Category Archives: IT-related failures

BBC’s DMI project – another fine mess that was predictable

By Tony Collins

A National Audit Office memorandum published today on the BBC’s failed £125.9m Digital Media Initiative is a reminder – as in most failed big IT-enabled projects – that the causes have nothing to do with software and everything to do with management and people.

The NAO’s memorandum tells an all too familiar story with government IT (and the BBC is a public sector organisation):

– Over-optimism about the ability to implement

– Over-optimism about the ability to achieve the benefits

– Unclear requirements

– No thorough independent assessment of the technical design to see whether the DMI was technically sound

– The successful completion of the most straightforward of technology releases for the DMI, but these proved an unreliable indicator of progress.

– Technical problems and releases not meeting user expectations which contributed to repeated extensions to the timetable for completing the system, eroding user confidence and undermining the business case.

– Poor internal reporting. “The governance arrangements for the DMI were inadequate for its scale, complexity and risk. The BBC did not appoint a senior responsible owner to act as a single point of accountability and align all elements of the DMI. Reporting arrangements were not fit for purpose,” said the NAO.

– In the same way as the DWP failed with Universal Credit to take full account of recommendations in review reports, the BBC “did not adequately address issues identified by external reviewers during the course of the programme”.  The BBC had been aware that business requirements for the DMI were not adequately defined.

The BBC estimates that it spent £125.9m on the DMI. It offset £27.5m of spending on the DMI against transfers of assets, cash and service credits that formed part of its financial settlement with DMI’s previous developer Siemens. This left a net cost of £98.4m.

The BBC cancelled the DMI without examining the technical feasibility or cost of completing it, said the NAO.

The Corporation has written off the value of assets created by the programme, but is exploring how it can develop or redeploy parts of the system to support its future archiving and production needs.

Diane Coyle, Vice Chairman BBC Trust, said:

“We are grateful to the NAO for carrying out this report, which reinforces the conclusions of the PwC review commissioned by the Trust. It is essential that the BBC learns from the losses incurred in the DMI project and applies the lessons to running technology projects in future.

“The NAO’s findings, alongside PwC’s recommendations will help us make sure this happens. As we announced last December, we are working with the Executive to strengthen project management and reporting arrangements within a clearer governance system.  This will ensure that serious problems can be spotted and addressed at an earlier stage.”

Amyas Morse, head of the National Audit Office, said today:

“The BBC Executive did not have sufficient grip on its Digital Media Initiative programme. Nor did it commission a thorough independent assessment of the whole system to see whether it was technically sound.

“If the BBC had better governance and reporting for the programme, it would have recognized the difficulties much earlier than May 2012.”

Comment

The DMI project is exemplar of all that tends to go wrong in big government IT-enabled projects. Strong independent oversight and independent reviews that were published would have provided the accountability to counterbalance over-optimism.  But these things never seems to happen.

There are also questions about why the BBC took on the project from Siemens  and turned what could have been a success into a financial disaster.

NAO memorandum on the BBC’s Digital Media Initiative

BBC World at One’s focus on Government IT

By Tony Collins

The lead item on BBC R4’s World at One on Friday was about Government IT contracts.

On the programme were the government’s Chief Procurement Officer Bill Crothers, Cabinet Office minister Francis Maude, the chairman of the Public Accounts Committee Margaret Hodge, the UK IT Association, and me.

Some of the points made:

–  Bill Crothers gave an example of what he called “abuse” by some big IT suppliers. He said a young man who works for him lost his power cable. The supplier quoted £65 for a replacement. The price should have been £5 or £6.  When Crothers queried it, the supplier justified its price on grounds of security. Crothers could not believe that a power lead had security implications so he questioned the price again and received several pages of explanation from the supplier, which he did not read. Eventually the supplier “was good enough to reduce the price to £37”.

– HMRC was charged £30,000 for changing some text on its website.

– Francis Maude said a DWP team and a further 12 people from the Cabinet Office’s Government Digital Service had built – in only three months – a prototype of a digital solution to support the introduction of Universal Credit. The system cost just over £1m, he said. [Separately big IT suppliers at DWP have been paid £303m up to March 2013 for Universal Credit work.] Maude declined to predict the outcome of the “twin-track” work on the UC project.

– Some big legacy systems may soon need replacing – those that pay about £60bn a year in state pensions and collect nearly £100bn a year in VAT. “Those are going to be big projects,” said Margaret Hodge. “I don’t think we have seen the end of big projects, or the end of disasters.”

World at One in detail

Presenter Shaun Ley and BBC political correspondent Ross Hawkins focused on government IT because of an announcement by the Cabinet Office that it is drawing the line on “bloated and wasteful IT contracts”. The Cabinet Office was pitching its announcement as marking a “massive change,” said Hawkins.

Ley said Francis Maude announced the safeguards  in an attempt to ensure that IT contracts don’t become multi-billion pound failures. He said that the abandoned NPfIT had cost close to £10bn.

Hawkins quoted the UK IT Association as saying that  government did not know how to do deals with smaller suppliers. On the government’s relationship with big suppliers UKITA said the government was like a “battered wife or husband who doesn’t seem to know how to leave.”

Appalling

Hawkins said Crothers has the air of a man going to war. Crothers’ conclusion on the way things are at the moment:

“This is about the oligopoly, the cluster of big suppliers that have had it took good for too long. It’s reflective of monopolistic or oligopolistic behaviour.  It is not acting as if they are in hungry and in a competitive market.  That’s appalling.”

Universal Credit

Hawkins asked Francis Maude how confident he was that what was being put in place on Universal Credit would work.

“I hope it will work,” said Maude. “The digital solution was created by a team within DWP with a dozen or so GDS [Government Digital Service] staff assisting.

“They created a working prototype for a digital solution within 3 months at a cost of only a bit over £1m. That certainly can be basis of a successful long-term solution.”

Hawkins [to Maude] “I asked you whether you were confident the approach with DWP would work and you said you hoped it would. That suggests to me that maybe you are not (confident).”

Maude: “N0-one knows with these things. Anyone who says you are certain everything is going to succeed … the way we do things now is build something quickly, test it, prove it, test it with users, and so you can’t have certainty about any of these outcomes.”

Outsourcing failures

Hawkins said “We have had story after embarrassing story about outsourcing failures [such as the] government being charged for tagging dead people … now ministers  have an interest in coming out on the front foot and just for once being on the attack and having a whack at the IT companies.

“You don’t need to be a political genius to work out why they would like to do that rather than be endlessly explaining themselves after embarrassing stories in the papers.”

Ley (to me): “Is this the best way to deal with the problems government has experienced? The journalist Tony Collins has written widely  about project failures in IT in both the public and private sectors.”

I replied that big companies have sometimes charged a lot to make small software changes.  The Cabinet Office’s “red lines” were a good idea though they were a formalising of restrictions that had been in place some time.

The Cabinet Office doesn’t have the power to make changes happen because departments are accountable to Parliament for their spend and so don’t want much interference from the Cabinet Office. But the Cabinet Office is right to try and reduce the amounts spent on big projects.

Ley: “What will be the effect of breaking up contracts?”

I said I hoped the Cabinet Office’s restrictions would bring about a change in culture in departments against the assumption that big is beautiful. Big projects should be split into components which would give SMEs a greater involvement and could reduce the risks of projects failing.

More project disasters?

Hodge gave her reaction to the Cabinet Office’s restrictions in the context of the Universal Credit project.

“Francis Maude and Cabinet Office have been trying really hard to get some sense into the way that project has developed. But sadly the news we have had lately suggests to me that they have failed. It is about £400m so far on IT.

“What went wrong there was that the department [DWP] thought it [UC] was a big IT project instead of thinking:  we are going to be changing our business; we are going to get 6 benefits rolled into one. They [the DWP] have not written off that money [£303m] which is what my committee thinks they should have done, because they want to save face. Down the line I think we’ll see some disasters there.

“There are a lot of projects around  government, what are called legacy projects, where old systems need to be replaced . They are big projects – pensions in DWP where £60bn is given out a year;  VAT receipts  in HMRC where nearly £100bn is collected. Those are going to be big projects. I don’t think we have seen the end of big projects, or the end of disasters.”

Ley: “What about breaking them up into smaller projects? Won’t that reduce potential risks?”

Hodge: “The important thing is what Tony Collins was saying to you. What we find is that the skills don’t exist within departments, either to commission the IT properly or to manage the suppliers once they have the IT in place.

“We are about to examine the army recruitment contract – I think that is what we’ll find.  The MoD hasn’t got the skills to manage it.

Ley: “Do you welcome the ending of automatic contract extensions?”

“I warmly welcome that. This is a small step in the right direction. Having an expert as we have in Bill Crothers in the Cabinet Office is really important. What we haven’t got are skills in the departments. It is not like a business. If it was, Bill Crothers would probably run IT across the whole of government. Our departments run in silos. They haven’t got the skills. They have this demand for big, big programmes in the future and I don’t think we have seen, sadly, the end of IT disasters.”

Update

Thank you to Dave Orr for drawing my attention to an excellent piece on the World at One item by procurement expert Peter Smith who concludes:

“… There is a big issue – large suppliers have not covered themselves in glory, but small suppliers just can’t develop huge systems for DWP or MOD.

“The large suppliers must have a role, but we have to manage these contracts better. And the answer can’t just be a small hit squad in Cabinet Office. This needs real capability development across government, which we haven’t really seen as yet in a coordinated fashion.”

BBC World at One – Government IT contracts

Bill Crothers on BBC Radio 4 – suppliers get another good kicking

Are Govt IT-based project disasters over? Ask the Army

By Tony Collins

When senior civil servants know an IT-based project is in trouble and they’re unsure how bad things are, they sometimes offer their minister an all-encompassing euphemism to publicly describe the status of the scheme – teething.

Which may be why the defence secretary Philip Hammond told the House of Commons in November 2013 that the IT project to support army recruiting was having “teething” problems.

Now Hammond knows more, he says the problems are “big”. He no longer uses the “t” word. Speaking about the £440m 10-year Recruitment Partnering Project in the House of Commons this week Hammond said:

“Yes, there are big problems with the IT and I have told the House on repeated occasions that we have IT challenges…”

Only a few days ago Cabinet Office minister Francis Maude suggested that Government IT was no longer a byword for disaster, though he accepted there were still challenges.

In a speech on how he expected the UK to become the G8’s most digital government by next year (whatever that means) Maude said: “… it’s great news that DVLA is about to launch online driving records which can be used by anyone with a driving licence as well as by the insurance industry.

“Back in 2010 our digital offering was limited at best and government IT was a by-word for disaster … There are still challenges but with the help of the Government Digital Service I am determined that the UK will be the G8’s most digital government by next year.”

A few days later The Times reported on a leaked Gartner report on the army Recruitment Partnering Project. The report expressed concerns about the entire plan, including a poor project management team and delays that were allowed to spiral out of control.

It claimed that the Army’s recruitment division had failed to challenge MoD policy in 2011 that had apparently favoured the less suitable of the two competing bidders chasing the contract.

Hammond is said to be mulling over a £50m payout for Capita to build a new infrastructure for the recruiting system instead of trying to integrate it with systems supplied by the “Atlas” consortium under the Defence Information Infrastructure project. Hammond told the House of Commons this week:

“… there have been initial difficulties with that recruiting process as we transition to the new recruiting arrangements with Capita.

“In particular, we have encountered difficulties with the IT systems supporting the application and enlistment process. The decision to use the legacy Atlas IT platform was deemed at the time to be the quickest and most cost-effective way of delivering the new recruitment programme.

“An option to revert to a Capita hosting solution was included in the contracts as a back-up solution.

“I was made aware in the summer of last year that the Army was encountering problems with the integration of the Capita system into the Atlas platform. Since then we have put in place a number of workarounds and mitigation measures for the old IT platform to simplify the application process, and we have reintroduced military personnel to provide manual intervention to support the process.

“Having visited the Army’s recruitment centre in Upavon [Wiltshire] on 30 October, it became clear to me that, despite the Army putting in place measures to mitigate those problems in the near term, further long-term action was needed to fix the situation.

“It was agreed in principle at that point that the Atlas system was not capable of timely delivery of the Capita-run programme and that we would need to take up the option of reverting to Capita building a new IT platform specifically to run its system, which will be ready early next year.

“… we have already taken action to bring in a range of new initiatives that will make it progressively easier and quicker for applicants … the introduction this month of a new front-end web application for Army recruitment; a simplified online application form; more streamlined medical clearance processes …

“With an improved Army recruitment website, streamlined medicals and an increase in the number of recruiting staff, recruits should see a much-improved experience by the end of this month.

“.. we are looking at further ways of improving the management of the recruiting process in the intervening period before the introduction of the advanced IT system now being developed in partnership with Capita, which is expected to be deployed in February 2015…”

Vernon Croaker, Labour’s defence spokesman, said the recruitment project was an IT fiasco. He wondered why Hammond had initially described the problems as teething.

“Today we have learned [from newspapers] that the problems are even worse than anyone thought and still have not been fixed.

“Will the Defence Secretary tell the House which Minister signed off the deal and who has been responsible for monitoring it?

“… Will the Secretary of State also confirm that £15.5m has been spent building the existing flawed computer system behind the project? Finally, is it correct that this continuing disaster is costing taxpayers £1 million every month?…”

Croaker quoted a minister Andrew Robathan as telling MPs on 10 April 2013 that the “Recruiting Partnering Project with Capita…will lead to a significant increase in recruiting performance”.

Croaker said: “Is there any Member of this House, any member of our armed forces or, indeed, any member of the British public who still believes that?”

In March 2012 Capita announced that the Recruitment Partnering Project was valued at about £44m a year for 10 years and was expected to deliver benefits in excess of £300m to the armed forces. It would “release military recruiters back to the front line” said Capita.

Comment. Francis Maude is probably right: there don’t seem to be as many big IT-based project failures as in previous decades. But then the truth isn’t known because progress reports on big IT-related schemes are not published.

Indeed little would be known about the Capita Recruitment Partnering Project is not for the leaked report to The Times. Without the leak, public information on the state of the project would be confined to Hammond’s “teething problems” comment to MPs last November.

Internal and external reports on the state of the Universal Credit IT project continue to be kept secret.  It’s not even clear whether ministers are properly briefed on their big IT projects. Hammond almost certainly wasn’t last year. IDS was left to commission his own “red team” review of Universal Credit IT.

Perhaps the “good news” reporting culture in Whitehall explains why the NHS IT scheme, the NPfIT, continued to die painfully slowly for 7 years before senior officials and ministers started to question whether all was well.

Hammond is still getting wrong information. He described “Atlas” systems in the House of Commons as the “legacy IT platform”.

The Atlas contract for the Defence Information Infrastructure was awarded in 2005 for 10 years. It doesn’t even expire until next year. It may be convenient for officials to suggest that the reason Capita has been unable to link new recruitment systems into the DII network is because DII is old – legacy IT.  But the multi-billion pound Atlas DII project cannot be accurately described as “legacy” yet.

If ministers don’t get the truth about their big IT projects until serous problems are so obvious they can no longer be denied, how can Parliament and taxpayers expect to get the truth?

Lessons from NASA?

NASA put in place processes, procedures and rules to ensure engineers were open and deliberately adversarial in challenging assumptions. Even so it has had difficulties getting engineers to express  their views freely.

Diane Vaughan in her excellent book “The Challenger Launch Decision” referred to large organisations that proceeded as if nothing was wrong “in the face of evidence that something was wrong”.  She said NASA made a series of seemingly harmless decisions that “incrementally moved the space agency towards a catastrophic outcome”.

After the loss of Challenger NASA made many changes. But an investigation into the subsequent tragedy of the Columbia space shuttle indicated that little had actually changed – even though few of the top people who had been exposed to the lessons of Challenger were still in position.

If NASA couldn’t change when lives depended on it, is it likely the UK civil service will ever change?  A political heavyweight,  Francis Maude has tried and failed to get departments to be more open about progress or otherwise on their big IT-based projects.  Permanent secretaries now allow the out-of-date “traffic light” status of some projects to be published in the annual report of the Major Projects Authority. That is not openness.

The failure so far of the Recruitment Partnering Project, the routine suppression of information on technology-based scheme such as this, and the circumscribed “good news” briefings to ministers, suggest that government IT-based project failures are here to stay, despite the best intentions of the Cabinet Office, GDS and the Major Projects Authority.

Thank you to campaigner Dave Orr for his email on the recruitment project

Big 4 Universal Credit IT suppliers punished?

By Tony Collins

The  latest draft business case for Universal Credit suggests existing IT suppliers will have little to do with the “end-state digital solution” that is  due eventually to support the roll-out of UC.

The Department for Work and Pensions will use a mixture of its own and external people for the end-state digital solution.

Computer Weekly quotes part of the draft business case as saying:

“To extend the current IT solution we will be using a standard waterfall delivery approach largely using existing suppliers and commercial frameworks, in order to de-risk delivery and ensure UC continues to have a safe and secure introduction.

“The end-state digital solution will be delivered using an agile, and therefore iterative, approach as advocated by the Cabinet Office with significantly less reliance on the large IT suppliers delivering the current UC IT service.”

Politicalscrapbook.net picks up Computer Weekly’s report and says that Iain Duncan Smith “punishes Universal Credit IT suppliers“. 

Costs

Computer Weekly quotes the draft business case as putting the cost of the end-state solution at £106m – comprising external IT costs of £69m and in-house “Design and Build” team costs of £37m.

The total cost of UC IT is now put at £535m – down substantially on the £673m estimate in the DWP’s December 2012 UC business case.

UC project at “red” 

Yesterday the Guardian reported that Francis Maude and his team at the government digital service have objected to the twin-track approach to UC but were outflanked by “a majority” of other government ministers and project advisers, leaked minutes say.

The twin-track approach to UC IT means that the DWP and its main suppliers – HP, Accenture, IBM and BT – continue to develop existing systems (a blend of legacy and new technology) while a separate team develops a new “end-state” system for use by the end of 2017. It’s unclear how the two systems will differ. 

Computer Weekly quotes the latest draft business case as saying it is “unclear what the digital service will deliver and to what timescales”.

Due to the multitude of problems facing universal credit, the project has been coded “red” overall, according to the Guardian.

Comment

Computer Weekly has done well to gain sight of the latest draft business case for UC.

Whoever wrote the draft appears to accept the Cabinet Office’s case for departments to “move away from large ICT projects” and thus “reduce waste, provide a more flexible approach to complex business requirements that are likely to change over time and reduce the risk of project failures”. (National Audit Office, Universal Credit: early progress). 

But is the DWP simply telling the Cabinet Office what it wants to hear?  All the signs are that the big money at the DWP will continue to go to its main IT suppliers. 

The £106m agile “end-state digital solution” is a bonus system which may or may not materialise.  It is in essence a big, agile research project and the DWP is having trouble finding IT professionals to work on it.

If ever it’s a success it could start to replace existing UC IT in 2017 or beyond. But that may never happen. The DWP has already spent more than £300m on existing UC technology and is set to spend a lot more: around £90m. The DWP is unlikely to scrap it.

So HP, IBM, Accenture and BT are all but guaranteed a large income stream from the non end-state UC technology.

Even without the UC project the big 4 are guaranteed a large income from the DWP’s other work which includes:

– Personal Independence Implementation – 2.8bn 2011–2016
– Fraud and error programme – £770m  2012–2015
– Child maintenance group change 1.2bn 2009–2014
– Pensions reform Enabling Retirement Savings programme 1.04bn 2007–2018
– State Pension reform – single tier £114m 2012–2017
– Specialist Disability Employment programme – £203m 2012–2014

The big 4 will also continue to receive a large chunk of the DWP’s IT budget for maintaining and upgrading the existing software, hardware and networks.

Business cases are written by experts in the writing of Whitehall business cases.  Their main purpose is to provide a case for the Treasury to release funds for a project. They give current thinking on costs and benefits. The documents are revised when these change significantly.

So the statement in the UC draft business case that the new end-state digital solution will rely “significantly less” on existing UC IT suppliers means little: it is subject to change.

And the words “significantly less” are  unexplained. They may have no scientific basis. 

Worrying

The big 4 suppliers continue to be all-important to the DWP – and are so enmeshed that they decide at times how much they should be paid, suggests the NAO.

From its latest report on the UC project, the NAO comments on the DWP’s lack of control of suppliers :

– “In February 2013, the Major Projects Authority reported there was no evidence of the Department actively managing its supplier contracts and recommended that the Department needed to urgently get a grip of its supplier management.”

– “[The DWP has] limited IT capability and ‘intelligent client’ function leading to a risk of supplier self-review.”

– “[The DWP has] inadequate controls over what would be supplied, when and at what cost because deliverables were not always defined before contracts were signed.”

– “[The DWP has an] over-reliance on performance information that was provided by suppliers without Department validation.”

– ” … the Department did not enforce all the key terms and conditions of its standard contract management framework, inhibiting its ability to hold suppliers to account.”

So it would be naively optimistic to suppose that if the big 4 were to be frozen out of the end-state solution for UC that it would make much difference to their income from the DWP.      

UC in chaos or not?

A generous interpretation of all the available evidence on the UC project so far is that the DWP is working through, and understanding, the difficulties on an immensely complicated IT-enabled project.

And supporters of the twin-track approach could argue that two completely independent sets of teams are working in parallel and in discreet competition to produce the most successful system. One team comprises the big 4 using waterfall and the other a largely in-house team using agile.  Eventually one system will prevail, even if it’s 2020 or beyond that it handles securely online all types of claims. On completion the system will simplify benefit claims and cut the costs of administration.

A less generous interpretation of the available facts is that the UC IT project  is in chaos and that vast sums continue to be poured into a poorly formed strategy that nobody in government will concede is failing;  all parties are preoccupied with resolving problems as they arise and expecting irrationally that things will come good in the end.  Nobody should expect the full truth to emerge from those who have a deep interest in the project’s success including IDS and his permanent secretary Robert Devereux.

Howard Shiplee, head of the UC project, may still be getting his head around how chaotic things are. The highly capable David Pitchford, who headed UC  for a few months before he quit the civil service last year, came close to saying the project was in chaos. His Major Projects Authority said in February 2013 that the DWP needed to “rethink the delivery approach”, said the NAO.

Indeed the UC project shows many of the usual signs of a government IT-based project failure:

– major changes in the basic assumptions between the business case of December 2012 and the latest draft business case
– excessive secrecy (keeping secret a succession of internal and external reports on the project).
– defensiveness (continued DWP claims that problems are historic)
– a high turnover of leaders
– a culture of good news that “limited open discussion and stifled challenge”, said the NAO
– a lack of control of suppliers (NAO)
– repeated delays
– suppliers that get paid regardless of whether their systems are contributing to a  successful project.

To me things look chaotic but I hope I’m wrong. I’d like UC IT to work. IDS and Shiplee will probably know the whole truth – and they are still in post, to date.  If Shiplee leaves the project before the general election that could be an indication of how bad things really are.   

Top 5 posts on this site in last 12 months

Below are the top 5 most viewed posts of 2013.  Of other posts the most viewed includes “What exactly is HMRC paying Capgemini billions for?” and “Somerset County Council settles IBM dispute – who wins?“.

1) Big IT suppliers and their Whitehall “hostages

Mark Thompson is a senior lecturer in information systems at Cambridge Judge Business School, ICT futures advisor to the Cabinet Office and strategy director at consultancy Methods.

Last month he said in a Guardian comment that central government departments are “increasingly being held hostage by a handful of huge, often overseas, suppliers of customised all-or-nothing IT systems”.

Some senior officials are happy to be held captive.

“Unfortunately, hostage and hostage taker have become closely aligned in Stockholm-syndrome fashion.

“Many people in the public sector now design, procure, manage and evaluate these IT systems and ignore the exploitative nature of the relationship,” said Thompson.

The Stockholm syndrome is a psychological phenomenon in which hostages bond with their captors, sometimes to the point of defending them.

This month the Foreign and Commonwealth Office issued  a pre-tender notice for Oracle ERP systems. Worth between £250m and £750m, the framework will be open to all central government departments, arms length bodies and agencies and will replace the current “Prism” contract with Capgemini.

It’s an old-style centralised framework that, says Chris Chant, former Executive Director at the Cabinet Office who was its head of G-Cloud, will have Oracle popping champagne corks.

2) Natwest/RBS – what went wrong?

Outsourcing to India and losing IBM mainframe skills in the process? The failure of CA-7 batch scheduling software which had a knock-on effect on multiple feeder systems?

As RBS continues to try and clear the backlog from last week’s crash during a software upgrade, many in the IT industry are asking how it could have happened.

3) Another Universal Credit leader stands down

Universal Credit’s Programme Director, Hilary Reynolds, has stood down after only four months in post. The Department for Work and Pensions says she has been replaced by the interim head of Universal Credit David Pitchford.

Last month the DWP said Pitchford was temporarily leading Universal Credit following the death of Philip Langsdale at Christmas. In November 2012 the DWP confirmed that the then Programme Director for UC, Malcolm Whitehouse, was stepping down – to be replaced by Hilary Reynolds. Steve Dover,  the DWP’s Corporate Director, Universal Credit Programme Business, has also been replaced.

4) The “best implementation of Cerner Millennium yet”?

Edward Donald, the chief executive of Reading-based Royal Berkshire NHS Foundation Trust, is reported in the trust’s latest published board papers as saying that a Cerner go-live has been relatively successful.

“The Chief Executive emphasised that, despite these challenges, the ‘go-live’ at the Trust had been more successful than in other Cerner Millennium sites.”

A similar, stronger message appeared was in a separate board paper which was released under FOI.  Royal Berkshire’s EPR [electronic patient record] Executive Governance Committee minutes said:

“… the Committee noted that the Trust’s launch had been considered to be the best implementation of Cerner Millennium yet and that despite staff misgivings, the project was progressing well. This positive message should also be disseminated…”

Royal Berkshire went live in June 2012 with an implementation of Cerner outside the NPfIT.  In mid-2009, the trust signed with University of Pittsburgh Medical Centre to deliver Millennium.

Not everything has gone well – which raises questions, if this was the best Cerner implementation yet,  of what others were like.

5) Universal Credit – the ace up Duncan Smith’s sleeve?

Some people, including those in the know, suspect  Universal Credit will be a failed IT-based project, among them Francis Maude. As Cabinet Office minister Maude is ultimately responsible for the Major Projects Authority which has the job, among other things, of averting major project failures.

But Iain Duncan Smith, the DWP secretary of state, has an ace up his sleeve: the initial go-live of Universal Credit is so limited in scope that claims could be managed by hand, at least in part.

The DWP’s FAQs suggest that Universal Credit will handle, in its first phase due to start in October 2013, only new claims  – and only those from the unemployed.  Under such a light load the system is unlikely to fail, as any particularly complicated claims could managed clerically.

 

MP calls for candour after Cerner NPfIT go-live at Croydon

By Tony Collins

Richard Bacon, a long-standing member of the House of Commons’ Public Accounts Committee, has called on Croydon Health Services NHS Trust to be more open about problems it faces after deploying a Cerner Millennium patient records system at the end of September.

The installation was carried out by BT under the London Programme for IT – a branch of the NPfIT.  The Health and Social Care Information Centre, which has taken on BT and CSC contracts under the NPfIT, was the trust’s partner for the Cerner deployment.

Bacon has closely followed the NPfIT and written a chapter on it in his book, “Conundrum: Why every government gets things wrong and what we can do about it” which he co-wrote with Christopher Hope, the Telegraph’s senior political correspondent.

According to fragments of information in Croydon Health Services’ latest board papers, dated 25 November 2013, the trust has faced a series of problems after the NPfIT Cerner go-live.

They included:

–  N3 Network downtime and waiting time breaches.

 Excessive waits for patients in A&E

 Going over budget.

– Significant loss of income.

 A bid to recover Cerner costs.

– A need for HSCIC support for delays. 

-A need for extra investment in Cerner to “stabilise the operational position”

The trust has not published any specific report on the implementation’s problemsNow Bacon says it is “unacceptable for any trust not to disclose the problems it faces – and possibly patients face – after a major IT implementation such as Cerner”.

He adds:

“If these implementations go wrong they can affect the safety of patients.  We know this from some NPfIT deployments at other  trusts. For Croydon to say that board members have been kept informed of the potential risks of the Cerner implementation through the “Corporate Risk and Board Assurance Framework”  is not reassuring.

“This is putting a matter of importance in the small print. Indeed, for officials to brief board members on the potential risks, rather than actual events, is also of concern.

“Patients need to know that Croydon takes a duty of candour seriously. If the Trust cannot be open about its IT-related problems, how can we be sure it will be open about anything else to do with patient safety?”

Patient records go-live “success” – or a new NPfIT failure 

Patient records go-live “success” – or a new NPfIT failure?

By Tony Collins

John Goulston says the go-live of a new patient records system at his trust is a “success”.

He should know. He’s Chief Executive of Croydon Health Services NHS Trust. He’s also chair of the trust’s Informatics Programme Board which has taken charge of bringing Cerner Millennium to Croydon’s community health services and the local University Hospital, formerly the Mayday.

He was formerly Programme Director of the London Programme for IT at NHS London – a branch of the NPfIT.

In a report two weeks ago Goulston said the trust deployed the “largest number of clinical applications in a single implementation in the NHS”. Croydon went live with Cerner Millennium on 30 September and 1 October 2013.

Said Goulston in his report:

“Administrative functions do not engage clinicians; providing them with a suite of clinical functionality has been justified as each weekday approx. 1,000 staff are logged on and using the system. CHS [Croydon Health Services] has in Phase 1 deployed, in addition to patient administration, the largest number of clinical applications in a single implementation in the NHS England.”

BT helped install Millennium at Croydon under the National Programme for IT.  The trust’s spokesman says the Department of Health provided central funding, and the trust paid for implementation “overheads”.  The Health and Social Care Information Centre was the trust’s partner for the go-live.

The Centre is the successor for Connecting for Health. It has taken on CfH’s officials who continue to help run the NPfIT contracts with BT and  CSC.

Goulston said that Cerner and BT have paid tribute to the trust which installed Millennium in A&E, outpatients, secretarial support and cancer services, and elsewhere.

“Our partners Cerner, BT and Ideal have commented that the Trust has undertaken one of the most efficient roll-outs of the system they have worked on, with more users adopting the system more quickly and efficiently than other trusts … the success we have achieved to date is the result of the efforts of every single system user and all staff members,” said Goulston.

Best Cerner implementation yet?

Optimistic remarks about their launch of Cerner Millennium were also made in 2012 by executives at the Royal Berkshire NHS Foundation Trust.  Their optimism proved ill-judged.

Of the Millennium go-live at Royal Berkshire, trust executives said that it “had been considered to be the best implementation of Cerner Millennium yet and that despite staff misgivings, the project was progressing well”.   This positive message should be disseminated, they said.

Months later they told the Reading Chronicle of patient safety issues and a financial crisis arising from the Millennium implementation.

A Royal Berkshire governors Rebecca Corre was quoted as saying: “There is a patient safety issue when staff write down observations and then there is an hour before they can get it onto the computer. If it is an experienced nurse, they may pick up a problem, but others may not.”

Ed Donald, Chief Executive of Royal Berkshire was quoted as saying:

“Unfortunately, implementing the EPR [electronic patient record] system has at times been a difficult process and we acknowledge that we did not fully appreciate the challenges and resources required in a number of areas.”

Are executives and managers at Croydon Health Services NHS Trust  now similarly afflicted with an unjustified optimism about the success of their Cerner go-live?  

Past consequences of NPfIT go-lives hidden?

The Department of Health has claimed benefits for the NPfIT of £3.7bn to March 2012 but there have been trust-wide failures: thousands of patients have had their appointments, care or treatment delayed by difficulties arising from past implementations of patient record systems under the NPfIT.  For thousands of patients waiting time standards have been exceeded or “breached” because of disruption arising from troubled go-lives.

In nearly every case trusts made it difficult for the facts to come out publicly. Vague or unexplained fragments of information about the consequences of the NPfIT implementation appeared  in different board papers over several months. The facts only emerged after a journalistic investigation that required scrutiny of many board papers and follow-up questions to the trust’s press office.

So Campaign4Change investigated Croydon Health’s implementation of Cerner Millennium to see if the Francis report’s call for a “duty of candour” over mistakes and problems in the NHS have made any difference to the traditional fragmentation of facts after NPfIT go-lives of patient record systems.

The Francis report called for “openness, transparency and candour“.  Trusts were told not to hide sub-standard practices under the carpet. The health secretary Jeremy Hunt said it can be “disastrous” when bad news does not emerge quickly and the public are kept in the dark about poor care.

To my questions about the Cerner Millennium implementation Croydon trust’s spokesman always responded promptly and tried to be helpful. But it appears that trust executives have given him limited information about consequences of the go-live, and have preferred to indulge the “good news” NHS culture that Jeremy Hunt warned about.

On being asked what problems the trust has faced since the go-live the spokesman gave various answers that made no mention of the problems.

“All of our staff received training on the system, and we are continuing to offer our teams support as it is embedded.”

What of the problems arising from the implementation, and has the board been fully informed?

“Millennium has featured regularly on the Corporate Risk Register presented to each Part 1 Board meeting.   In addition, implementation has received detailed confidential consideration at Part 2 of Board meetings, (which is why you won’t find it in our public board papers).”

Given Francis’s call for duty of candour,  should the trust be more open about its problems?

“The initial roll out for CRS Millennium was introduced over three days at the Trust, with a phased approach.  We did this to ensure the system was working in each department, before introducing it in another area.

“We are monitoring waiting time performance and records management so we can identify any issues if they emerge. The system is still being introduced in some services and when this is completed we will be able to assess the overall programme,” said the spokesman.

Does Croydon’s unwillingness to give in its statements to me any details of problems indicate that the culture of a lack of transparency in the NHS will be hard to change, no matter how many times Jeremy Hunt talks about the need for candour when things go wrong?

The spokesman:

“I’d like to be clear about the Trust’s approach:

  • The Trust board has been cited on the roll out of CRS Millennium and any potential risks throughout the process.  As I previously noted, the board received an update in September.  The board meeting, which will take place on Monday of next week, will receive a further update from the Chief Executive.  The papers from this meeting will be published on our website and the meeting takes place in public;
  • A meeting chaired by the Chief Operating Officer has reviewed any operational matters arising on a daily basis.  This is an internal meeting for clinicians and managers which has informed the implementation process;
  • Patients and visitors to the hospital have been kept fully appraised of the introduction of the system and were made aware that they may experience some delays to the check-in process while staff became familiar with the new computer system;

“These actions would suggest that the Trust has been transparent in its approach.  You are welcome to review the board papers when they are published.”

Serious problems now emerge

Croydon did indeed publish its board papers on 25 November 2013 – which is to its credit because not all NHS trusts publish timely board papers.

But it’s mostly in the small print of various board papers that details emerge of Millennium-related problems. The shortcomings are mentioned as individual items rather than in a single, detailed Cerner Millennium deployment report.  This leaves one to question whether trust directors have an overview of the seriousness of the difficulties arising from its implementation of a new patient records system.

These are some excerpts from deep inside Croydon’s latest board papers:

Breaches in waiting time standards

– “CRS Millennium (Cerner) Deployment -Network downtime – Week 1.  In particular, the significant network downtime in week 1 (BT N3 problem) led to no electronic access to Pathology and Radiology which resulted in longer waits for patients in the Emergency Department (ED) leading to a large number of breaches. This was a BT N3 problem which has been rectified with BT providing CHS with the required scale of N3 access (>600 concurrent users and >1,600 users on any day – which is the largest network usage of any trust in England).”

– • “Hospital Based Pathways: The deployment of CRS Millennium was a particular challenge in the month across the multiple service areas within the Directorate of A&E, Surgery and Maternity.

• “Cancer & Core Functions: With the implementation of CRS Millennium, the open pathways part of RTT [referral to treatment – patient waiting times) may fail the standard – validation will be completed after the narrative for this report… “

Excessive waits in A&E

– “The main drivers adversely affecting the performance in the month [October 2013) for A&E were the deployment of CRS Millennium and the commencement of winter pressures due to the seasonality change.  A&E  4-Hour Total Time in Department Target: 95.00%. Actual: 91.57%.”

Over budget

“The Trust position as at October is an adverse variance of £4.1m. This is a significant deterioration on the Month 6 position. The movement is mainly due to a significant reduction in income mainly as a result of operating issues caused by the Cerner deployment (£0.9m)…  Actual £14.8 (£14.8)m; Budget £10.7m; Variance £4.1m.”

“Cerner Millennium: Plan YTD [year-to-date] £245,000; Actual YTD  £621,000;

Significant loss in income

“… A new patient administration system was deployed in the Trust on the 30th September and 1st October (Cerner Millennium). The deployment has resulted in significant loss in income in September and October £ 1.1m. Trust performance on Activity Planning Assumptions and Key Performance Indicators is substantially worse than plan …”

Extra costs

“Medical £412k and admin £148k agency levels continue to be high due to cover for vacancies, annual leave, sickness and release of staff for Cerner training. The Trust has also incurred additional costs associated with the Cerner deployment (£600k) including overtime payments to administration staff and training costs.”

Bid to recover Cerner costs?

“… The Trust is currently forecasting a deficit position of £17.8m, which is £3.3m off the plan submitted to the NHS Trust Development Authority. This is a £3m movement from the month 6 forecast and is as a result of operational issues caused by the Cerner deployment. The current projected impact is an additional costs £1.7m and a loss in activity £1.1m . An application is to be made to recover the additional cost/losses relating to the Cerner deployment [of £2.9m] …”

HSCIC support for delays

“Cerner Millennium – Revised implementation date to Sept 2013 (achieved) ,with resultant additional costs including additional PC requirements of £146k, specialist support services £300k, procurement costs £91k, data cleansing costs £200k.

“Health& Social Care Information Centre (HSCIC) has confirmed support for the delayed implementation will be provided, accounting treatment of support to be confirmed with Department of Health.”

More money to stabilise operational position?

“As a result of operational issues caused by the Cerner deployment , Income is significantly reduced in October. The forecast assumes that the Trust will resume normal operating levels from November and that an element of the income lost will be will be recovered in the latter part of the year. A business case is being submitted to the Trust Board for additional investment in Cerner to stabilise the operational position.

“If there are further operational issues due to the Cerner deployment then this will significantly impact on the year end forecast…”

Over-optimism?

Principal risk -reporting output from Cerner is not accurate or timely. Officer in charge: CEO. Before go-live risk scores: June 2013 – 16; July – 16; Aug  – 10; Sept – 10. After go-live risk score (for Oct): 20 [high risk of likelihood and consequences]

Principal risk – operational readiness following the implementation of Cerner. Officer in charge: COO.  Before go-live risk score 15. Post go-live: 20. Risk rating before go-live – Green. After go-live – Red.

Red risks

Corporate Risk Assurance Framework

Nine risks are reported as Red [two of which relate directly to Millennium]:

“… Reporting output from Cerner is not accurate or timely. Data migration was successful. However reliance on external provider as internal knowledge has not yet been fully gained. A data quality dashboard with exception reporting is in place.

“… Operational readiness following the implementation of Cerner CRS Millennium impact conveyed to Trust Development Authority e.g. ED [Emergency Department] reporting and cost overruns

Risk scores

– Failure of CRS millennium to deliver anticipated benefits – 12. Officer in charge: CEO

– Reporting output from Cerner is not accurate or timely – 20. Officer in charge: CEO

– Operational readiness following the implementation of Cerner – 20. Officer in charge: COO

Croydon’s trust’s response to problems

Said John Goulston, Croydon’s CEO, in his latest [November 2013] report to the board of directors:

“The issues being encountered now with CRS Millennium are not due to any lack of integration testing with legacy applications or testing of workflow. They can be attributed to changing from a 25 year old Patient Administration System (Patient Centre) which did not require working in real time, was simple and intuitive to use, easily configurable and flexible to our needs.

“CRS Millennium’s patient administration functions are almost the complete opposite and the language used is new for our staff i.e. conversations, encounters etc. For our staff it has been a big ask for them to step into and up to such a complex application.”

He added: “The benefits of the new system are that each patient will have a single accurate electronic record that can be viewed and kept up-to-date by hospital and community clinical staff. This will eventually mean less time searching for patient notes, missing documentation and duplicating patient information…

“As with any massive change, there are still some challenges to tackle in making the system work effectively for every single user, in a diverse and complex organisation.

“However the success we have achieved to date is the result of the efforts of every single system user and all staff members. I would like to thank all our staff for their hard work in getting the Trust to this important stage.”

The trust spokesman gave me this statement on the problems:

“The Trust board has been given regular reports on the roll out of CRS Millennium and any potential risks throughout the process, not least through its regular reviews of the Corporate Risk and Board Assurance Frameworks.  As I previously noted, the board received a specific update in September.

“As you already know, November’s board meeting received a further update from the Chief Executive.  The papers from this meeting were published and the meeting takes place in public;  Those attending are invited to put forward questions.

“A meeting chaired by the Chief Operating Officer continues to review operational matters.  This is an internal meeting for clinicians and managers which has informed the implementation process;

“Patients and visitors to the hospital have been kept fully appraised of the introduction of the system and were made aware that they may experience some delays to the check-in process while staff became familiar with the new computer system;

“As you highlight from the board report, Cerner & BT noted that ‘the Trust has undertaken one of the most efficient roll-outs of the system they have worked on’   The papers also note some operational challenges as the system was rolled out.  These have been addressed as part of the daily meetings I reference above – these are mainly concerned with users familiarising themselves with the system and have been addressed through the support and training staff received.

“In terms of the costs, the introduction of CRS Millennium has been supported by central funding from the Department of Health with the Trust paying the implementation overheads.   These costs are a matter of public record and the Trust publishes annual Accounts as part of its Annual Report.”

Comment

When you go into hospital it’s reassuring to know the directors will be well informed and open about problems that could affect you.

The approach of Croydon Health Services NHS Trust to openness about its problems is not reassuring. It is no better or worse than other trusts that have implemented Cerner’s Millennium. In fact the timely publication of its board papers means it is more open than some.

But it should not require a time-consuming journalistic investigation to establish the consequences for patients of an NPfIT go-live. It has required just such an investigation after the go-live of Millennium at Croydon.

Board directors will not have the time to dig for, and piece together, information about internal problems that could delay patient appointments, treatment and care. They need the unpalatable facts in one place. Croydon Health Services has failed to make it easy for patients or board directors to see what has gone wrong.

NPfIT deployments at other trusts have led, cumulatively, to thousands of patients having appointments that were disrupted, or who had to wait longer to be seen than necessary, or whose records were not available, or who were seen with another patient’s records.

In shying away from telling the whole truth trusts take their cue from the top: the Department of Health has always made it hard to establish facts about anything to do with the NPfIT.  Said the Public Accounts Committee in its report The National Programme for IT in the NHS: an update on the delivery of detailed care records systems in July 2011:

 “It is unacceptable that the Department [of Health] has neglected its duty to provide timely and reliable information to make possible Parliament’s scrutiny of this project.

“Basic information provided by the Department to the National Audit Office was late, inconsistent and contradictory.”

Unanswered questions

Croydon has questions to answer, such as how many breaches of waiting time standards it has had, and may still be having, due to problems arising from the go-live. Other unanswered questions:

– What does a “a large number of breaches” in the Emergency Department mean? Have each the patients affected been told?

– Why are the risks related to the implementation much higher after go-live than before, given that the trust has had years to prepare for the go-live, and the many lessons it could have learned from other trusts?

– Exactly what problems are still affecting patients?

In a post-Francis NHS, Jeremy Hunt has demanded openness about mistakes and problems. There is an agreed need for change – but how can Hunt change an NHS culture – indeed a public sector culture – in which senior executives, in troubled IT implementations, will always emphasise the good news over the bad, perhaps hoping the bad will always remain hidden?

DWP drops claim Universal Credit is on time

By Tony Collins

For  more than a year the DWP press office has countered articles on Universal Credit’s IT project problems with the claim that the scheme is on time and to budget. Spokespeople for the department have said each time that Universal Credit will be fully delivered by the end of 2017.

Now it has dropped the claim.  Today the DWP says in a press release that “most” of the existing benefit claimants will be moved over to Universal Credit during 2016 and 2017.  

On the advice of Universal Credit project lead Howard Shiplee the DWP is pressing ahead with the existing IT and “enhancing” it rather than starting anew. 

Says the DWP:

The next stage of delivery of Universal Credit will concentrate on the continued safe and secure roll out of the vital reform… 

As announced in July, the department has been working in conjunction with the Government Digital Service to explore an enhanced IT system for Universal Credit that uses the latest in technological advances.

“Today, ministers confirm that this system has proved viable and the department will further develop this work with a view to rolling it out once testing is complete.

“While this work is undertaken, Universal Credit will continue to expand. It is now live in 7 areas across the country, growing to 10 by spring 2014. From there, the roll out will expand beyond the existing single claimant group, to new claims from couples and families in all of these areas.

“By the end of next year, Universal Credit will start also to expand to cover more of the north-west. Universal Credit will therefore expand in scope and scale over the next 2 years.

“Pressing ahead with the existing system while the enhanced IT is being developed will allow for greater understanding of how individuals in different circumstances interact with Universal Credit. It also allows higher volumes of people to benefit from the better work incentives that come with the new benefit. Importantly, this approach will still allow the Universal Credit programme to roll out within the original budget.”

Work and Pensions Secretary Iain Duncan Smith said:

“This is a once in a generation reform. And we’re going to get it right by bringing it in carefully and responsibly.

“Our approach will ensure that while we continue to enhance the IT for Universal Credit, we will learn from and expand the existing service, so that we fully understand how people interact with it, and how we can best support them.
Early indications show that people are positive about the new benefit, and my department is working hard to ensure this good progress continues.

“Current plans will see new claims to existing benefits closed during 2016. This will mean that all new benefit claimants across the country will claim Universal Credit instead of the legacy benefits like Jobseeker’s Allowance or Housing Benefit…

“Decisions on the later stages of Universal Credit roll out will also be informed by the completion of the enhanced IT and these decisions will determine the final details for how people transition to the new benefit.

“The overriding priority throughout will be continued safe and smooth delivery and, as recommended by the Public Accounts Committee in their recent report on Universal Credit, this will take precedence over meeting specific timings.”

Comment 

Can the public and Parliament trust anything the DWP says about the progress on major IT-based projects? Those working on Universal Credit have known for 18 months that the project has been in trouble, but this has been repeatedly denied by DWP spokespeople who have insisted the scheme is on budget and on time to be fully completed by the end of 2017.

We know from the National Audit Office that the IT is not within budget and today we have the DWP’s admission that the programme will not be complete by the end of 2017 – something Campaign4Change and other sites have posted articles on for more than a year.

DWP’s over-optimism

“We will implement Universal Credit on time by 2017 and within budget – our plan is achievable.” – DWP in September 2013.

The DWP spokesperson added (September 2013) 

“We are committed to delivering Universal Credit on time by 2017 and within budget, and under new leadership we have a plan in place that is achievable.”

A DWP spokesperson told ComputerworldUK in September 2013:

“We are committed to delivering Universal Credit on time by 2017 and within budget, and under new leadership we have a plan in place that is achievable.”

It’s likely that Howard Shiplee has reported to IDS on what can and cannot be achieved by the end of 2017. He might have detailed the many IT-related uncertainties that still exist. But his report has not been published. The DWP doesn’t publish any reports on the progress or otherwise of its IT-related projects.

So will the DWP ever be open about its IT-enabled projects and programmes? Or will it continue to deny problems, write-offs and mistakes until they are only too obvious to be denied?  

Since the 1980s the DWP has been writing off tens of millions on failed IT projects. The Department may continue to have costly failures while its officials can easily keep the problems detailed in internal reports  hidden until they have moved on.

Will truth ever be told when things go wrong?

By Tony Collins

Cabinet Office minister Francis Maude has criticised civil servants who don’t always tell ministers what is going on in their departments. He used the Universal Credit project as an example.

He told the Financial Times: “There were a lot of failures in DWP and it isn’t good that it took a review commissioned . . . by the secretary of state to disclose what was going on.”

He added:

“You’ll find a lot of ministers don’t know a lot of things going on in the department because there’s no way you’ll find out.”

Maude’s comments touch on a common factor in IT-related project disasters in government – that ministers get mostly “good news” from their officials, and learn little or nothing about the seriousness of problems until a debacle is only too apparent to be denied.

But can ministers or the boards of large private companies ever expect their senior staff to be the bearers of bad news?

The Performing Right Society did not find out the truth about its failing IT-based project until it appointed a new head of IT who had no emotional equity in what had gone on before. [Crash – chapter 1)

The National Audit Office report “Universal Credit: early progress” referred to a “good news” culture at the Department for Work and Pensions that “limited open discussion of risks and stifled challenge”.

Ministers in charge of the Rural Payments Agency’s Single Payment Scheme said they were kept in the dark about the seriousness of IT-related problems. “When delays occurred, many stakeholders only found out at the last minute,” said a report of the Public Accounts Committee.

“Conspiracy of optimism”

The PAC report of March 2007 is worth a further mention:

“Lord Bach [minister in charge of the Single Payment Scheme] told us that he felt very let down by the advice he had received from the RPA [Rural Payments Agency], upon whom he said the Department relied very heavily in these circumstances, and the “conspiracy of optimism” on the part of the Agency.”

Lord Bach told MPs that he kept being told by officials that all was well.

“I frankly have to say that I do not think that that was satisfactory from senior civil servants whose job is to tell ministers the truth.”

Let down by civil servants – Universal Credit

Now the FT reports that Francis Maude has “entered the controversy over the implementation of the government’s universal credit scheme”. Maude told the FT he believed that Iain Duncan Smith, the work and pensions secretary, had been let down by his civil servants.

Maude said senior civil servants in charge of projects should tell ministers bluntly if they felt they were being misdirected and insist on a formal “letter of direction” to show that they had raised their objections. If they did not, they should be accountable for failings on their watch.

Maude did not comment directly on whether Robert Devereux, the top official in Mr Duncan Smith’s department, should take the rap for the much-criticised implementation of universal credit, but said: “I think everybody has to take responsibility for what they were part of”.

SROs accountable to MPs?

He suggested that civil servants who are in charge of big projects, known as senior responsible owners (SROs), should account directly to parliament, which would “toughen the relationship with ministers” and give officials a greater incentive to challenge developments they believed were wrong.

He said: “If you have an SRO who knows that he or she is going to be hauled up in front of select committees and interrogated . . . then I think you’re much more likely to have what is a very healthy thing in our system which is push-back. . . There’s a great phrase ‘speaking truth unto power’ and it’s very important – it doesn’t happen enough.

He added: “I’ve never had a civil servant come to me and say ‘Would you like us to stop doing this?’ The answer might easily be, ‘yes’.”

Comment:

Do ministers and boards of large private companies always have to commission their own independent reports to find out if their organisation’s biggest IT-based projects are failing? Probably.

The problem is not one of lying. Civil servants tend not to lie. Neither do senior executives when reporting to their boards. But the sin of omission – the art of not telling the truth while not lying – is well practiced in public life.

A succession of IT-based project disasters in the US, Australia and the UK show that truth is the first casualty of any large failing IT-based project.

Barnet Council and Capita

It’s isn’t just IT-based projects that bring out the sin of omission. Outsourcing deals do too. Barnet Council’s outsourcing deal to Capita is mired in controversy over truth.

Why did Barnet’s officials give Capita £16m after saying that the council had no spare cash, and that Capita would make the necessary upfront IT investments?

Officials have given a long-winded explanation which is a little like the drawn-out, incomprehensible explanation a six year-old may give in the playground when teacher asks why he took his friend’s bar of chocolate.

Liverpool LDL, BT and excessive mark-ups?

Liverpool Direct Ltd, a joint venture between Liverpool council and BT, is also mired in a controversy over truth. According to the Liverpool Daily Post, Local Government Minister Brandon Lewis has questioned whether LDL is proving value for money. There are allegations of excessive mark-ups on IT and services supplied by BT to the council.

It seems that BT makes a mark-up on what it supplies to LDL and LDL makes a further mark-up on what it supplies to the council.

But a council spokesperson said: ““The mark up incorporates a calculation of the cost of setting up a particular piece of hardware or software by LDL. The important figure is the profit after tax per item which is much lower, and on some items, LDL actually makes a loss.”

The minister said Liverpool Council needed to open up its books if it wants to insist it gets value for money from the BT deal. Will Liverpool Council open up?

Hardly.

Politicise parts of the civil service?

There is a strong argument for politicising the top echelons of the civil service so that ministers are not so reliant on officials who are thought to be neutral but evidence shows can be biased towards good news and suppressing the bad.

Ministers and boards of large companies do not need various versions of the truth when things go wrong. They need their own version.

As Richard Nixon said when accepting the presidential nomination in 1968 [pre-Watergate]:

“Let us begin by committing ourselves to the truth—to see it like it is, and tell it like it is—to find the truth, to speak the truth, and to live the truth.”

Doubtless Nixon believed it when he said it. Just as countless officials and executives in public and private life believe they are speaking the truth when they ministers and boards on their big IT-based projects. It may be the truth. But how much of it are they telling?

Update:

In a tweet BrianSJ3 makes a great suggestion: Genchi Genbutsu – “go and see for yourself” he says.

Did DWP mislead MPs and media over Universal Credit?

By T0ny Collins

Today’s report of the all-party Public Accounts Committee “Universal Credit: early progress” goes beyond criticisms of the scheme in a National Audit Office report of the same name on 5 September 2013.

Public Accounts MPs say the Department for Work and Pensions gave “misleading interviews to the press regarding progress after it became aware of difficulties with the programme”.

And as recently as July 2013 the “Department denied that there were problems with the programme’s IT when it gave evidence to the Work and Pensions Committee”.

These criticisms are against a background of the DWP’s refusal to publish any of the many internal and external reports the department has commissioned on the project’s progress, problems and challenges since 2011.

The Times today says that work and pensions secretary Iain Duncan Smith and members of his parliamentary team are “understood to have approached at least three Tory MPs on the cross-party [Public Accounts] committee to ask them to ensure that Robert Devereux, Permanent Secretary at the Department for Work and Pensions, was singled out for censure”.  In the end there was only limited criticism in the PAC report of Devereux – under his formal title of “Accounting Officer”.

Comment

If the DWP has been misleading the press, giving incorrect evidence to Parliament, and keeping secret its reports on the problems and challenges facing one of the government’s most important IT-based programmes – all of which seem to be the case – is it an institution that regards itself as uniquely outside the democratic process?

On big IT projects, officials are not motivated by money and concern for their jobs as are private sector boards of directors. When a private company gets it wrong and loses tens of millions on a project, the share price may fall, individual bonuses may be hit, and jobs, including the CEO’s, may be at risk.

In the public sector getting it wrong rarely has any implications for officials. They have only the threat of departmental embarrassment as a deterrent to getting it wrong. But they need not fear even embarrassment if they can mislead the press and Parliament and keep secret all their internal and external reports.

If a lack of transparency, culture of denial, and the misleading of Parliament continue to characterize big risky IT-based ventures in central government, one has to ask whether Whitehall is congenitally ill-suited to running such programmes.

The Public Accounts Committee warned in a report in 1984 about the risks of large public sector computer programmes. That report came after a series of project disasters.

So what has been learned in the last 30 years – other than that central departments are poorly equipped managerially – or democratically – to handle big IT-based programmes and projects?

These are some of the Public Accounts Committee’s findings:

MPs try to be positive

“We believe that meeting any specific timetable is less important than delivering the programme successfully. There is still the potential for Universal Credit to deliver significant benefits, but there is no clarity yet on the amount of savings it will achieve.”

Culture of denial

“The programme had also developed a flawed culture of reporting good news and denying that problems had emerged. This culture resulted from the desire of senior staff within the programme to show publically that they were able to push the programme forward, at the expense of ensuring that adequate controls were in place or listening to concerns raised about its delivery.

“Although the Department has tried to tackle this culture, it gave misleading interviews to the press regarding progress after it became aware of difficulties with the programme, and as recently as July 2013 the Department denied that there were problems with the programme’s IT when it gave evidence to the Work and Pensions Committee.”

Shocking absence of control over suppliers

“There has been a shocking absence of control over suppliers with the Department neglecting to implement basic procedures for monitoring and authorising expenditure…

“The Department recognises its supplier management has been weak, risking value for money.  Four main suppliers – Accenture, IBM, Hewlett Packard and British Telecom – have provided IT systems for Universal Credit, and by March 2013 the Department had paid them £265m out of the £303m spent with suppliers on IT systems.

“In February 2013 the Major Projects Authority found no evidence of the Department actively managing its supplier contracts, resulting in suppliers being out of control and financial controls not being in place.  The Department has yet to provide a comprehensive assessment of how much of this expenditure has proved nugatory, although the Major Projects Authority believes it will be a substantial figure running into hundreds of millions of pounds.”

Lack of oversight

The lack of oversight allowed the Department’s Universal Credit team to become isolated and defensive, undermining its ability to recognise the size of the problems the programme faced and to be candid when reporting progress…

“Oversight has been characterised by a failure to understand properly the nature and enormity of the task, a failure to monitor and challenge progress regularly, and a failure to intervene promptly when problems arose.

“Senior managers only became aware of problems through ad hoc reviews, mostly conducted by external reviewers, as inadequate management information and reporting arrangements had not alerted them that things were amiss.

“Given its huge importance to the Department, the Accounting Officer [Robert Devereux] and his team should have been more alert to identifying and acting on early warning signs that things were going wrong with the programme

Blinkered culture remains?

“Risk was not well managed and the divergence between planned and actual progress could and should have been spotted and acted upon earlier. The Department only reported good news and denied the problems that had emerged. The risk of a similarly blinkered culture remains as the Department will be working to tight timescales to get the programme back on track.”

Problems hidden

“It is extremely disappointing that the litany of problems in the Universal Credit Programme were often hidden by a culture prevalent in the Department which promoted only the telling of ‘good news’.

“For example, officials were aware that a critical report highlighting many of these issues had been discussed internally for months. Indeed, there are real doubts over when officials became aware of these problems and it is difficult to conceive, based on the evidence we were presented with, that officials within the Department did not know of them before July 2012.”

Shocking absence of financial and other controls

“There has been a shocking absence of financial and other internal controls and we are not yet convinced that the Department has robust plans to overcome the problems that have impeded progress.”

Did the DWP do anything well?

“The Department initially adopted a piecemeal approach to delivering the programme.

“In 2011 it identified over a hundred different types of users for Universal Credit, and initially sought to design IT solutions for each set of circumstances individually. It was only in early 2012 that the Department decided to stand back and try to establish a clearer picture of what the programme’s overall shape might look like.

“During the summer of 2012 the Department became aware of the problems that Universal Credit faced. It was first alerted by concerns raised in a supplier-led review, commissioned by the Secretary of State, which reported in July.

“The Department subsequently established that the programme’s progress was stalling because there were a number of unresolved issues which had become intractable, particularly relating to the level of security needed for identity assurance and protection against fraud and error and cyber-attack.

“The Department had been previously unaware of the programme’s difficulties because its internal lines of monitoring, intervention and defence, intended to identify and mitigate such problems, were not working properly. Governance arrangements were not remotely adequate, and the Accounting Officer [Robert Devereux] discussed progress with the head of the Universal Credit programme only every two or three weeks.

“The Department had inadequate performance information to scrutinise and challenge the programme’s reports of its progress, so internal reporting arrangements did not flag up that things were amiss. The Department’s corporate finance undertook insufficient work to ensure there was an appropriate control environment in place, and the Department’s process for ministers to sign-off higher-value contracts was weak.

“The Department’s senior management had relied on ad hoc reviews, mostly conducted by external reviewers, which only provided an occasional snapshot of the programme, instead of ensuring effective internal systems were in place to monitor and challenge progress. However, during 2012 the problems surfaced more clearly as the Universal Credit team became unable to respond to recommendations made by such reviews.”

Will Universal Credit ever work?

“The Department remains uncertain about key details of its final plans. It does not know how much can be delivered online, when this will be available, and what activities will continue to require face-to-face meetings.

“ The Department also does not know what the final cost of the IT will be, or the savings the programme is expected to deliver. Nor does it know when it will close down the other benefits that Universal Credit will replace.”

The Department has a target of enrolling 184,000 claimants on Universal Credit by April 2014 and has launched limited pilot schemes.”

Says the PAC report: “The current rate of progress is significantly below target, however. Only around 2,500 claimants were registered at the time of our hearing in September, and the Department was unwilling to speculate what number will be enrolled by next April.”

In a steady state Universal Credit is expected to deal with 10 million people in about 7.5 million households, making 1.6 million changes in circumstances each month.

Security versus usability

“The Department is aware that the system must include suitable security arrangements if Universal Credit is to operate effectively and deliver its intended benefits.  However, the Department has not yet finalised such a solution, and was unable to say when two key components – those countering fraud and error and confirming claimants’ identity- would be completed.

“The Department has found it particularly hard to establish the right balance between security and usability. The development of an effective security system has been hindered by security not being integral to the design of IT components from the outset, but instead being retro-fitted into systems, and suppliers working on different assumptions and to different standards. To address this, the Department told us it has now brought security issues together in one place, with one senior official responsible for overseeing this part of the programme.”

DWP response to PAC report

A Department for Work and Pensions spokesperson told the BBC

“This report doesn’t take into account our new leadership team, or our progress on delivery,” it said. “We have already taken comprehensive action including strengthening governance, supplier management and financial controls.”

The DWP said it did not accept “the write-off figure quoted by the committee” and expected it to be substantially less”.

A spokesman for Iain Duncan Smith told the BBC that he had “every confidence” in the team now running the programme, including Mr Devereux – whose position  some newspapers have suggested is under threat.

“Both the National Audit Office and the public accounts committee acknowledged a fortress mentality within the Universal Credit programme,” he said.

“Iain was clear back in the summer about how he and the permanent secretary took action to fix those problems.”

PAC report: Universal Credit: early progress

National Audit Office report: Universal Credit: early progress