Category Archives: FOI

DWP tries anew for leave to appeal FOI ruling on Universal Credit reports

By Tony Collins

The DWP is continuing its protracted legal fight to stop publication of four reports on the Universal Credit programme.

The department this week asked the upper tribunal for leave to appeal a decision of the first-tier information tribunal that the four reports be published.  The first-tier tribunal had refused the DWP leave to appeal.

As expected, the DWP is doing everything possible within the FOI Act to stop the UC programme reports being published. This is despite MPs on the Work and Pensions Committee saying there is a “lack of transparency” on the Universal Credit programme.

The reports in question are more than two years old but they would show how much ministers knew about UC programme problems at a time when the DWP was issuing regular press releases claiming the scheme was on time and to budget.

By law the DWP has to deal with every FOI request individually but in practice the department has rejected every FOI request for reviews and assessments of its major IT-enabled projects and programmes including Universal Credit.

The four reports in question are:

– A project assessment review on the state of the UC programme in November 2011, as assessed by the Cabinet Office’s Major Projects Authority.

– A risk register of possible risks to the development or eventual operation of UC as perceived by those involved.

– An issues register of problems that have materialised, why and how they can be minimised or eliminated.

– A milestone schedule of progress and times by which activities should be completed.

In his request to the upper tribunal for leave to appeal the first-tier tribunal’s decision, the DWP’s lawyer  argues that the first-tier tribunal wholly misunderstood the nature of any “chilling effect” that publishing the reports would have on the frankness of civil servants contributing to them.

He said that the tribunal’s finding that disclosure of the reports would have no chilling effect was “perverse”, and that the tribunal failed to give due weight to the evidence of a senior civil servant Sarah Cox on the chilling effect.

He said that “many ex-ministers and others have spoken of the chilling effect of disclosure as an observable phenomenon within government” though he provided no evidence of this in his submission.

He added that the first-tier tribunal’s reasoning was “defective” in a number of respects. The tribunal had made a fundamental error of law, he said.

The tribunal’s “factual conclusion that disclosure of the disputed information would have no chilling effect whatsoever was one which no reasonable tribunal, properly directing itself as to the relevant legal principles, could have reached,” said the DWP’s lawyer.

Judge refuses DWP leave to appeal FOI ruling on Universal Credit reports

 

Why the DWP wants Universal Credit reports kept secret

By Tony Collins

Yesterday the Department for Work and Pensions, via Andrew Robertson, a lawyer in the Treasury Solicitor’s Department, issued the grounds for its appeal against an Information Tribunal ruling that four reports on Universal Credit be released.

The four reports in question are:

– A project assessment review on the state of the project in November 2011, as assessed by the Cabinet Office’s Major Projects Authority.

– A risk register of possible risks to the development or eventual operation of UC as perceived by those involved.

– An issues register of problems that have materialised, why and how they can be minimised or eliminated.

– A milestone schedule of progress and times by which activities should be completed.

The DWP keeps losing appeals to stop the reports being published– but public money being no object when it comes to justifying departmental secrecy, it keeps spending on appeals. The latest appeal is to the “Upper Tribunal”. A decision on whether the appeal can go to the Upper Tribunal will come shortly from the “First-tier” tribunal.

The DWP says its main grounds for appeal is that the Information tribunal “wholly misunderstood the nature and/or manifestation of any ‘chilling effect’. [The chilling effect suggests that public servants will not tell the whole truth in project reviews if they know the reports will be published. The counter argument is that it is the job and duty of public servants to tell the truth, which they are more likely to do if the reports are published and they could be held accountable if it transpires later they had not told the whole truth.]

The DWP said the Tribunal’s misunderstanding about the chilling effect “amounted to an error in law” and was “perverse”.

The DWP’s appeal document is here: Application for Permission to Appeal & Grounds of Appeal 16.04.14 (as fi…

Comment:

The DWP’s appeal document shows the ease with which its lawyers could credibly argue – with an entirely straight face – that day is night, and night is day, on the basis that daylight in one part of the world always signifies darkness in another part of the world.

The DWP’s lawyers could also credibly argue that black is white, and white is black, on the basis that colour is simply a perception based on the light reflected back to our eyes and that if an object can reflect back all the light we see it is white, and black will be perceived only superficially since it is necessary to doubt everything when assessing the world from a fresh perspective, clear of any preconceived notions.

It is in this Orwell-parodying vein that the DWP’s lawyers argue that four Universal Credit reports need to be kept secret. Below are 2 extracts from the DWP’s appeal document. Anyone who understands what either of these paragraphs means deserves a prominent place in the DWP legal team. Here’s a clue. Having read the paragraphs below three times I think they’re saying that it is difficult to prove whether a leaked document has had a chilling effect.

Says the DWP appeal:

“Any argument as to the ‘chilling effect’ of disclosure is necessarily speculative, because it makes assumptions about the future effect of an event that has not yet occurred (i.e. the future effect of disclosure of particular information). Any argument as to the ‘chilling effect’ of disclosure in the past of any ‘chilling effect’ is likely to be the assertion of persons whose experience in particular working environments has enabled them to assess and evaluate how candour and frankness may alter, or may have altered, in the light of premature disclosure of information…”

Here’s another excruciating extract from the DWP’s appeal document:

“The Tribunal’s assumption that it would be ‘quite easy to assemble’ a ‘before’ and ‘after’ documentary comparison itself exemplifies its erroneous understanding of how a ‘chilling effect’ can be proved. Far from being easy, it would in the majority of cases be impossible to demonstrate that a particular type of document had changed fundamentally as a result of disclosure. That is because the likely effect of disclosure will very probably not be a change in the form in which a document (such as a risk register) is produced. It will rather be a change in the substantive content of the register, as a result of a conscious or subconscious decrease in the candour of those contributing to it. But it will equally be impossible to show what those contributors might have said, had it not been for disclosure: because they will not, in fact, have said it.”

Jonathan Swift, in perhaps the best satirical book of all time, Gulliver’s Travels, described lawyers as a society of men “bred up from their youth in the art of proving by words multiplied for the purpose, that white is black, and black is white, according as they are paid”.

It’s not that the DWP’s lawyers lie. They don’t need to. This latest appeal is a legal nicety, a way of stringing things out, a display of conformance with the FOI game. Nothing will convince the DWP that it should publish the UC reports in question. Nothing will convince the DWP that it should publish any of its reports on any of its major IT-related projects or programmes.

If they need to, Iain Duncan Smith or Lord Freud, his minister, will simply sign a ministerial veto preventing publication of the UC reports under the FOI Act. If there is a legal challenge to the veto, as with the veto on the release of Prince Charles’ letters, IDS will be pleased to have the matter kicked into touch; and while the legalities stretch out over years the UC reports will continue to moulder in locked DWP cupboards.. Eventually they may be released – when they are so old nobody will care what they say. Or they will have disintegrated ( and no, the DWP doesn’t always keep its most secret reports electronically).

That’s what open government means to the DWP… precisely nothing.

Millions of pounds of secret DWP reports

Judge rules that key Universal Credit reports should be published

DWP throws money at keeping Universal Credit reports secret

Too much dishonesty and secrecy over Universal Credit project?

DWP criticised for “worrying” secrecy

DWP refused to release Universal Credit report to MPs

“Outrageous” secrecy at DWP (2005) 

MPs criticise secrecy in DWP IT probe (2004)

Judge rules that key Universal Credit reports should be published

By Tony Collins

A freedom of information tribunal has ruled that the Department for Work and Pensions should disclose four internal documents on the Universal Credit programme.

The documents give an insight into some of the risks, problems and challenges faced by DWP directors and teams working on UC.

They could also provide evidence on whether the DWP misled Parliament and the public in announcements and press releases issued between 2011 and late 2013.

The DWP and ministers, including the secretary of  state Iain Duncan Smith, declared repeatedly that the UC scheme was on time and on budget at a time when independent internal reports – which the DWP has refused to publish – were highly critical of elements of management of the programme.

Some detail from the internal reports was revealed by the National Audit Office in its Universal Credit: early progress in September 2013.

The FOI tribunal, under judge David Farrer QC, said in a ruling on Monday that in weighing the interest in disclosure of the reports “we attach great importance not only to the undisputed significance of the UC programme as a truly fundamental reform but to the criticism and controversy it was attracting by the time of FOI requests for the reports in March and April 2012”.

It added:

“We are struck by the sharp contrast [of independent criticisms of elements of the UC programme]  with the unfailing confidence and optimism of a series of press releases by the DWP or ministerial statements as to the progress of the Universal Credit programme during the relevant period.”

A measure of the importance of the tribunal hearing to the DWP was its choice of Sarah Cox to argue against disclosure.

Cox is now the DWP’s Director, Universal Credit, Programme Co-ordination.

She led business planning and programme management for the London Organising Committee of the Olympic and Paralympic Games.

Despite Cox’s arguments Judge Farrer’s tribunal decided that the DWP should publish:

– A Project Assessment Review of Universal Credit by the Cabinet Office’s Major Projects Authority. The Review gave a high-level strategic view of the state of UC, its problems, risks and how well or badly it was being managed.

– A Risk Register of Universal Credit. It included a description of the risk, the possible impact should it occur, the probability of its occurring, a risk score, a traffic light [Red/Green Amber] status, a summary of the planned response if a risk materialises, and a summary of the risk mitigation.

– An Issues Register for Universal Credit. It contained a short list of problems, the dates when they were identified, the mitigating steps required and the dates for review and resolution.

– A High Level Milestone Schedule for Universal Credit. It is described in the tribunal’s ruling as a “graphic record of progress, measured in milestones, some completed, some missed and others targeted in the future”.

Campaign for openness

Campaigners have tried unsuccessfully for decades to persuade Whitehall officials to publish their independent reports on the progress or otherwise of big IT-enabled projects and programmes.

So long as the reports remain confidential, ministers and officials may say what they like in public about the success of the programme without fear of authoritative contradiction.

This may be the case with the Universal Credit. The tribunal pointed out that media coverage of the problems with the scheme was at odds with what the DWP and ministers were saying.

The ruling said:

 “Where, in the context of a major reform, government announcements are so markedly at odds with current opinion in the relatively informed and serious media, there is a particularly strong public interest in up-to-date information as to the details of what is happening within the [Universal Credit] programme, so that the public may judge whether or not opposition and media criticism is well-founded.”

The tribunal quoted a DWP spokesperson in 2012 as refuting criticism from the shadow secretary of state. The spokesperson said:

Liam Byrne is quite simply wrong. Universal Credit is on track and on            budget. To suggest anything else is wrong.”

 Sarah Cox implied that the DWP might have regarded a programme as on schedule, even if milestones were not achieved on time, provided that punctual fulfillment of the whole project was still contemplated. In reply to this, the Tribunal said:

 “If that was, or indeed is, the departmental stance, then the public should have been made aware of it, because prompt completion following missed interim targets is not a common experience.”

DWP abuse of the FOI Act?

Under the FOI Act ministers and officials are supposed to regard each request on its own merits, and not have a blanket ban on, say, disclosure of all internal reports on the progress or otherwise of big IT-enabled change programmes.

The tribunal in this case questioned whether the DWP had even read closely the Project Assessment Review in question. The tribunal had such doubts because the DWP, some time after the tribunal’s hearing, found that it had mistakenly given the tribunal a draft of the Project Assessment Review instead of the final report.

The tribunal said:

“…the DWP discovered that the version of the Project Assessment Review supplied to the Tribunal was not the final version which had been requested. It was evidently a draft. How the mistake occurred is not entirely clear to us.

“ Whilst the differences related almost entirely to the format, it did raise questions as to how far the DWP had scrutinised the particular Project Assessment Review requested, as distinct from forming a generic judgement as to whether PARs should be disclosed.”

DWP’s case for non-disclosure

The DWP argued that disclosure would discourage candour, imagination [which is sometimes called creative or imaginative pessimism] and innovation – known together as the “chilling effect”.

It also said that release of the documents in question could divert key staff from their normal tasks to answering media stories based on a misconception, willful or not. These distractions would seriously impede progress and threaten scheduled fulfillment of the UC programme.

Disclosure could embarrass suppliers that participated in the programme, damage the DWP’s relationship with them, and cause certain risks to come closer to being realised. The DWP gave the tribunal further unpublished – closed – evidence about why it did not want the Project Assessment Review released.

My case for disclosure

In support of my FOI request – in 2012 – for the UC Project Assessment Review, I wrote papers to the tribunal giving public interest reasons for disclosure. Some of the points I made:

– the DWP made no acknowledgement of the serious problems faced by the UC programme until the National Audit Office published its report in September 2013: Universal Credit: early progress.

– Large government IT-enabled projects have too often lacked timely, independent scrutiny and challenge to improve performance. Publication of the November 2011 Project Assessment Review would have been a valuable insight into what was happening.

– The NAO report referred to the DWP’s fortress mentality” and a “good news culture” which underlined the public interest in early publication of the Project Assessment Review.

Part of John Slater’s case for disclosure

At the same time as dealing with my FOI request for the PAR, the tribunal dealt with FOI requests made by John Slater who asked for the UC Issues Register, Risk Register and High Level Milestone Schedule.

In his submission to the tribunal Slater said that ministerial statements and DWP press releases, which continued from 2011 to late 2013, to the effect that the Universal Credit Programme was on course and on schedule, demanded publication of the documents in question as a check on what the public was being told.

Information Commissioner’s case for disclosure

The Information Commissioner’s legal representative Robin Hopkins made the point that publishing the Project Assessment Review would have helped the public assess the effectiveness of the Cabinet Office’s Major Projects Authority as a monitor of the UC programme.

A chilling effect?

The tribunal found that there is no evidence to support the “chilling effect” –  the claim that civil servants will not be candid or imaginatively pessimistic in identifying problems and risks if they know their comments will be published.

If a chilling effect exists, said the tribunal, “then government departments have been in the best position over the last ten years to note, record and present the evidence to prove it.

“Presumably, a simple comparison of documents before and after disclosure demonstrating the change, would be quite easy to assemble and exhibit,” said the tribunal’s ruling.

In her evidence to the tribunal Ms Cox did not suggest that the revelation by a third party of the “Starting Gate Review” [which was published in full on Campaign4Change’s website] had inhibited frank discussion within the UC programme, the tribunal said.

The tribunal also pointed out that the public is entitled to expect that senior officials will be, when helping with internal reports, courageous, frank and independent in their advice and assessments of risk.

“We are not persuaded that disclosure would have the chilling effect in relation to the documents before us,” said the tribunal. It also found that the DWP would not need to divert key people on UC to answering media queries arising from publication of the reports. The DWP needed only to brief PR people.

On whether the Issues Register should be published the tribunal said:

“The problems outlined in the Issues Register are of a predictable kind and “unlikely to provoke any public shock, let alone hostility, perhaps not even significant media attention. On the other hand, the public may legitimately ask whether other problems might be expected to appear in the register.”

On the chilling effect of publishing the Risk Register the tribunal said that any failure of a civil servant to speak plainly about a risk and hence to conceal it from the UC team would be more damaging to UC than any blunt declaration that a certain risk could threaten the programme.

“We acknowledge that disclosure of the requested information may not be a painless process for the DWP,” said the tribunal. ““There may be some prejudice to the conduct of government of one or more of the kinds asserted by the DWP, though not, we believe, of the order that it claims.

“We have no doubt, however, that the public interest requires disclosure, given the nature of UC programme, its history and the other factors that we have reviewed,” said the Tribunal.

The DWP may appeal the ruling which could delay a final outcome by a year or more.

Comment

The freedom of information tribunal’s ruling is, in effect, independent corroboration that Parliament can sometimes be given a PR line rather than the unvarnished truth when it comes to big IT-based programmes.

Indeed it’s understandable why ministers and officials don’t want the reports in question published.  The reports could provide concrete evidence of the misleading of Parliament. They could refer to serious problems, inadequacies in plans and failures to reach milestones, at a time when the DWP’s ministers were making public announcements that all was well.

Those in power don’t always mind media speculation and criticism. What they fear is authoritative contradiction of their public statements and announcements. Which is what the reports could provide. So it’s highly likely the DWP will continue to withhold them, even though taxpayers will have to meet the rising legal costs of yet another DWP appeal.

One irony is that the DWP’s ministers, officials, managers, technologists and staff probably have little or no idea what’s in the reports the department is so anxious to keep confidential.  On one of my FOI requests it took the DWP several weeks to find the report I was seeking – after officials initially denied any knowledge of the report’s existence.

This is a department that would have us believe it needs a safe space for the effective conduct of public affairs. Perhaps the opposite is the case, and it will continue to conduct some of its public affairs ineffectively until it benefits from far more Parliamentary scrutiny, fewer safe spaces and much more openness.

FOI Decision Notice Universal Credit March 2014

George Osborne gives mixed messages over UC deadline

Universal Credit now at 10 job centres – 730 to go. 

DWP finds UC reports after FOI request

UC – new claimant figures

Should Liverpool Council smile now it’s ending BT joint venture?

By Tony Collins

Liverpool Direct Ltd describes itself as the largest public/private partnership of its kind in the UK. BT and Liverpool City Council formed the joint venture in 2001. At one point it employed more than 1,300 people.

Last year the joint venture had a visit from  Prince Edward who met its apprentices and trainees.

Now Liverpool City Council is taking full ownership of the joint venture. BT is handing back its 60% share in Liverpool Direct to the council. But the way the dissolution is being handled is like a theatre compere smiling exaggeratedly at the audience while he pushes off stage a performer who has overstayed his welcome.

Indeed the council’s report on why BT is being pushed out has an oversized grin on every page. Too much self-conscious praise for BT, perhaps. Which may show how political outsourcing deals have become.

This is the first sentence of the council’s report on why the joint venture with BT is ending:

“BT and Liverpool City Council have enjoyed a long and successful partnership through the joint venture company Liverpool Direct Limited.”

And then:

“The ethos of the Partnership was to place the ‘customer at the heart’ of the organisation through the development of innovative new ways of working building on BT’s global brand and reputation.”

There’s much more praise for BT. From the council’s report:

Groundbreaking achievements have included:

  • Establishment of the first ever 24x7x365 local government contact centre including a call centre which is top quartile
  • The only ‘Benefits Plus’ service in the UK.
  • A comprehensive and integrated network of One Stop Shops serving 350,000 visitors each year.
  • First class ICT infrastructure.
  • Creation of 300 new jobs supporting 3nd party business won by LDL.

But there’s a give-away line in one of the sets of bullet points on some of the benefits of the partnership. In 2011 came a refresh of the 10 year-old deal. The benefits of the refresh:

  • Further price reduction of £22.5m.
  • Increased share of third party business. Potential investment of £17m.
  • Continued sponsorship of ( e.g. BT Convention Centre 2012-2017)
  • The ‘write off’ by both parties of potential legal claims against Liverpool City Council estimated by BT of approximately £56m.
  • Increased ownership level from 20% to 40% in favour of the council.

Spot the anomaly – a write-of legal claims against each other of £56m? So the partnership wasn’t quite so wonderful. But that was 2011. Why is the council now pushing out BT from the Liverpool Direct joint venture – what the council calls officially “The Way Forward”?

Amid all the praise for BT it is not easy to see at first glance why Liverpool Direct is being taken into the council’s full ownership. It turns out that austerity is the reason. The council needs to make more cuts than BT is willing to make, and it recognises that BT needs to make a profit. Which raises the question of whether the council was willing to pay BT a decent profit during bountiful times until cuts began to bite.

From Liverpool Council’s report:

“In the early Autumn of 2013, both parties were in active discussions in an effort to resolve the serious financial savings Liverpool City Council needed to make between 2014 and 2017.

“As a result of these discussions and negotiations, BT agreed a further price reduction of £5m contribution to the budget process for 2014/15 together with a further £5m for the following financial year.

“Whilst the Council really appreciated BT’s continued commitment to the city, the current budget deficit would require a far more substantive financial contribution from the Contract both for 2014/15 and for future years.

“Unfortunately BT feels unable to commit to any further price reduction within the Contract as they need to sustain their own financial position. Moreover, the City Council is now well placed, as a result of the long collaboration with BT and the learning gained from the Partnership, to continue to drive forward business transformation and run the services with consequent cost savings to the city.”

The result is that negotiations will continue with a view to transferring BT’s 60% share in Liverpool Direct to the council by 31 March 2014; and the good news doesn’t stop there.

“The City Council and BT both believe that the transfer will enable additional savings to flow to the council including all income from third party contracts.

“BT remains committed to serving residents and businesses in Liverpool and its long and successful relationship with Liverpool City Council will carry on with BT continuing to provide a range of services to the council. During negotiations in late 2013 BT announced it plans to recruit a further 240 staff in Liverpool to support the growth of high-speed broadband services and has recently committed to being a major sponsor of the 2014 International Festival of Business.”

A dark side?

Behind the smiles Liverpool City Council has, it seems, an unusually secretive side.   Richard Kemp CBE has been a member of Liverpool City Council for 30 years having held major portfolios in both control and opposition. He is leader of the Liberal Democrats on the Council. He was Vice Chair of the Local Government Association of England & Wales for more than 6 years.

He says on his blog that has “taken the very unusual step of asking for two independent enquiries into activities of Liverpool City Council”. He adds: “The cases are related and refer to the tangled web of relationships which surround the Liverpool/Liverpool Direct Ltd/Lancashire/One Call Ltd/BT activities.

“In the first instance I have asked that the Lancashire Police extend their Lancashire investigation into Liverpool. In the second I have asked the Information Commissioner to look at the appalling record of the council in responding to freedom of information requests about any matter relating to Liverpool Direct Ltd.”

He says the council has an excellent record of responding to FOI requests – except when it comes to LDL. “When I raised this with the Mayor at the Mayoral Select Committee I didn’t get any answers …”

He also says:

“I find it amazing that I have been told that no contract exists between Liverpool, Lancashire and BT only to find that there is a legal agreement! As a layman I am unclear as to what the difference is between these two positions.

“We now need external scrutiny and investigation to examine these tangled relationships and work out not only who agreed what and when but also whether Liverpool and Lancashire tax payers are getting value for money for this deal.

“In a system where there is no internal scrutiny, Liverpool Labour members have to ask permission to raise issues in the scrutiny process, I feel that I have no alternative but to ask for help in looking at these affairs outside the council.

“In my career I have not only been a councillor for a long time but also asked to work in other councils which were in severe difficulties with their governance structures. Liverpool feels as bad as any council that I have worked in. There is no clear definition of Member and Officer roles.

“ No effective challenges exist within the system and a centralised almost Stalinist decision-making process pertains … I hope that these external investigations will take place and then that they force change in this secretive and opaque council.”

Infighting

A local paper, the Liverpool Echo, has also been investigating the council and its deal with BT.

It says the deal “has been dogged by accusations of infighting between BT and the Council, after top QCs were brought in to settle disputes over how much work would be awarded to LDL under the terms of its contract”.

An internal council report obtained by the Echo before agreement for the contract refresh in 2011 “showed the it took place amid the threat of costly legal claims by BT if city bosses pulled the plug and did not stay in partnership with them until 2017”.

Private/public deals too secretive – MPs today

A report by the Public Accounts Committee published today Private Contractors and Public Spending says private and public partnerships are too secretive – and they lie largely outside the FOI Act. Indeed a BBC File on 4 investigation into the growing influence of accountancy companies such as Capita in public life reached similar conclusions. File on 4 suggested that even if the contract between Service Birmingham, Capita and Birmingham City Council were published in full it could prove impenetrably complicated.

Margaret Hodge MP, chairman of the Public Accounts Commitee, said today:

 “There is a lack of transparency and openness around Government’s contracts with private providers, with ‘commercial confidentiality’ frequently invoked as an excuse to withhold information.

“It is vital that Parliament and the public are able to follow the taxpayers’ pound to ensure value for money. So, today we are calling for three basic transparency measures:

– the extension of Freedom of Information to public contracts with private providers;

– access rights for the National Audit Office; and

– a requirement for contractors to open their books up to scrutiny by officials.

Comment:

It’s remarkable how council outsourcing deals are becoming more cabalistic despite many initiatives toward more open government.

It’s a pity that things have reached a point where Richard Kemp, a Liverpool councillor of 30 years, ends up reporting his authority to the police and the Information Commissioner.

Meanwhile Liverpool City Council, which is one of the most self-image-protecting authorities in the UK, ends a long-standing joint venture with BT by giving the supplier nothing but praise – in public.

Democracy is a form of government in which all eligible citizens participate equally, either directly or indirectly through elected representatives. Clearly that’s not happening properly in Liverpool – or  some other parts of local government.

Reasons I have asked police and Information Commissioner to come in 

BT ad Capita  –  outsourcing joint ventures under pressure in Liverpool and Birmingham 

Private contractors and public spending – Public Accounts Committee report published today

A tragic outcome for Cerner Millennium implementation at Bath?

By Tony Collins

Three year-old Samuel Starr died in the arms of his parents as his they read him his favourite stories at the local hospital. 

At an inquest this week his parents, and specialists, raised questions about whether long delays in arranging appointments on a new Cerner Millennium system at Bath’s Royal United Hospital, which replaced an old “TDS” patient administration system, was a factor in his death.

Ben Peregrine, the speciality manager for paediatrics at the RUH in Bath,  told the inquest:

“Samuel’s appointment request must have fallen through the cracks between the old and new system.”

After successful heart surgery at 9 months, Samuel should have had regular scans to see if his condition had worsened. But he didn’t have any scans for 20 months, in part because of difficulties in organising the appropriate appointments on Bath’s new Millennium systems.

Though there is no certainty, Samuel may be alive today if he’d had the scans.

In a review of Samuel’s death, which took place in November 2012, the details of which have only just been made public, Bristol Children’s Hospital concluded that appointment delays might have played a part.

It said: “Death was felt to be possibly modifiable if [there had been] earlier surgery before cardiac function deteriorated.”

Samuel had his first surgical procedure, open heart surgery at Bristol Royal Hospital for Children, on 3 March 2010. He was discharged six days later, and referred to the Paediatric Cardiac Clinic at the Royal United Hospital in Bath for check-ups.

This week’s inquest heard that the first check-up took place in Bristol in October 2010, when an echocardiogram, also known as an ‘echo’, was carried out. Samuel’s parents, Paul Starr and Catherine Holley, expected a follow-up appointment in January 2012 but by March they’d not received one.

Their community nurse rang the hospital five times in as many months for a follow-up appointment but could not arrange one. When another echo was eventually taken in June 2012 – 20 months after the first – it was found that Samuel needed urgent surgery which proved more complicated than expected. He died on 6 September 2012.

Paul Starr told the BBC that during the long delays in obtaining an appointment for a further scan Samuel’s heart function went from good to bad. He said: “It is not like he had bad care in that time. He had no care at all.”

Ben Peregrine, the speciality manager for paediatrics at the hospital, told the inquest:

“The new system is now up and running as best as it can be, but as long as there is still humans entering the information there will always be room for error.”

The BBC reported that the delay in Samuel’s treatment “came after a new computerised appointment booking system was introduced at the RUH in 2011. It was only after an appointment had been set that doctors discovered the three-year-old, from Frome in Somerset, needed open heart surgery.”

BBC West’s Inside Out obtained a hospital document “Issues for discussion including any action or learning to be taken as a result of the child’s death. Issues that require broader multi-agency discussion” that has as its first bullet point:

“Failure of the RUH Millennium computer software to organise appointments at the designated time leading to a delay of three months before Samuel was seen by (redacted) in Bath.

“Parents have since told me that Samuel had not had an ECHO for 20 months prior to June 2012. At his previous cardiac appointment (April 2011) [redacted] failed to carry out an ECHO because he was not expecting to see Samuel despite Samuel’s parents being sent an appointment for this day.”

It appears that events at Bath after the Cerner go-live have, in the main, followed a pattern at a dozen or so other trusts that have installed the Millennium system.

The pattern was outlined in a Campaign4change post in December 2012:

– go-live

– chaos

– a trust admission that potential problems, costs and risks were underestimated

– a public apology to patients

– a trust promise that the problems have been fixed

– trust board papers that show the problems haven’t been fixed or new ones have arisen

– ongoing difficulties producing statutory and regulatory reports

– provision in trust accounts for unforeseen costs

– continuing questions about the impact of the new system on patients

– a drying-up of information from the trust on the full consequences of the EPR implementation, other than public announcements on its successful aspects.

Catherine Holley, Samuel’s mother, believes the Millennium implementation at the Royal United Hospital at Bath might have followed the above cycle.

Bath went live with Cerner Millennium at the end of July 2011. An upbeat trust statement at the time to E-Health Insider said:

“We can confirm that the new Cerner Millennium IT system successfully went live on Friday 29 July – as planned – at Royal United Hospital Bath NHS Trust.

“BT and Cerner worked closely with the trust and the Southern Programme for IT on the implementation over the past year – a complex and major change management programme.”

As part of its investigation into Samuel’s death, the BBC asked the RUH how many appointments were overdue to delayed because of the new computer system. Said the BBC’s Inside Out West programme:

“They told us there were 63 overdue appointments some with delays of up to 2 years before they were discovered.”

Separately an FOI request to the trust on the Millennium installation brought the response that there have been 65 cardiac outpatients’ appointments “that have been identified as being were missed due to problems with the delayed and that occurred around implementation of Cerner Millennium… All of these appointments have been followed up and actioned as required.”

The RUH is not discussing Samuel Starr’s death. A spokesperson said the inquest is expected to give Samuel’s family and everyone involved in his care a clearer indication of the circumstances surrounding his death. “We have offered our sincere condolences to the family of Samuel Starr following his sad death.”

Contradictory

RUH Board reports on Millennium’s deployment have had a general “good news” tone. But some of the reports have mentioned potentially serious problems. This was in an RUH board report in 2011 on Millennium:

“… there were significant issues with clinic templates and data that had not been migrated. This affected encounters with long term follow up appointments. As a result this meant that there was unplanned downtime across Outpatients and backlogs developed in addition to those produced as a result of planned downtime”.

Comment:

What’s striking about the reports to the Bath board of directors on the Cerner Millennium implementation is their similarity, in tone and substance, to the “good news” reports of deployments of Millennium at other trusts.

The go lives are nearly always depicted as successes for clinicians that have had minor irritations for administrators.

Now we know from the RUH Bath’s implementation of Millennium that when appointments are delayed as a result of inadequate preparations for, and structural settlement of, a new patient administration system, it can be a matter of life and death.

Indeed the BBC, in its investigation into Samuel Starr’s short life, raises the question of whether delayed appointments have been a factor in other deaths.

But do trusts genuinely care about the bigger picture, or do they regard each case of harm or death as an individual, unique event, to be reviewed after the problems come to light?

At the RUH Bath, IT appears to be treated as a separate department, too little interweaved with care and treatment. Managers talked enthusiastically of smartcard use, the work of the service desk, the need for more printers, resolving BT outages, the benefits of the service security model, champion users and floorwalkers, completing the Readiness Workbook, and keeping the Deployment Hazard Document up to date – while the parents of Samuel Starr could not get an appointment on the new system for their son to have a vital heart scan.

In 2011 a senior executive at Bath told his trust staff: “Our partners BT and Cerner are describing it [the go-live of Cerner Millennium] as the smoothest deployment yet” and “we now have the foundation in place to meet the future needs of the Trust and the NHS”.

Will things improve?

The comment in my post of December 2012, which was about Royal Berkshire’s implementation of Cerner Millennium, seems apt so some it may be worth repeating (below).

“Some Cerner implementations go well and bring important benefits to hospitals and their patients. Some implementations go badly. One question the NHS doesn’t ask, but perhaps should, is: what level of problems is acceptable with a new electronic patient record system?

“It appears from some EPR implementations in the NHS that there is no such thing as a low point. No level of disruption or damage to healthcare is deemed unacceptable.

“Berkshire’s chief executive Edward Donald speaks the truth when he says that the trust’s implementation of Cerner was more successful than at other NHS sites. This is despite patients at his trust attending for clinics that did not exist, receiving multiple requests to attend clinics and not receiving follow-up appointments…

“The worrying thing for those who use the NHS is that, as far as new IT is concerned, it is like flying in a plane that has not been certified as safe – indeed a plane for which there has been no statutory requirement for safety tests. And if the plane crashes it’ll be easy for its operators and supplier to deny any responsibility. They can argue that their safety and risk ratings were at “green” or “amber-green”.

“The lack of interest in the NHS over the adverse effect on patients of patient record implementations means that trusts can continue to go ahead with high-risk electronic patient record system go-lives without independent challenge.”

This very thing seems to have happened at the RUH Bath – with possibly tragic consequences.

Thank you to openness campaigner Dave Orr for drawing my attention to the BBC’s investigation into Samuel Starr’s death.

RUH booking system might have contributed to boy’s death – BBC

Boy died after scan delay – BBC

Best Cerner Millennium implementation yet?

Top 5 posts on this site in last 12 months

Below are the top 5 most viewed posts of 2013.  Of other posts the most viewed includes “What exactly is HMRC paying Capgemini billions for?” and “Somerset County Council settles IBM dispute – who wins?“.

1) Big IT suppliers and their Whitehall “hostages

Mark Thompson is a senior lecturer in information systems at Cambridge Judge Business School, ICT futures advisor to the Cabinet Office and strategy director at consultancy Methods.

Last month he said in a Guardian comment that central government departments are “increasingly being held hostage by a handful of huge, often overseas, suppliers of customised all-or-nothing IT systems”.

Some senior officials are happy to be held captive.

“Unfortunately, hostage and hostage taker have become closely aligned in Stockholm-syndrome fashion.

“Many people in the public sector now design, procure, manage and evaluate these IT systems and ignore the exploitative nature of the relationship,” said Thompson.

The Stockholm syndrome is a psychological phenomenon in which hostages bond with their captors, sometimes to the point of defending them.

This month the Foreign and Commonwealth Office issued  a pre-tender notice for Oracle ERP systems. Worth between £250m and £750m, the framework will be open to all central government departments, arms length bodies and agencies and will replace the current “Prism” contract with Capgemini.

It’s an old-style centralised framework that, says Chris Chant, former Executive Director at the Cabinet Office who was its head of G-Cloud, will have Oracle popping champagne corks.

2) Natwest/RBS – what went wrong?

Outsourcing to India and losing IBM mainframe skills in the process? The failure of CA-7 batch scheduling software which had a knock-on effect on multiple feeder systems?

As RBS continues to try and clear the backlog from last week’s crash during a software upgrade, many in the IT industry are asking how it could have happened.

3) Another Universal Credit leader stands down

Universal Credit’s Programme Director, Hilary Reynolds, has stood down after only four months in post. The Department for Work and Pensions says she has been replaced by the interim head of Universal Credit David Pitchford.

Last month the DWP said Pitchford was temporarily leading Universal Credit following the death of Philip Langsdale at Christmas. In November 2012 the DWP confirmed that the then Programme Director for UC, Malcolm Whitehouse, was stepping down – to be replaced by Hilary Reynolds. Steve Dover,  the DWP’s Corporate Director, Universal Credit Programme Business, has also been replaced.

4) The “best implementation of Cerner Millennium yet”?

Edward Donald, the chief executive of Reading-based Royal Berkshire NHS Foundation Trust, is reported in the trust’s latest published board papers as saying that a Cerner go-live has been relatively successful.

“The Chief Executive emphasised that, despite these challenges, the ‘go-live’ at the Trust had been more successful than in other Cerner Millennium sites.”

A similar, stronger message appeared was in a separate board paper which was released under FOI.  Royal Berkshire’s EPR [electronic patient record] Executive Governance Committee minutes said:

“… the Committee noted that the Trust’s launch had been considered to be the best implementation of Cerner Millennium yet and that despite staff misgivings, the project was progressing well. This positive message should also be disseminated…”

Royal Berkshire went live in June 2012 with an implementation of Cerner outside the NPfIT.  In mid-2009, the trust signed with University of Pittsburgh Medical Centre to deliver Millennium.

Not everything has gone well – which raises questions, if this was the best Cerner implementation yet,  of what others were like.

5) Universal Credit – the ace up Duncan Smith’s sleeve?

Some people, including those in the know, suspect  Universal Credit will be a failed IT-based project, among them Francis Maude. As Cabinet Office minister Maude is ultimately responsible for the Major Projects Authority which has the job, among other things, of averting major project failures.

But Iain Duncan Smith, the DWP secretary of state, has an ace up his sleeve: the initial go-live of Universal Credit is so limited in scope that claims could be managed by hand, at least in part.

The DWP’s FAQs suggest that Universal Credit will handle, in its first phase due to start in October 2013, only new claims  – and only those from the unemployed.  Under such a light load the system is unlikely to fail, as any particularly complicated claims could managed clerically.

 

The story of Southwest One

By Tony Collins

Dave Orr worked in a variety of IT and project management roles for Somerset County Council and retired in 2010. For years he has campaigned with extraordinary tenacity to bring to the surface the truth over an unusual joint venture between IBM, Somerset County Council, a local borough council and the local police force.

Now he has written an account of the joint venture and the lessons. It is published on the website of procurement expert Peter Smith.

Orr questions whether Southwest One was ever a good idea, since it was formed in 2007.

The deal has not made the savings intended, a SAP implementation went awry, the contract has been mired in political controversy and criticism, Southwest One has repeatedly lost money, and many of the transferred staff and services have returned to the county council, and some services returned to the borough council. IBM and the county council have ended up in a legal dispute that cost the county council £5.5m to settle. Southwest One was not exactly the partnership it set out to be.

The contract may show how an outsourcing deal that doesn’t have the support of the staff being transferred is flawed fundamentally from the start (which is one reason few people will be surprised if a 10-year £320m deal for Capita to run Barnet Council’s new customer service organisation [NSCSO]  ends in tears).

These are some of Orr’s points:

–  Like other light-touch regulators, the Audit Commission repeatedly gave Southwest One positive reports, without ever qualifying the accounts, even as problems with SAP implementation mounted in 2009 and procurement savings were not being made in line with forecasts.

 – The contract called for transformation based upon ‘world-class technologies’, yet all of the IT Service was placed into Southwest One with no IT expertise back in the Somerset County client (until after a poor SAP implementation in 2009). Was the lack of retained IT skills in the Somerset County client behind the formal acceptance of a badly configured SAP implementation?

– Large scale outsourcing over a long contract of 10 years or more requires an ability to foresee the future that is simply not possible to capture in a fixed contract. In a 10-year contract, there will be three changes of national government and three changes of local government. That is a great deal of unpredictable change to cope with via a fixed, long-term contract.

– Local Government will always be at a disadvantage in resources and skills, to a large multi-national contractor like IBM, when it comes to negotiating, letting and managing a complex multi-service contract.

– What was the culture of Southwest One (75% owned by IBM)? Was it private, public or a hybrid? The management culture remained firmly IBM, yet the councils and police workforces were seconded and remained equally firmly public sector rooted. There is such a thing as a public service ethos. In fact, Southwest One was run like a mini-IBM based upon global divisions, complete with IBM standard structures and processes. Southwest One seconded employees were not allowed anything like a full access to IBM internal systems, thus creating additional complexity, as “real” IBM employees relied entirely upon on-line systems.

–  Mixed teams in a single shared service were hard to amalgamate. This meant the IBM managers of Southwest One never really gained the sort of command & control of the multi-tier workforces that their bonus-oriented model needs to function. “I doubt that IBM would ever again contemplate the seconded staff model over the TUPE transfer model,” says Orr.

– Somerset County Council ran with a “thin” client management team that, in Orr’s view, did not have sufficient expertise or enough staff resources to effectively manage this complex contract with IBM. The councils relied upon definitions of “partnership” that meant one thing to the councils’ side and quite another thing to IBM, says Orr.

– In Southwest One, Somerset County Council handed their entire IT Service over lock, stock and barrel. “Can you really consider IT as wholly a ‘back office’ service? Many successful private Companies see IT as a strategic service to be kept under their own control.”

– The real savings might have been found in optimising processes in big departments (like Social Care, Education, Highways) that lay outside of Southwest One’s reach. “The focus on IT rather than service processes was another flaw in the model.”

Orr  concludes that nobody who played a major part in the Southwest deal has in any way been held to account for what has gone wrong.

Southwest One – the complete story from Dave Orr

Universal Credit – good for its IT suppliers?

By Tony Collins

The DWP is conceding in its own tangential way that the IT for Universal Credit is not up to scratch; and an article in the Daily Telegraph suggests that Universal Credit this year (and perhaps well beyond) will handle so few claimants that the calculations for the time being could be done by hand, or on a spreadsheet, and not automatically by IT systems. The Register, through anonymous sources, has confirmation of this.

The FT says there will be a progressive national rollout of the coalition’s welfare reform in just six additional jobcentres which it said was the “latest sign the project is falling behind schedule”. It added that a significant shake-up of the IT underpinning universal credit is under way. 

The DWP said David Pitchford, the Whitehall troubleshooter who took over the running of Universal Credit for three months, had been asked to “review” the IT and ministers had “accepted his recommendation that they should explore enhancing the IT for universal credit working with the government digital service”.

“Advancements in technology since the current system was developed have meant that a more responsive system that is more flexible and secure could potentially be built,” said the DWP.

The FT quoted Howard Shiplee, who has led the Universal Credit  project since May, as denying claims from MPs that the original IT had been dumped because it had not delivered. “The existing systems that we have are working, and working effectively,” he said.

He added that he had set aside 100 days not to stop the programme, but to reflect on where it has got to and start to look at the entire total plan.

Iain Duncan Smith, the work and pensions secretary, doesn’t concede that the  timetable for the implementation of Universal Credit has changed. He told the work and pensions committee on Wednesday that numbers of claimants would ramp up during 2014 and he insisted that all claimants would be on the system by 2017, as originally planned.

“We get fixated on things like IT; the reality is it’s about a cultural shift,” Duncan Smith told MPs.

Comment

Iain Duncan Smith makes it clear that his DWP staff and suppliers, with the help of HMRC, are implementing Universal Credit with extreme care. Labour’s  work and pensions spokesman Liam Byrne says the Universal Credit project is a shambles. The truth is hard to fathom.

For years the DWP has rejected press reports that the IT for Universal Credit was in trouble. It is able to do without fear of authoritative contradiction because it keeps secret all its consultancy reports on the state of the Universal Credit project, despite FOI requests.

The Cabinet Office minister Francis Maude and his officials talk much about the need for openness and transparency. Isn’t it time they persuaded DWP officials to release their internal and external reports on the detailed challenges faced by suppliers and civil servants on Universal Credit and other major government IT projects?

All big government IT projects are characterised by secrecy and defensiveness, although a little information about them is in the vague and subjectively-worded Major Projects Authority annual report.

One by-product of departmental defensiveness and secrecy is that the IT suppliers – in Universal Credit’s case HP, IBM and Accenture – are likely to continue to be paid even if the project is halted and redesigned. It’s probable the suppliers would argue that they have successfully done what they were asked to do in the contract. Who knows what the truth is?

The DWP is in effect protecting its suppliers from public and parliamentary scrutiny. It has been this way for decades and nothing has changed.

EC probes IBM CIO secondment at the Met Office

By Tony Collins

A part of the European Commission is investigating a decision by the Met Office to appoint an IBM executive as CIO while he worked at the same time for IBM, the organisation’s main IT supplier.

The investigation was prompted by concerns of campaigner Dave Orr who wrote to the EC about the Met Office’s appointment of an IBM secondee David Young as CIO for two years between 2010 and December 2012.

Now Michel Barnier, the EC Commissioner responsible for internal market and services, says in a letter to Orr’s MEP Sir Graham Watson that the EC’s Directorate-General for Internal Market and Financial Services has been carrying out “an in-depth analysis” of the facts presented by Orr.

As part of this, the EC has written to the UK government seeking clarification on a number of points.

Some of Orr’s concerns arise from the Met Office’s responses – and non-responses – to his freedom of information requests. One of his concerns is of a potentially cosy relationship between the Met Office as a publicly-funded organisation and its principal IT supplier IBM; and he has wanted to know why the job of Met Office CIO was not openly advertised in a competitive recruitment process and whether its appointment of an IBM secondee had the potential for a possible conflict of interest.

Orr said that the secondment had the potential to confer a unique and significant intelligence and relationship advantage for IBM that other supercomputer suppliers could not hope to match. “In my view, that is anti-competitive and may in spirit at least, fail the EU procurement rules,” said Orr.

Barnier said that the existence of a conflict of interest would “depend on a number of factors such as the precise role and responsibilities the position entails, in particular whether it includes formulating and preparing technical specifications or tender documents for future IT contracts that the Met Office may put out to tender”.

It is also relevant, said Barnier, whether the terms and conditions of the secondment “impose any obligations or restrictions on the head of the department to prevent conflicts of interest, both during the secondment and afterwards”. He also wanted to know if internal rules were in place to prevent conflicts of interest in the course of tendering procedures.

The Met Office and ministers said that Young was not involved in procurement decisions relating to existing supercomputer facilities. Norman Lamb, then minister at the Department for Business Innovation and Skills, said last year:

“Any potential conflicts of interest regarding David Young’s appointment were fully considered prior to his appointment and his terms of engagement specifically cover these …

“David Young had no involvement in the procurement process for existing supercomputing facilities, either for IBM or the Met Office, and he will have completed his secondment and left the Met Office prior to the selection of replacement supercomputer facilities.”

A wise decision?

The decision to second an IBM employee to run the 300-strong IT department, which is based at the Met Office’s supercomputer site in Exeter, raises questions that may go beyond the potential for a conflict of interest.

As Young was unable to be involved in some buying decisions and was unable to attend the technology strategy board to avoid any potential for a conflict of interest, did the Met Office restrict itself unnecessarily in hiring a CIO who faced these constraints?

Did the Met Office waste money – and a precious two years – hiring a lifeguard whose terms of employment required him to wear handcuffs?

The secondment of Young came at a difficult time for the Met Office – and some of the main difficulties it faced in 2010 are largely the same today.

Responses to Orr’s FOI requests and a report by the House of Commons’ Science and Technology Committee highlight some of the Met Office’s challenges:

– A need for modernised software that will take advantage of next-generation supercomputers.

– A need for a replacement supercomputer that has twice the power of the existing one which operates close to one petaflop (one thousand million million floating point operations per second).

– Funding a new supercomputer (with optimised software) at a time of cut-backs in government spending.

A Met Office Executive Board paper said that its executives have had “soft” negotiations with various suppliers about next generation supercomputer technology. They spoke to Bull, Cray, Microsoft, NEC and SGI.

“Vendor presentations indicate that performance increases will come from increasing the number of processors and/or adding co processors designed to process arrays of data efficiently, rather than increasing the speed of individual processors,” said the Met Office paper.

The Met Office says that “significant optimisation work will be needed [on the code] and, if this is not completed around 2014, a delay in the launch of the procurement may be unavoidable.” It has been seeking software engineers with experience of Fortran (which was originally developed by IBM) or C, Unix or Linux and Perl.

A House of Commons report in 2012 emphasised the need for new technology at the Met Office. The report of the Science and Technology Committee “Met Office Science” said in February 2012:

“It is of great concern to us that these scientific advances in weather forecasting and the associated public benefits (particularly in regard to severe weather warnings) are ready and waiting but are being held back by insufficient supercomputing capacity. We consider that a step-change in supercomputing capacity is required in the UK.”

MPs acknowledged that “affordability is an issue.”

The Met Office declined to answer Orr’s FOI requests about the cost to the taxpayer of employing Young.

Since Young’s  secondment ended in December 2012 the Met Office has hired one of its own employees as CIO. Charles Ewen has worked for the Met Office since 2008. He works with science teams to operate the Met Office’s high performance computing facilities. He is responsible for the development and implementation of the Met Office’s ICT Strategy and for the internal technical teams within the Technology Information Services Directorate.

Comment:

The Met Office hired Young for the best of reasons: after a succession of internal management changes it wanted a highly professional, stabilising CIO. But did it need a CIO from IBM, its principal IT supplier?

That the Met Office was sheepish about the appointment of an IBM secondee was, perhaps, revealed by its website which, in giving a profile of Young, did not mention – at first – that he was seconded from IBM. After Dave Orr’s FOI requests the Met Office corrected its website omission, making clear that Young was on secondment from IBM.

The Met Office has been in existence nearly 16o years. It was founded by Vice-Admiral Robert FitzRoy in 1854 as the Meteorological Department of the Board of Trade. It is highly regarded internationally. A testament to the quality of its computer models  – which are used for daily forecasts – is that its “Unified Model” is licensed in Norway, Australia, South Korea, South Africa, India, New Zealand and the US Air Force.

Scientists say that a three-day forecast today is as accurate as a one-day forecast was 20 years ago. But in the UK the Met Office gets a bad press – not always unjustifiably.  There is a perception that the accuracy of forecasting is not improving. Sometimes it seems poor.

The algorithms that form the basis of weather and climate models place huge demands on supercomputing architectures. The models produce exceptionally large volumes of data. Although the Met Office had a new IBM supercomputer in 2008 it soon needed more powerful hardware and modernised software.

So was it a good idea, with all the challenges the Met Office faced in 2010 – including the need to persuade the government of the need to fund  new supercomputer facilities – to appoint a CIO for two years who, because he was an IBM secondee, had understandable restrictions on his freedom to do his job, restrictions the Met Office has been reluctant to reveal, despite Dave Orr’s FOI requests?

Hole in the head

The Met Office may regard an EC inquiry into its appointment of an IBM secondee as the last thing it needs now. But accountability should not be left to the occasional scrutiny by a Commons committee – or to Dave Orr’s FOI requests.

Another Universal Credit leader stands down

By Tony Collins

Universal Credit’s Programme Director, Hilary Reynolds, has stood down after only four months in post. The Department for Work and Pensions says she has been replaced by the interim head of Universal Credit David Pitchford.

Last month the DWP said Pitchford was temporarily leading Universal Credit following the death of Philip Langsdale at Christmas. In November 2012 the DWP confirmed that the then Programme Director for UC, Malcolm Whitehouse, was stepping down – to be replaced by Hilary Reynolds. Steve Dover,  the DWP’s Corporate Director, Universal Credit Programme Business, has also been replaced.

A DWP spokesman said today (11 March 2013),

“David Pitchford’s role as Chief Executive for Universal Credit effectively combines the Senior Responsible Officer and Programme Director roles.  As a result, Hilary Reynolds will now move onto other work.” She will no longer work on UC but will stay at the DWP, said the spokesman.

Raised in New Zealand, Reynolds is straight-talking. When she wrote to local authority chief executives in December 2012, introducing herself as the new Director for the Universal Credit Programme, her letter was free of the sort of jargon and vague management-speak that often characterises civil service communications.  It is a pity she is standing down.

Some believe that Universal Credit will be launched in such a small way it could be managed manually. The bulk of the roll-out will be after the next general election, which means the plan would be subject to change. Each limited phase will have to prove itself before the next roll-out starts.

Reynolds’ letter to local authorities suggests that the roll-out of UC will, initially, be limited.  She said in her letter,

“For the majority of local authorities, the impact of UC during the financial year 2013/14 will be limited. .. Initially, UC will replace new claims from single jobseekers of working age in certain defined postcode areas.

“From October 2013 we plan to extend the service to include jobseekers with children, couples and owner-occupiers, gradually expanding the service to locations across Great Britain and making it available to the full range of eligible working age claimants …by the end of 2017.”

Some IT work halted? 

Accenture, Atos Origin, Oracle, Red Hat, CACI and IBM UK have all been asked to stop work on UC, according to shadow minister Liam Byrne MP, as reported on consultant Brian Wernham’s blog.

Wernham says that Minister Mark Hoban did not rebut Byrne’s statement but said that HP was committed to carrying on with the project. HP is responsible for deployment of a solution, not development, says Wernham’s agile government blog.

Comment

The DWP says that Pitchford has taken over from Reynolds – but separately the DWP had confirmed that Pitchford was leading UC temporarily and that Reynolds had a permanent job on the programme. Pitchford’s usual job is running the Major Projects Authority in the Cabinet Office.

All the changes at the DWP, and the reported halting of work by IT contractors, imply that the UC project is proving more involved, and moving more slowly,  than initially thought. It’s also a reason for the DWP to continue to refuse FOI requests for internal reports that assess the project’s progress.

Perhaps the DWP doesn’t want people to know that the project is on track for such a limited roll-out in October that it could be managed, in the main, by hand. With the bulk of the roll-out planned for after the next general election Labour may be denied the use of UC as an effective electoral weapon against the Conservatives. In other words, the riskiest stage of UC is being put off until 2016/17.

 Francis Maude, who is worried that UC will prove an IT and electoral disaster, has his own man, David Pitchford, leading the project, if only temporarily. Meanwhile UC project leaders from the DWP continue to last an extraordinarily short time. Reynolds had been UC programme director for only four months when she stood down. Pitchford is in a temporary role as the programme’s head, and Andy Nelson has recently become the DWP’s Chief Information Officer.

So much for UC’s continuity of leadership.

The truth about the project hasn’t been told. Isn’t it time someone told Iain Duncan Smith what’s really happening – Francis Maude perhaps?