the SIP report why the council is outsourcing at all, only perhaps a hint that the deal will be value for money.

“The contract will be fully evaluated by the Head of Finance and her team to ensure value for money once the final bid is received. No savings have been assumed for 2013/14 budgetary purposes, although there are assumptions of savings for the indicative figures for future years,” says the SIP report.

Comment

It is a pity that Cornwall Council’s cabinet is rushing to sign a deal for which it won’t be accountable if things go wrong. In a few weeks a new council will be voted in and, if the outsourcing deal with BT ends up in a dispute or litigation, the new council will simply blame the old, as happened when Somerset County Council’s joint venture deal with IBM, Southwest One, went into dispute.

In essence, with the local elections only two months away, Cornwall Council’s cabinet has a freedom to make whatever decision it likes with impunity; and it appears to be taking that freedom to an extreme, almost to the point of sounding, in the latest SIP report, as if the council is an arms-length marketing agent of BT.

Cornwall Council’s cabinet has a mandate from the full council to move to a contract with BT. The full council has voted to “support” a deal. But that vote was a mandate to negotiate, not to sign anything BT wants to sign.

Openness has gone out of the window and BT, it seems, is no longer being rigorously  challenged – by Cornwall’s cabinet, the full council, the public or the media.

How exactly can BT guarantee jobs and make savings? We don’t know. The Cabinet isn’t saying, and its members are doing all they can to stop councillors saying.

Are BT’s promises reliant on the fact that IT is subject to constant and sometimes costly change – often unforeseen change – and that is bound to continue, at least in the form of supporting changing legislation and reorganisations?

Unforeseen changes could add unforeseen costs which the council may have to pay because IT is at the heart of business continuity.  In any dispute with the council  – and BT knows its way around the world of contested contracts – the company would have the upper hand because of its experience with litigation and the fact that the council would need undisrupted IT at a time of change and could not afford, without risk, to take the service back in-house.

We have seen how normality broke down at Mid Staffs NHS Foundation Trust amid a lack of openness and excessive defensiveness;  and we have seen, in Somerset County Council’s joint venture with IBM, Southwest One, what can happen when a contract signing is rushed.

Cornwall Council’s cabinet is doing both. It is rushing to sign a contract; and it is rushing to sign it amid excessive secrecy.

Surely Cornwall Council can do better than slip into the shadows to sign a deal with BT before the council elections in May?  If it is such a good deal, the new council will want to sign it. A new council should have the chance to do so.

For Cornwall Council to outsource now what is arguably its single most important internal resource – IT – is bad for local democracy: it is snub to anyone who holds true the idea that local councillors are accountable to local people.

Thank you to campaigner Dave Orr who drew my attention to information that made this post possible.

* Cornwall Council, by the way, has one of the best local authority websites I have seen.  If the website is a reflection of the imagination and efficiency of its IT department, Cornwall Council should be selling its IT skills to BT for a small fortune – not giving staff away.