Category Archives: Infrastructure and Projects Authority

Goodnewspeak and its Orwellian dark side

By Tony Collins

Orwell made no mention of goodnewspeak. But maybe today it’s an increasingly popular descendant of  Newspeak – a language devised by Orwell to show how the State could use words and phrases to limit thought.

This week, as a statue of Orwell was unveiled outside the BBC, a local council in Sussex made an announcement that was a fine example of goodnewspeak.

This was Horsham District Council’s way of not saying that it was scrapping weekly rubbish collections.

This was the benign side of goodnewspeak. The dark side is a growing acceptance in Whitehall, local authorities and the wider public sector that nothing negative can be thought of let alone expressed at work.

This suppression of negative thoughts means that the rollout of Universal Credit can be said officially to be going well and can be speeded up  despite the clamour from outsiders, including a former Prime Minister (John Major), for a rethink to consider the problems and delays.

[Labour MP Frank Field said last month that the DWP was withholding bad news on Universal Credit.]

It means that the Department for Business, Energy and Industrial Strategy can continue to praise all aspects of its smart meters rollout while its officials keep silent on the fact that the obsolescent smart meters now being installed do not work properly when the householder switches supplier.

It means that council employees can think only good about their major IT suppliers – and trust them with the council’s finances as at Barnet council.

[Nobody at Barnet council has pointed out the potential for a conflict of interest in having outsourcing supplier Capita reporting on the council’s finances while having a financial interest in those finances. It took a local blogger Mr Reasonable to make the point.]

Goodnewspeak can also mean that public servants do their best, within the law, to avoid outside scrutiny that could otherwise lead to criticism, as at Lambeth council.

Last month Private Eye reported the results of a “People’s Audit” in which local residents asked questions and scrutinised the authority’s accounts. The audit found that:

 – The number of managers earning between £50,000 and £150,000 has increased by 88, at a cost of more than £5.5m year.
-Spending on Lambeth’s new town hall has gone from a projected £50m to £140m.
– The council “invested” a total of £57,000 on its public libraries last year – closing three of them – while spending £13m on corporate office accommodation.
-£10.3m was spent making people redundant.

These disclosures (and there are many more of them) raise the question of what Lambeth is doing to dispel the impression that it manages public money badly and that its decisions could be routine in the world of local authorities.

Lambeth council’s reaction to the audit was to denounce it and issue its own goodnewspeak statement; and it is considering a proposal to lobby the government to allow councils to ban such People’s Audits in future.

Lambeth’s website, incidentally, is entitled “Love Lambeth”. Which, perhaps, shows that its leaders have, at least, a deep sense of irony.

Whitehall

The following lists of announcements on the websites of the Department for Work and Pensions and the Department of Transport are examples of how goodnewspeak manifests itself in Whitehall:

And the Department of Transport’s website:

Ministry of Truth

Orwell wrote in Nineteen Eighty-Four of the Ministry of Truth whose expertise was lying, the Ministry of Peace which organised wars and the Ministry of Plenty which rationed food.

Some of the Party’s slogans were:

War is peace.
Freedom is slavery.
Ignorance is strength.

And Orwell, whose wife worked at the Ministry of Information at Senate House, London (Orwell’s model for the Ministry of Truth) said,

“If you want to keep a secret, you must also hide it from yourself.”

Comment

Of course goodnewspeak doesn’t exist as a policy anywhere. But its practice is all-pervasive in the public sector. And it seems to change the way people think when they’re at work.

It blocks out any view other than the official line.

In Nineteen Eight-four, Orwell created “Newspeak” as a language of the Party to coerce the public to shape their thoughts around the State’s beliefs. Its much-reduced vocabulary stopped people conceiving of any other point of view.

Not using Newspeak was a thoughtcrime. The Party advocated Duckspeak – to speak without thinking – literally quack like a duck.

Has this already happened in a minor way at Barnet? A council document on the benefits of its outsourcing policies was peppered with abstractions that could have been constructed by software-driven random-phrase generators:

“Ahead of the game”
“Top to bottom organisational restructure”
“Flexibility to meet future challenges whilst ensuring we provide excellent services to residents today.”
“Root of our success”
“New solutions to complex problems”
“Pioneering partnerships”
“Investing for the future”
“Protect what makes Barnet such a great place to live”
“Increasing resident satisfaction”
“Paying dividends”
“Prepared for the future”
“Great strides”
“A radical, ‘whole place’ approach to designing and providing services”
“We have not been backwards in coming forwards”
“Pursuing alternatives to the norm”
“Vision into reality”
“Frame our future strategic direction”
“Future Shape”
“Drivers for change”
“Genuine innovation in Local Government”
“Bold in its decision making”
“Forward looking change strategy”
“A new relationship with citizens”
“A one public sector approach”
“A relentless drive for efficiency”
“Focus on stimulating the market”
“Best in class’ range of tradable services to win and deliver work for other authorities.”
‘Form follows function’.
“Clear roles and responsibilities”
“An internal escalation model”
“Renewed focus on improving engagement”
“Increasing transparency, and developing trust”
“Connect with people and build relationships of trust”
“A steep demand line to climb”

Dark side

One worrying consequence is that Whitehall civil servants and public servants and ruling councillors at, say Barnet and Somerset councils (and even at Cornwall), made the assumption that their IT suppliers shared the public sector’s goodnewspeak philosophy.

But suppliers are commercially savvy. They don’t exist purely to serve the public. They have to make a profit or they risk insolvency.

For years, goodnewspeak at Somerset County Council led to officers and councillors regularly praising the successes of a joint venture with IBM while covering up the problems and losses, in part by routine refusals of FOI requests.

Goodnewspeak at Liverpool Council meant that its officials had nothing but praise for BT when they ended a joint venture in 2015. They said that ending the joint venture would save £30m. But the joint venture itself was supposed to have saved tens of millions.

Somerset County Council made a similar good news announcement when it terminated its joint venture Southwest One with IBM.

Such announcements are consistent with Newspeak’s “Doublethink” – the act of simultaneously accepting two mutually contradictory beliefs as correct.

DWP

Outsiders can find goodnewspeak shocking. The Daily Mirror reported on how the DWP celebrated the rollout of Universal Credit at Hove, Sussex, with a cake. Were managers mindful of the fact that some failed UC claimants have been driven to the brink of suicide?

Disillusioned

Francis Maude, when minister for the Cabinet Office, was almost universally disliked in the civil service. He was an outsider who did not accept the Whitehall culture.  Even though he believed the UK had the best civil service in the world, he did not always show it.

He tried to reduce Whitehall spending on IT projects and programmes that could not be justified. He spoke an IT supplier oligopoly.

Now he has left government, most of his civil service reforms (apart from the Government Digital Service) have settled back to how they were before he arrived in 2010.

In a speech last month, Maude spoke of a “distressing” disillusionment with the civil service culture. He said:

“Based on my experience as a Minister in the eighties and early nineties my expectations (of the civil service) were high. And the disillusionment was steep and distressing.

“It remains my view that we have some of the  very best civil servants in the world … But the Civil Service as an institution is deeply flawed, and in urgent need of radical reform.

” And it is civil servants themselves, especially the younger ones, who are most frustrated by the Service and its culture and practices.”

World’s best civil service

He added that, as the new minister responsible for the civil service, every draft speech or article presented to him started: ‘The British Civil Service is the best in the world.’

But complaints by ministers in all parties about the lack of institutional capability, inefficiency and failed implementation were legion, he said.

“When we queried the evidential basis for this assertion, it turned out that the only relevant assessment was a World Bank ranking for ‘government effectiveness’, in which the UK ranked number 16.”

Speaking the unsaid

Perhaps more than any former minister, Maude has expertly summarised the civil service culture but in a way that suggests it’s unredeemable.

“I and others have observed that all too often the first reaction of the Civil Service when something wrong is discovered is either to cover it up or to find a scapegoat, often someone who is not a career civil servant and who is considered dispensable.
“There seems to be an absolute determination to avoid any evidence that the permanent Civil Service is capable of failure.
“Another indicator is that if a Minister decides that a Civil Service leader is not equipped for his or her task, this has to be dressed up as “a breakdown in the relationship”, with the unspoken suggestion that this is at least as much the fault of the Minister as of the civil servant.
“It can never be admitted that the mandarin was inadequate in any way.
“When I suggested that there might be room for improvement, the distinguished former Civil Service Head, Lord Butler, accused me of a failure of leadership. Actually the leadership failure is to pretend that all is well when no one, even civil servants themselves, really believes that.

The good news

All is not lost – thanks to a vibrant and investigative local press in some areas and resident auditors such as Mr Reasonable, Mrs Angry, David Orr, Andrew Rowson and the people’s auditors in Lambeth.

Along with the National Audit Office and some MPs, these resident auditors are the only effective check on goodnewspeak. They are reminder to complacent officialdom that it cannot always hide behind its barrier of unaccountability.

Long may these dogged protectors of the public interest continue to highlight financial mismanagement, excess and self-indulgent,wasteful decisions.

Earlier this year Nineteen Eight-Four hit the No 1 spot in Amazon’s book sales chart.

Perhaps copies were being scooped up by shortlisted candidates for top public sector jobs as vital homework before falling in with the culture at their interviews.

**

Outside the BBC, Orwell’s new statute is inscribed with a quotation from a proposed preface to Animal Farm that was never used:

“If liberty means anything at all, it means the right to tell people what they do not want to hear.”

Thank you for David Orr, one of the dogged local resident auditors referred to above, for drawing my attention to some of the articles mentioned in this post.

DWP good news announcements

Newspeak

Whitewashing history in education

 

Advertisements

A proposed Bill and charter that could change the face of Whitehall IT and save billions

By Tony Collins

A government-commissioned review yesterday backed a Bill that could, if enacted and applied to Whitehall generally, prevent billions of pounds being lost on wasteful projects.

The Public Authority Accountability Bill – known informally as the Hillsborough Law – would establish an offence of intentionally or recklessly misleading the public, media or court proceedings.

It would also impose a legal requirement on public authorities to act with candour, transparency and frankness when things go wrong.

Although the Bill was a reaction, in part, to the cover up by public authorities of their failings in the light of Hillsborough, it could, if enacted, deter public authorities from covering up failings generally – including on major IT programmes.

For decades public authorities have had the freedom – unrestricted by any legislation – to cover up failures and issue misleading statements to the public, Parliament and the media.

In the IT sphere, early problems with the Universal Credit IT programme were kept secret and misleadingly positive statements issued. The National Audit Office later criticised a “good news” culture on the Universal Credit programme.

And still the DWP is fighting to block the disclosure of five project assessment reviews that were carried out on the Universal Credit IT programme between 2012 and 2015.

It could be argued that billions of pounds lost on the NPfIT – the National Programme for IT in the NHS – would have been avoided if the Department of Health had been open and candid at the start of the programme about the programme’s impractically ambitious aims, timescales and budgets.

The Department for Business, Energy and Industrial Strategy is currently keeping secret its progress reports on the £111bn smart meters rollout – which independent experts have said is a failing programme.  The department routinely issues positive statements to the media on the robust state of the programme.

The Public Authority Accountability Bill was drafted by lawyers who had been involved with representing bereaved Hillsborough families. It is aimed mainly at government inquiries, court proceedings and investigations into lapses of public services.

But it would also enshrine into law a duty on public authorities, public servants, officials and others to act within their powers with “transparency, candour and frankness”.

Lawyers who drafted the Bill refer on their website to “institutional defensiveness and a culture of denial” when things go wrong. They say,

“In 2017 we expect public authorities and individuals acting as public servants to be truthful and act with candour. Unfortunately, repeated examples have shown us that this is not generally the case.

“Instead of acting in the public interest by telling the truth, public authorities have tended to according to narrow organisational and individual motives by trying to cover up faults and deny responsibility …”

Backing for the Bill came yesterday from a 117-page report on the Hillsborough disaster by Bishop James Jones. The government commissioned him to produce a report on the experiences of the Hillsborough families so that their “perspective is not lost”.

Jones’ impressive report refers to institutions that “closed ranks, refused to disclose information, used public money to defend its interests and acted in a way that was both intimidating and oppressive”

His report refers to public bodies in general when it points to a “cultural condition” and “mindset” that features an “instinctive prioritisation of the reputation of an organisation over the citizen’s right to expect people to be held to account for their actions”. This, says the report, “represents a barrier to real accountability”.

It adds,

“As a cultural condition, this mindset is not automatically changed, still less dislodged, by changes in policies or processes. What is needed is a change in attitude, culture, heart and mind.”

The report urges leaders of “all public bodies” to make a commitment to cultural change by publicly signing a new charter.

The charter commits public bodies to:

  •  Place the public interest above its own reputation.
  • Approach forms of scrutiny with candour, in an open, honest and transparent way, making full disclosure of relevant documents, material and facts.
  • Learn from the findings of external scrutiny and from past mistakes.
  • Avoid seeking to defend the indefensible or to dismiss or disparage those who may have suffered where the organisation has fallen short.
  • When falling short, apologise straightforwardly and genuinely.
  • Not knowingly mislead the public or the media.

The report says that institutional defensiveness and a culture of denial are “endemic amongst public institutions as has been demonstrated not only by the Hillsborough cover up but countless other examples.”

Stuart Hamilton, son of Roy Hamilton who died at Hillsborough, is quoted in the report as saying,

“Police, officials and civil servants should have a duty of revealing the full facts and not merely selecting some truths to reveal but not others. Not lying or not misleading is simply not good enough. Without this, future disasters cannot be averted and appropriate policies and procedures cannot be developed to protect society.

“Such selective revealing of information also results in the delay of justice to the point where it cannot be served”.

He added,

“I believe that without a change not only in the law but also in the mindset of the public authorities (which a law can encourage) then very little exists to stop the post-event actions happening again.”

IT-enabled projects

Whitehall departments and the Infrastructure and Projects Authority publish their own narratives on the progress on major IT-enabled projects and programmes such as Universal Credit and smart meters.

But their source reports aren’t published.

Early disclosure of failings could have prevented hundreds of millions of pounds being lost on FireControl project, BBC’s Digital Media Initiative, the Home Office Raytheon e-borders and C-Nomis national offender management information projects and the Rural Payments Agency’s CAP delivery programme (which, alone, contributed to EU penalties of about £600m).

Comment:

Yesterday’s beautifully-crafted report into the Hillsborough disaster – entitled “The patronising disposition of unaccountable power” – is published on the Gov.uk website.

It has nothing to do with IT-enabled projects and programmes. But, in an unintentional way, it sums up a public sector culture that has afflicted nearly every Whitehall IT-based project failure in the last 25 years.

A culture of denial is not merely prevalent today; it is pervasive. All Whitehall departments keep quiet about reports on their failings. It is “normal” for departments to issue misleadingly positive statements to the media about progress on their programmes.

The statements are not lies. They deploy facts selectively, in a way that covers up failings. That’s the Whitehall culture. That’s what departments are expected to do.

According to Bishop Jones’ Hillsborough report, one senior policeman told bereaved families that he was not obliged to reveal the contents of his reports. He could bury them in his garden if he wished.

It’s the same with government departments. There is no legal duty to keep programme reports, still less any requirement to publish them.

If Bishop Jones’ charter is signed by leaders of public authorities including government departments, and Andy Burnham’s Bill becomes law,  the requirement for candour and transparency could mean that IT programme progress reports are made available routinely.

If this happened – a big if – senior public officials would have to think twice before risking billions of pounds on a scheme that held out the prospect of being fun to work on but which they knew had little chance of success within the proposed timescales, scope and budget.

It’s largely because of in-built secrecy that the impossibly impractical NPfIT was allowed to get underway. Billions of pounds was wasted.

Some may say that the last thing ministers and their permanent secretaries will want is the public, media and MPs being able to scrutinise what is really happening on, say, a new customs IT project to handle imports and exports after Brexit.

But the anger over the poor behaviour of public authorities after Hillsborough means that the Bill has an outside chance of eventually becoming law. Meanwhile public sector leaders could seriously consider signing Jones’ charter.

John Stuart Mill wrote in 1859 (On Liberty and The Subjection of Women) that the “only stimulus which can keep the ability of the [public] body itself up to a high standard is liability to the watchful criticism of equal ability outside the body”.

 

Whitehall renews facade of openness on major IT projects

By Tony Collins

Headlines yesterday on the state of major government IT projects were mixed.

Government Computing said,

“IPA: Whitehall major projects show ‘slow and steady’ delivery improvement”

Computer Weekly said,

“Government IT projects improving – but several still in doubt”

The Register said,

“One-quarter of UK.gov IT projects at high risk of failure – Digital borders, digital tax and raft of MoJ projects singled out”

The headlines were prompted by the Infrastructure and Projects Authority’s annual report which was published yesterday.

The report listed the RAG – red/amber/green – status of each of 143 major projects in the government’s  £455bn major projects portfolio. Thirty-nine of these are ICT projects, worth a total of £18.6bn.

Publication of the projects’ red/amber/green status – called the “Delivery Confidence Assessment” – seemed a sign that the government was being open over the state of its major IT and other projects.

A reversal of decades of secrecy over the progress or otherwise of major IT projects and programmes?

In a foreword to the Infrastructure and Project Authority’s report, two ministers referred twice to the government’s commitment to openness and accountability.

MP Caroline Nokes, Cabinet Office minister, and MP Andrew Jones, a Treasury minister, said in their joint foreword,

“The government is also committed to transparency, and to being responsive and accountable to the public we serve.

“Accordingly, we have collected and published this data consistently over the past five years, enabling us to track the progress of projects on the GMPP [Government Major Projects Portfolio] over time.

“We will continue to be responsive and accountable to the public.”

But the report says nothing about the current state of major IT projects. The delivery confidence assessments are dated September 2016. They are 10 months out of date.

This is because senior civil servants – some of whom may be the “dinosaurs” that former minister Francis Maude referred to last month – have refused to allow politicians to publish the red/amber/gtreen status of major projects (including the Universal Credit programme and the smart meters rollout) unless the information, when published, is at least six months old.

[Perhaps one reason is to give departmental and agency press officers an opportunity to respond to journalists’ questions by saying that the red, red/amber of amber status of a particular major project is out of date.]

Amber – but why?

An amber rating means that “successful delivery appears feasible but significant issues already exist” though any problems “appear resolvable”.

In September 2016 the Universal Credit programme was at amber but we don’t know why. Neither the IPA or the Department for Work and Pensions mention any of the “issues”.

The £11bn smart meters rollout is also at amber and again we don’t know why. Neither the IPA nor the Department for Business, Energy and Industrial Strategy mention any of the “issues”. Permanent secretaries are allowed to keep under wraps the IPA’s reasons for the red/amber/green assessments.

Even FOI requests for basic project information have been refused.  Computer Weekly said,

“Costs for the Verify programme were also withheld from the IPA report, again citing exemptions under FOI.”

Comment

The senior civil servants who, in practice, set the rules for what the Infrastructure and Projects Authority can and cannot publish on major government projects and programmes are likely to be the “dinosaurs” that former Cabinet Office minister Francis Maude referred to last month.

Maude said that Whtehall reforms require that new ministers “face down the obstruction and prevarication from the self-interested dinosaur tendency in the mandarinate.”

Clearly that hasn’t happened yet.

The real information about Universal Credit’s progress and problems will come not from the Infrastructure and Projects Authority – or the Department for Work and Pensions – but from local authoritities, housing associations, landlord organistions, charities and consumer groups such the Citizen’s Advice Bureau (which has called for Universal Credit to be halted), the local press, the National Audit Office and Parliamentary committees such as the Public Accounts Committee and Work and Pensions Committee.

On the smart meter rollout, the real information will come not from the Infrastructure and Projects Authority – or the Department for Business, Energy and Industrial Strategy – but from business journalist Paul Lewis, consumer advocate Martin Lewis, business organistions such as the Institute of Directors,  experts such as Nick Hunn, the Energy and Climate Change Committee and even energy companies such as EDF.

Much of this “real” information will almost certainly be denied by Whitehall press officers. They’ll be briefed by senior officials to give business journalists only selected “good news” facts on a project’s progress and costs.

All of this means that the Infrastructure and Projects Authority may have good advice for departments and agencies on how to avoid project failures – and its tact and deference will be welcomed by permanent secretaries – but it’s likely the IPA will be all but useless in providing early warnings to Parliament and the public of incipient project disasters.

Ministers and some senior civil servants talk regularly about the government’s commitment to openness and accountability. When it will start applying to major government IT projects?

 

UK.gov watchdog didn’t red flag any IT projects. And that alone should be a red flag to everyone

 

 

 

 

MPs suggest Cabinet Office is losing its grip on departments – but does it care?

By Tony Collins

The Register has an excellent piece by Kat Hall on how the Cabinet Office is losing its grip on Government departments.

Citing the annual report of the all-party Public Accounts Committee, Hall says there are issues where “departments repeatedly don’t do what they have been told or asked to do by the centre”.

An analysis by The Register found that

“government departments are winning significantly more exemptions to splash the cash on expensive IT projects since the departure of former Cabinet Office minister Francis “Mad Frankie” Maude last year”.

Chair of the Public Accounts Committee Meg Hillier said: “After my second year as Chair I am increasingly concerned about the long-term accountability of senior civil servants.

“The game of musical chairs starts as one Permanent Secretary moves on and they all change jobs in the system. And few are in post long enough to have a vested interest in the long-term aims of their department or a project.

“And there is the age-old tension between a department and central Whitehall through the Cabinet Office.”

Universal Credit and HMRC’s plans to overhaul its Aspire IT contract – the biggest in Europe – were outlined as being two areas of concern. As was the Home Office’s Emergency Services Network.

“The Home Office seemed to downplay the risks to the contract and its being caught unawares by the contractor does not reassure us that the Department is on top of the contract or this project. This could cost the taxpayer dear,” it said.

Comment:

It’s hard to argue with a comment on Hall’s piece by @JagPatel3 who suggests that some in Whitehall are as preoccupied with spin as with the efficient delivery of public services.

“… Government is preoccupied with presentation, manipulation of words and the dark art of spinning – instead of working on its programme of reform to deliver public services efficiently, to satisfy the wants, needs and expectations of the electorate.

“The political imperative of needing to put a positive slant on everything the Government does or will do, irrespective of whether it is true or not, is the reason why spin has become the centrepiece of this Government’s communications strategy.

“And because Government has got a monopoly on inside information (enabling it to maintain extremely tight control), it uses spin to divert attention away from the key issues that really matter to citizens …

“the eagerness with which senior Civil Servants have complied with their political masters’ desire to see policy announcements framed around presentation and spin, at the expense of substance, would explain why their skills set has been narrowed down to this single, dark art.”

The commentator also says that the “intense focus of attention on presentation alone has resulted in a massive gap opening up between the leadership and lower ranks of the Civil Service, who have to deal with the reality of delivering public services on the ground, on a day-to-day basis, which has in itself, led to alienation and disaffection”.

A good summary. Many ordinary civil servants are doing the hard work of delivering public services while a few of their masters are preoccupied with keeping what they do secret and justifying or defending all else that is published in National Audit Office reports, other third-party reports or leaked emails.

It’s hardly surprising the Cabinet Office is losing control of departments. Since Maude’s departure it doesn’t want control. It has become clear that it wants, in a hassle-free way,  to continue with Sir Humphrey’s non-integrated approach to government.

The Cabinet Office is just another Whitehall department. Why would it want to be an “enforcer?”

Some officials “smuggle their often half-baked proposals past ministers” says Cabinet Office adviser who quits

By Tony Collins

Jerry Fishenden has resigned from the Cabinet Office‘s Privacy and Consumer Advisory Group after nearly six years. First he was its chairman and more recently co-chairman.

The Privacy and Consumer Advisory Group comprises privacy and security experts who give the government independent analysis and guidance on personal data and privacy initiatives by departments, agencies and other public sector bodies. This includes GOV.UK Verify.

The group’s advice has had the citizens’ interests in mind. But the group might have been seen by some Whitehall officials as having an open and frank “outsiders” culture.

Francis Maude, then Cabinet Office minister, helped to set up the group but he left in 2015 and none of his replacements has had a comparable willingness to challenge the civil service culture.

Maude welcomed the help of outsiders in trying to change the civil service.  He tried to bring down the costs of Government IT and sought to stop unnecessary or failing projects and programmes. He also wanted to end the “oligopoly” of a handful of large IT suppliers. But Maude’s initiatives have had little continuing support among some Whitehall officials.

Fishenden said in a blog post this week that Maude had wanted the Privacy and Consumer Advisory Group to be a “critical friend” – a canary that could detect and help fix policy and technology issues before they were too far down the policy / Bill process.

“The idea was to try to avoid a repeat of previous fiascos, such as the Identity Card Act, where Whitehall generalists found themselves notably out of their depth on complex technical issues and left Ministers to pick up the pieces.”

He added that “since Francis Maude’s departure, there has been only one meeting” with subsequent Cabinet Office ministers.

“Without such backing, those officials who find the group’s expert reviews and analyses “challenging” have found it easier to ignore, attempting instead to smuggle their often half-baked proposals past Ministers without the benefit of the group’s independent assistance…

“Let’s just hope that after the election the value of the group will be rediscovered and government will breathe life back into the canary. Doing so would help realise Francis Maude’s original purpose – and bring significant benefits to us all, whether inside or outside of government.”

Comment

One of the Privacy and Consumer Group’s strengths has been its independent view of Government IT-related initiatives  – which is probably the main reason it has been marginalised.

Fishenden’s departure is further confirmation that since Maude’s departure, the Cabinet Office – apart from the Government Digital Service – has settled back into the decades-old Whitehall culture of tinkering with the system while opposing radical change.

While Whitehall’s culture remains unreformable, central government will continue to lose the best IT people from the private sector. Some of these include the former Government Digital Service executive director Mike Bracken, Stephen Foreshew-Cain, who took over from Bracken, Janet Hughes, programme director of Verify,  Andy Beale, GDS’s chief technology officer, Paul Maltby, GDS’s director of data and former Whitehall chief information officers Joe Harley, Steve Lamey, Andy Nelson and Mark Dearnley.

The unfortunate thing is that a few powerful career civil servants, including some permanent secretaries, will be delighted to lose such outsiders.

Jerry Fishenden is simply the latest casualty of a civil service tradition that puts the needs of the department before those of the citizen.

It’s a culture that hasn’t changed for decades.

The canary that ceased to be – Jerry Fishenden’s blog on his departure

Privacy and Consumer Advisory Group

Does Universal Credit make a mockery of Whitehall business cases?

By Tony Collins

Does Universal Credit make a mockery of this Treasury guidance on business cases?

It’s supposed to be mandatory for Whitehall departments to produce business cases. They show that big projects are “unequivocally” affordable and will work as planned.

But Computer Weekly said yesterday that the Department for Work and Pensions has not yet submitted a full business case for Universal Credit although the programme has been running for six years.

The result is that the Universal Credit IT programme may be the first big government computer project to have reached the original completion date before a full business case has been finalised.

Its absence suggests that the Department for Work and Pensions has not yet been able to produce a convincing case to the Treasury that the IT programme will either work or be affordable when it is due to roll out to millions of claimants.

The absence also raises a question of why the Department for Work and Pensions was able to award contracts and proceed with implementation without having to be accountable to Parliament for milestones, objectives, projected costs and benefits – all things that would have been recorded in the full business case.

If the DWP can proceed for years with project implementation without a full business case, does this mean that other Whitehall department need have no final structured plan to justify spending of billions on projects?

Will Universal Credit work?

By early March 2017, fewer than 500,000 people were on Universal Credit. On completion, the system will be expected to cope with seven million claimants.

Although the rollout of the so-called “digital” system – which can handle all types of claim online – is going well (subject to long delays in payments in some areas and extreme hardship for some), there are uncertainties about whether it will cope with millions of claimants.

Universal Credit campaigner John Slater has been unable to obtain any confirmation from the DWP on whether it is planning to complete the rollout by 2022 – five years later than originally scheduled.

Business cases present arguments that justify the spending of public money. They also provide a “clear audit trail for purposes of public accountability,” says Cabinet Office guidance on business cases.

But hundreds of millions has already been spent on Universal Credit IT, according to the National Audit Office.

Business cases are mandatory … sort of

The Treasury says that production of business cases is a

“mandatory part of planning a public sector spending proposal …”

Yesterday, however, Computer Weekly reported that,

“Amazingly, given the programme has been going since 2011, the full business case for Universal Credit has still not been submitted or signed off by the Treasury – that’s due to take place in September this year.”

The Treasury says that preparation of the Full Business Case is “completed following procurement of the scheme – but prior to contract signature – in most public sector organisations.”

But by March 2013, the Department for Work and Pensions had already spent about £303m on Universal Credit IT, mostly with Accenture (£125m), IBM (£75m), HP (49m) and BT (£16m), according to the National Audit Office.

Why a business case is important

The Treasury sums up the importance of business cases in its guidance to departments,

“… it is vital that capital spending decisions are taken on the basis of highly competent professionally developed spending proposals.

The business case provides a

“structured process for appraising, developing and planning to deliver best public value.”

The full business case, in particular, sets out the

  • contractual arrangements
  • funding and affordability
  • detailed management arrangements
  • plans for successful delivery and post evaluation.

In the absence of a full business case the DWP was able to start the Universal Credit IT programme with little structured control on costs. The National Audit Office found in 2013 that there was

  • Poorly managed and documented financial governance
  • Limited evidence that supplier invoices were properly checked before payments were made.
  • Inadequate challenge of purchase decisions
  • Insufficient information on value for money of contracts before ministers approved them
  • Insufficient challenge of suppliers’ cost changes
  • Over-reliance on performance information from suppliers that the Department for Work and Pensions didn’t validate.
  • No enforcement by the DWP of key parts of the supplier contracts

Comment

Officials at the Department for Work and Pensions have gone to the bank for money for a new business venture – the building of Universal Credit IT – and said in effect,

“We’ll let you have an outline business case that may change a few times and in a few years, perhaps on completion of the programme or thereabouts, we’ll provide a full business case. But we’d like the money now please.”

In response the bank – HM Treasury – has replied in effect,

“You’re supposed to supply a full business plan before we decide on whether to give you the money but we know how important Universal Credit is.

“We’ll tell you what: we’ll let you have a few tens of millions here and there and see how you get on.

“For the time being, without a full business case, you’re restricted to an IT spend of around £300m.

“In terms of the eligibility criteria for the money, you can let us know what this should be when you’re a few years down the road.

“We accept that you’ll be in a much better position to know why you should be given the money once you’ve spent it.”

Does “mandatory” mean anything when there is no sanction against non-compliance?

And when the DWP is able to embark on a multi-billion pound programme without submitting a full business case until after the original completion date (2017), what’s the point of a business case?

The fact that the DWP is six years into implementation of Universal Credit without a full business case suggests that departments make up the rules as they go along.

What if the Treasury rejects the Universal Credit business case when it’s eventually submitted?

Will the DWP wait another few years to submit a case, when an entirely new set of officials will be in place? By then, perhaps, the Universal Credit rollout will have finished (or been aborted) and nobody at that stage could be effectively held to account if the scheme didn’t work or money had been wasted.

If Whitehall routinely waits until an IT-based programme is finished before presenting a full business case for Treasury approval, there’s nothing the Treasury can do if it wants and needs the programme.

Sir Humphrey is all-powerful.  Why should officials worry about presenting full business cases on programmes they know there’s a political imperative to deliver?

Can DWP meet its revised 2022 target for completion of Universal Credit? – Computer Weekly

Treasury guidance on business cases

 

 

Large suppliers still dominate government IT

By Tony Collins

In 2012, the then Cabinet Office minister Francis Maude, lamented the high costs of government IT and spoke of an “oligopoly” of large suppliers. He suggested things would change.

“… contracts were consistently awarded to a limited number of very large suppliers on long-term exclusive contracts.

“As a result there was inadequate competition and an abdication of control. The concept of having one supplier, aggregated supply, increased project risk and removed competitive tension.

“The Government repeatedly found itself paying large amounts for systems that were delivered late, over budget and which often did not fully meet the original policy requirement.  If indeed, they were delivered at all. There are plenty of well-documented disasters – such as DH’s now terminated National programme for IT.

“Ultimately, the last Government lost control of IT – it outsourced not only delivery, but its entire strategy and ability to shape the future of our public services.

“At the same time smaller, more innovative and efficient suppliers were finding themselves locked out of the supply of services to Government because of what was described by Parliament as a powerful “oligopoly” of large suppliers.

“Procurements took so long only the big companies could absorb the cost – which they naturally passed on to us.

“All in all, we had an approach that was bad for users, bad for the taxpayer and bad for growth.”

Public sector IT spending was up to £20bn a year, he said, adding that “public sector productivity was actually declining”.  He outlined how things were changing.

What has happened since?

A report published today by the National Audit “Digital Transformation in Government” raises a question of how much has changed.

Efforts to boost the SME share of government IT business “have had some impact”, says the National Audit Office, but it adds that “most government procurement with digital and technology suppliers continues to be with large organisations”.

“In 2015-16, 94% of such spending was with large enterprises, a fall of less than one percentage point since 2012-13.”

Today’s NAO report is mainly about the Cabinet Office’s Government Digital Service – GDS. It points out GDS’s strengths and weaknesses but in general does not give any advice on the sensitive point of whether it should have more or less influence on government IT.

On digital transformation, it says that the work of the NAO shows that attempts to transform government have had mixed success.

“Many public services appear increasingly unsustainable. Those responsible for major programmes have continued to exhibit over-optimism and make slow progress towards their objectives.”

It adds,

“Digital transformation has a mixed track record across government. It has not yet provided a level of change that will allow government to further reduce costs while still meeting people’s needs.

“GDS has also struggled to demonstrate the value of its own flagship initiatives such as Verify, or to set out clear priorities between departmental and cross-government objectives.

“GDS’s renewed approach aims to address many of these concerns as it expands and develops into a more established part of government. But there continues to be a risk that GDS is trying to cover too broad a remit with unclear accountabilities.

“To achieve value for money and support transformation across government, GDS needs to be clear about its role and strike a balance between robust assurance and a more consultative approach.”

Comment

The National Audit Office report is strong on facts and quality of research but avoids the big question of how GDS can bring about change when the top brass in departments prefer autonomy to what they see as GDS’s interference.

GDS’s existence goes to the heart of how the civil service runs. It is one part of the civil service trying to bring about change in other parts of the civil service.

And the evidence so far is that the civil service doesn’t like change.

The NAO report disappoints because it doesn’t address how government IT is to change if departments are to continue to run empires unchallenged by GDS or the heads of the civil service. Sir Humphrey is still king.

GDS scrutinises departmental IT spending – spending applications are reviewed by a team of eight people within GDS’s Standards Assurance team – but, much to Sir Humphrey’s delight, GDS’s influence seems to be waning.

When Jack Straw was Justice secretary, he told MPs in 2007 that when he abandoned projects there was a fuss at first and soon nobody noticed the project did not exist.

“There is always the option to abandon things. I did that in the Foreign Office with much complaint that the world might end.

“What happened was that we saved a lot of money and no one ever noticed the fact that that scheme did not exist…it is very frustrating that so many people, including the private sector, are taken in by snake oil salesmen from IT contractor who are not necessarily very competent and make a lot of money out of these things. I am pretty intolerant of this.”

How much has changed? Outsiders including Jack Straw and Francis Maude, together with insiders such as Chris Chant have pointed to the need for major changes in the way departments manage huge IT budgets and there have been some improvements: HMRC’s is breaking up its monolithic “Aspire” contract, citizens may notice that it is possible now to renew passports and driving licences online and GDS has had an impact in making departments think hard about whether they really need to spend the amounts they do on major IT contracts.

But major change in the costs of government IT seems not just a long way off but unattainable while the dominance of Sir Humphrey remains unchallenged.

Digital Transformation in Government – NAO report