Today’s National Audit Office report Universal Credit: early progress is one of most excoriating the NAO has published on a government IT-enabled project or programme.

Iain Duncan Smith, secretary of state for work and pensions, has already responded to the NAO report by implying it is out of date and that the problems are in the past. This is a standard government response to well researched and highly critical NAO reports.

But the authors of the NAO report have pointed to some UC problems that are so fundamental that it may be difficult for any independent observer to credibly regard the project’s problems as historic. Says the NAO:

“The Department [DWP] is unable to continue with its ambitious plans for national roll-out until it has agreed the future service design and IT architecture for Universal Credit.”

So can the UC project ever be a success if, years after its start, there is no agreed design or IT architecture? Says the NAO

“The Department may also decide to scale back the complexity and ambition of its plans.”

Although the DWP has spent more than £300m on UC IT, mostly with the usual large IT suppliers, complex claims cannot yet be handled without manual work and calculations.

In February 2013, the Cabinet Office’s Major Projects Authority reviewed Universal Credit and raised “serious concerns about the programme’s progress”, says the NAO report. “The review team was concerned that the pathfinder [pilot project] could not handle changes in circumstances and complex cases which had to be dealt with manually, and that this meant the pathfinder could not be rolled out to large volumes.”

The Independent says the DWP gave false assurances on the project’s progress. The Daily Mail says the scheme has got off to a “disastrous start”.

The NAO’s main findings:

 Is £303m spent on IT value for money?

 “At this early stage of the Universal Credit programme the Department has not achieved value for money. The Department has delayed rolling out Universal Credit to claimants, has had weak control of the programme, and has been unable to assess the value of the systems it spent over £300m to develop [up to the end of March 2013].

“These problems represent a significant setback to Universal Credit and raise wider concerns about the Department’s ability to deal with weak programme management, over-optimistic timescales, and a lack of openness about progress.”

A projected IT overspend of £233m?

The NAO puts the expected cost of implementing Universal Credit to 2023 at £2.4bn. The spend to April 2013 is £425m, including £303m on the IT. The planned IT investment in the current spending review period from the May 2011 business case was £396m, but the December 2012 business case puts the planned IT investment in the current review period at £637m – and increase of £233m, or 60%. The DWP wants to make changes elsewhere in its budgets to accommodate the extra IT spend.

Ministers and DWP spokespeople have said repeatedly that the project is within budget.

Some of the IT spend breakdown

– Core software applications including a payment management component  – £188m

– Interface with HMRC real time information – £10m

– Case management module – £6m

– Licences – £31m

– Supplier support – £26m

– Hardware, telephony and changes to old systems – £50m

– Departmental staff costs on the Business and IT Solution team – £29m.

– Staff contractors provided by suppliers to support departmental staff  – £26m.

Main IT suppliers – spend to end of 2012/13

– Accenture. Software design, development and testing including: interview system; evidence capture, assessment and verification; and staff contractors – £125m

– IBM. Software design, development and testing including: real time earnings; process orchestration and payment management; and staff contractors – £75m

– HP. Hardware and legacy system software, and staff contractors – £49m

– BT. Telephony. It also supplied specialist advice on agile development methods – £16m

A further £9m was spent on live system support costs provided by HP; bringing total spending with suppliers to £312m, says the NAO.

 Is the IT high quality or not?

The NAO report suggests there may be conflicting views between those in DWP who believe the IT is high quality and others who are not so sure.

“The Department believes that the majority of the built IT is high quality, but has not been fully developed and cannot support scaling up the programme as it stands. Some assessments have commented that systems are inflexible or over-elaborate.”

Will the IT support a national roll-out?

The NAO says it’s uncertain that the IT can support full national roll-out of Universal Credit without further work and investment.

“The Department does not yet know to what extent its new IT systems will support national roll-out. Universal Credit pathfinder systems have limited function and do not allow claimants to change details of their circumstances online as originally intended. The Department does not yet have an agreed plan for national roll-out and has been unclear about how far it will build on pathfinder systems or replace them.”

Will timetable and scope have to change further?

“The Department will have to scale back its original delivery ambition and is re-assessing what it must do to roll-out Universal Credit to claimants. The current programme team is developing new plans for Universal Credit. Our experience of major programmes supported by IT suggests that the Department will need to revise the programme’s timing and scope, particularly around online transactions and automation.”

Over-optimism?

“It is unlikely that Universal Credit will be as simple or cheap to administer as originally intended. Delays to roll-out will reduce the expected benefits of reform…”

Rushed?

“ The ambitious timetable created pressure on the Department to act quickly…”

Open to fraud?

“The Department’s current IT system lacks the ability to identify potentially fraudulent claims. Within the controlled pathfinder environment, the Department relies on multiple manual checks on claims and payments. Such checks will not be feasible or adequate once the system is running nationally.

“Without a system in place, the Department will be unable to make the savings it had planned, by reducing overpayments from fraud and error. In December 2012, it estimated these savings to be worth £1.2 billion per year in steady state.”

Separately the NAO states that there have been “unanticipated security problems from putting transactions online”. The DWP may now scale back all that was planned to be online.

In January 2013 the technical director of CESG and other reviewers said that the UC security solution was “over-complex” and could have conflicted with DWP plans to encourage people to claim online.

Delay in national roll-out

“The Department has delayed rolling out Universal Credit nationally. The Department will not introduce Universal Credit for all new out-of-work claims nationally from October 2013 as planned. Instead it will add a further six pathfinder sites from October 2013

 “Pause UC immediately”

In early 2013 the Cabinet Office’s Major Projects Review Group noted that the Department had not addressed issues with governance, management and programme design despite their having been raised in previous reports. The Authority “recommended that the Universal Credit programme be paused immediately”.

All  post-2015 plans under review

The original plans were for UC roll-out to finish by late 2017. All statements by officials and Iain Duncan Smith have confirmed this 2017 deadline. In fact, says the NAO, all milestones beyond the start of 2015 are “currently under review” including:

• National roll-out of all new claims

• Closedown of tax credits new claims

• Roll-out of Pension Credit Plus on Universal Credit platform

• Completion of claimant migration

The NAO says the DWP has considered completing the roll-out beyond 2017.

Complete rethink needed

 The Cabinet Office’s Major Projects Authority reviewed and reported on Universal Credit in February 2013. The Authority’s found that:

“Universal Credit Programme needs a complete rethink of the delivery approach together with streamlining potentially over-elaborate solutions.”

A separate review of the project by Capgemini in January 2013 and a “Reset IT stocktake” in April 2013 concluded that the UC “architecture is of limited extensibility”.

Pathfinders of limited value

“The pathfinder lacks a complete security solution. Claimants cannot make changes in circumstances online. This increases the need for manual work as changes must be made by telephone. The pathfinders also require more staff intervention than planned, because of reduced automation and links between systems.”

100 day planning period

 “In May 2013, the Department appointed the current senior responsible owner [Howard Shiplee] to lead the Universal Credit programme. The team is now conducting a ‘100-day planning period’, which will end at the end of September 2013. The Department will then submit a new business case to HM Treasury, and ask for ministerial sign-off for delivery plans in late 2013.”

Secrecy – even internally?

“The reset took place between February and May 2013. The reset team included departmental, Cabinet Office and Government Digital Services staff. The reset team developed an extensive set of materials as part of a ‘blueprint’ covering design and implementation, and 99 detailed recommendations. The reset team shared the blueprint with the Department’s Executive Team who approved it at each stage of its development. The Department shared the blueprint with a small number of people but did not initially share it widely.”

A £34m write-off – so far

“The Department has acknowledged that it needs to write off some of the value of its Universal Credit IT assets. By the end of 2012-13, the Department had spent £303m on its IT systems and created assets which it valued at £196m – a difference of £107m. But the DWP has decided to write-off £34m – 17% – though it may increase the size of the write-off later.

“The Department is conducting further impairment reviews of the value of its Universal Credit IT assets before finalising its 2012-13 accounts.” The £34m write-off was based on a “self-assessment which it asked its suppliers to conduct”.

Number of claimants well below planned level

“In its October 2011 business case, the Department expected the Universal Credit caseload to reach 1.1 million by April 2014, but reduced this to 184,000 in the December 2012 business case.”

Planned savings down by nearly £500m

“The cost to government of implementing Universal Credit will be partly offset by administrative savings. In December 2012, the Department estimated that a three-month delay in transferring cases from existing benefits to Universal Credit would reduce savings by £240m in the current spending review period and by £247m after April 2015.”

 Anyone know who decided on October 2013 for planned UC roll-out?

 “The Department was unable to explain to us why it originally decided to aim for national roll-out from October 2013. It is not clear whether the Department gave decision-makers an evaluation of the relative feasibility, risks and costs of this target date.”

 Agile … with a 1,000-strong team?

“In 2010, the Department was unfamiliar with the agile methodology and no government programme of this size had used it. The Department recognised that the agile approach would raise risks for an organisation that was unfamiliar with this approach. In particular, the Department

• was managing a programme which grew to over 1,000 people using an approach that is often used in small collaborative teams;

• had not defined how it would monitor progress or document decisions;

• needed to integrate Universal Credit with existing systems, which use a waterfall approach to managing changes; and

• was working within existing contract, governance and approval structures.

“To tackle concerns about programme management, the Department has repeatedly redefined its approach. The Department changed its approach to ‘Agile 2.0’ in January 2012. Agile 2.0 was an evolution of the former agile approach, designed to try to work better with existing waterfall approaches that the Department uses to make changes to old systems.

“After a review by suppliers raised concerns about the achievability of the October 2013 roll-out the Department then adopted a ‘phased approach’ and created separate lead director roles for the pathfinder (phase 1), October roll-out (phase 2) and subsequent migration (phase 3).

“The Cabinet Office does not consider that the Department has at any point prior to the reset appropriately adopted an agile approach to managing the Universal Credit programme.”

Anyone know how UC is meant to work?

The source of many problems has been the absence of a detailed view of how Universal Credit is meant to work. The Department has struggled to set out how the detailed design of systems and processes fit together and relate to the objectives of Universal Credit.

“This is despite this issue having been raised repeatedly in 2012 by internal audit, the Major Projects Authority and a supplier-led review. This lack of clarity creates problems tracking progress, and increases the risk that systems will not be fit for purpose or that proposed solutions are more elaborate or expensive than they need to be…

“The Department was warned repeatedly about the lack of a detailed ‘blueprint’, ‘architecture’ or ‘target operating model’ for Universal Credit. Over the course of 2011 and the first half of 2012, the Department made some progress but did not address these concerns as expected.

“By mid-2012, this meant that the Department could not agree what security it needed to protect claimant transactions and was unclear about how Universal Credit would integrate with other programmes. These concerns culminated, in October 2012, in the Cabinet Office rejecting the Department’s proposed IT hardware and networks.

“ Given the tight timetable, unfamiliar programme management approach and lack of a detailed operating model, it was critical that the Department should have good progress information and effective controls. In practice the Department did not have any adequate measures of progress.”

High turnover among IT leaders?

“Including the reset and the current director general for Universal Credit, the programme has had five different senior responsible owners since mid-2012.

“The Department has also had high turnover in important roles other than the senior responsible owner. The Department has had five Universal Credit programme directors since 2010.”

The NAO said that the director of Universal Credit IT was “removed from the programme in late 2012 and the Department has replaced the role with several roles with IT responsibilities”. During and since the ‘reset’ the Government Digital Service has helped to redesign the systems and processes supporting transformation.

Good news culture and a fortress mentality

“The culture within the programme has also been a problem…Both the Major Projects Authority and a supplier-led review in mid-2012 identified problems with staff culture; including a ‘fortress mentality’ within the programme. The latter also reported there was a culture of ‘good news’ reporting that limited open discussion of risks and stifled challenge.”

“Inadequate control of suppliers”

The Department had to manage multiple suppliers. Three main suppliers – Accenture, IBM and HP – developed components for Universal Credit. The Department commissioned IBM to act as an Applications Development Integrator from January 2012, providing some oversight and overall management of IT development, but creating risks of supplier self-management.

The NAO found that there were inappropriate contractual mechanisms; charges were on the basis of time and materials, leaving the majority of risks with the Department. The NAO said there were “inadequate controls over what would be supplied, when and at what cost because deliverables were not always defined before contracts were signed.”

There was “over-reliance on performance information that was provided by suppliers without Department validation”. And weak contractual relationships with suppliers meant that the DWP “did not enforce all the key terms and conditions of its standard contract management framework, inhibiting its ability to hold suppliers to account”

Said the NAO:

“Various reviews have criticised how the Department has managed suppliers. In June 2012, CESG reported the lack of an agreed, clearly defined and documented scope with each supplier setting out what they should provide. This hampered the Department’s ability to hold suppliers to account and caused confusion about the interactions between systems developed by different ones. In February 2013, the Major Projects Authority reported there was no evidence of the Department actively managing its supplier contracts and recommended that the Department needed to urgently get a grip of its supplier management.”

Suppliers paid without proper checks

“The Department has exercised poor financial control over the Universal Credit programme. The Department commissioned an external review in early 2013 of financial management in Universal Credit. The review found several weaknesses including poor information about the basis for supplier invoices, payments being made without adequate checks and inadequate governance and oversight over who approved spending. The review team checked a sample of invoices against the timesheets of suppliers and found no evidence of inappropriate charging, although timesheet information is not complete and cannot be linked to specific activity…”

The NAO went on to emphasise that there was “insufficient review of contractor performance before making payments. “On average six project leads were given three days to check 1,500 individual timesheets, with payments only stopped if a challenge was raised.”

The NAO added that inadequate internal challenge of purchase decisions meant that ministers had “insufficient information to assess the value for money of contracts before approving them”.

50 people on the UC programme board

“The programme board acts as the programme’s main oversight and decision-making body… The programme board has been too large and inconsistent to act as an effective, accountable group. Over the course of 2012, the programme board had 50 different people attending as core members…

“The board did not have adequate performance information to challenge the programme’s progress. In particular, while the board had access to activity measures for IT system development, it could not track the actual value of this activity against spending.

“In the absence of such measures of progress, the board relied on external reviews to assess progress. Such external reviews were not sufficiently frequent for the board to use them as a substitute for timely, adequate management information.”

Programme board disbanded

 “… during the reset [Feb-May 2013], [the DWP] suspended the programme board entirely.

Failure to act on recommendations

“From mid-2012, it became increasingly clear that the Department was failing to address recommendations from assurance reviews… the key areas of concern raised by the Major Projects Authority in February 2013 had appeared in previous reports.

“From mid-2012, the underlying concerns about how Universal Credit would work meant that the Department could not address recommendations from assurance reviews; it failed to fully implement two-thirds of the recommendations made by internal audit and the Major Projects Authority in 2012. Without adequate, timely management information, the Department relied on periodic external assurance reports to assess progress.”

Ceasing work for national roll-out

“By late 2012, the Department had largely stopped developing systems for national roll-out and concentrated its efforts on preparing short-term solutions for the pathfinder…”

Slippery Parliamentary answers

The NAO lists almost imperceptible changes in the language of Parliamentary answers on Universal Credit.

In 2011 the DWP said in a Parliamentary answer that “all new applications” for out-of-work financial help would be treated as a UC claim; and in November 2012 the DWP said in a Parliamentary reply that in October 2013 it would start to migrate claimants from the old system to the new. But by June 2013 the DWP’s line had changed. By then it was saying in a Parliamentary reply that Universal Credit will “progressively roll-out” from October 2013 with all those who are entitled to UC claiming the new benefit by 2017. In fact all new applications for out-of-work help are not being treated as a UC claim. The NAO says that new claimants in the pathfinder must be “single, without children, newly claiming a benefit, fit for work, not claiming disability benefits, not have caring responsibilities, not be homeless or in temporary accommodation, and have a valid bank account and National Insurance number”.

Will UC ever work?

“ …it is still entirely feasible that it [UC] goes on to achieve considerable benefits for society. But to do so the Department will need to learn from its early mistakes.

“As it revises its plans the Department must show it can: exercise effective control of the programme; develop sufficient in-house capability to commission and manage IT development; set clear and realistic expectations about the timescale and scope of Universal Credit; and, address wider issues about how it manages risks in major programmes.”

**

Margaret Hodge MP, Chair of the Public Accounts Committee, says of the NAO report:

“The Department for Work and Pensions has made such a mess of setting up Universal Credit that the Major Projects Authority had to step in to rescue the programme.

“DWP seems to have embarked on this crucial project, expected to cost the taxpayer some £2.4bn, with little idea as to how it was actually going to work.

“Confusion and poor management at the highest levels have already resulted in delays and at least £34m wasted on developing IT. If the Department doesn’t get its act together, we could be on course for yet another catastrophic government IT failure.

“This damning indictment from the NAO gives me no confidence that we will see the £38 billion of predicted benefits between 2010-11 and 2022-23. Vulnerable benefit claimants need a secure system they can rely on.”

NAO report – Universal Credit: early progress

Has 2 decades of outsourcing cut costs at HMRC?

By Tony Collins

If HMRC’s experience is anything to go by, outsourcing can, in the long-term, at least triple an organisation’s IT costs.

When Inland Revenue contracted out its 2,000-strong IT department to EDS, now HP, in 1994 it was the first major outsourcing deal in central government.

Costing a projected £1.03bn over 10 years the outsourcing was a success, according to the National Audit Office in a report in March 2000. The deal  enabled Inland Revenue to bring about changes in tax policy to a tight timetable, said the NAO’s Inland Revenue/EDS Strategic Partnership – Award of New Work.

But costs soared for vague reasons. Something called “post-contract verification” added £203m to the £1.03bn projected cost over 10 years. A further increase of £533m was because of “workload increases including new work”. Another increase of £248m was put down to inflation.

By now the deal with HP had risen from £1.03bn to about £2bn.

When the contract expired in 2004, HM Revenue and Customs and HP successfully transferred the IT staff to Capgemini. The new 10-year contract from 2004 to 2014 (which was later extended 2017) had a winning bid price of £2.83bn over 10 years.

So by 2004 the costs of outsourcing had risen from £1.03bn to £2.83bn.

The new contract in 2004 was called ASPIRE – Acquiring Strategic Partners for Inland Revenue. HMRC then added £900m to the ASPIRE contract for Fujitsu’s running of Customs & Excise systems. By now there were about 3,800 staff working on the contract.

The NAO said in its report in July 2006  – ASPIRE, the re-competition of outsourced IT services – that Gateway reviews had identified the need for a range of improvements in the management of the contract and projects.

Now costing £7.7bn over 10 years

The latest outsourcing costs have been obtained by Computing. It found that annual fees paid to Capgemini under ASPIRE were:

  • 2008/09:  £777.1m
  • 2009/10:  £728.9m
  • 2010/11:  £757.8m
  • 2011/12:  £735.5m
  • 2012/13:  £773.5m

So IT outsourcing costs have soared again. The original 10-year costs of outsourcing in 1994 were put at £1.03bn. Then the figure became about £2bn, then £2.83bn, then £3.7bn when Fujitsu’s contract was added to ASPIRE. Now annual IT outsourcing costs are running at about £770m a year – £7.7bn over 10 years.

So the original IT running costs of Inland Revenue and Customs & Excise have, under outsourcing contracts, more than tripled in about two decades.

Comment:

What happened to the prevailing notion that IT costs fall over the long-term, and that outsourcing brings down costs even further?

Shouldn’t HMRC’s IT costs be falling anyway because of reduced reliance on costly Fujitsu VME mainframes, reductions in data centres, modernisation of PAYE, and the clearance of time-consuming unreconciled items on more than 10 million tax files?

HMRC knows how much profit Capgemini makes under “open book” accounting. It’s a margin of about 10-15% says the NAO. Lower margins are for value-added service lines and higher margins for riskier projects. If the overall target profit margin of 12.3% is exceeded, HMRC can obtain an equal share of the extra profits.

There were 10 failures costing £3.25m in the first 15 months. Capgemini refunded £2.67m in service credits in the first year of the contract.

It’s also worth mentioning that Capgemini doesn’t get all the ASPIRE fees. It is the lead supplier in which there are around 300 subcontractors – including Fujitsu and BT.  Capgemini pays 65% of its fees to its subcontractors.

The outsourcing has helped to enable HMRC to bring in self-assessment online and other changes in tax policy. But HMRC’s quality of service generally (and not exclusively IT) is mixed, to put it politely.

The adjudicator for HMRC who intervenes in particularly difficult complaints identifies as particular problems the giving out of inaccurate information and recording information incorrectly.

She says in her 2013 annual report:

“I am disappointed at the number of complaints HMRC customers feel they need to refer to me in order to get resolution. My role should be to consider the difficult exceptions, not handle routine matters that are well within the capability of departmental staff to resolve successfully. At a time of austerity it is also important to note that the cost of dealing with customer dissatisfaction increases exponentially with every additional level of handling.”

RTI

There are complaints among payroll companies and specialists that real-time information  is not working as well as HMRC has claimed. There seems to be growing irritation with, for example, HMRC’s saying that companies owe much more than they do actually owe. And HMRC has been sending out thousands of tax codes that are wrong or change frequently – or both.

HMRC says it has made improvements but the helpline is appalling. It’s not unusual for callers to wait 30 minutes or more for an answer – or to hang on through multifarious automated messages only to be cut off.

That said there are signs HMRC is, in general, improving slowly. Chief executive of HMRC since 2012 Lin Homer is more down-to-earth and slightly more willing to own up to HMRC’s mistakes than her predecessors, and the fact that RTI and the modernisation of PAYE has got as far as it has is creditable.

But is HMRC a shining example of outsourcing at its best, of outsourcing that cuts costs in the long term? No. A decade of HP and a decade of Capgemini has shown that with outsourcing HMRC can cope, just about, with major changes in tax policy to demanding timetables. But the costs of the outsourcing contracts in the two decades since 1994 have more than tripled.

What about G-Cloud? We look forward to a change in direction from the incoming head of IT Mark Dearnley (if he has much say).

**

A Deloitte survey “The trend of bringing IT back in-house” dated February 2013, said that 48% of respondents in its Global Outsourcing and Insourcing survey 2012 reported that they had terminated an outsourcing agreement early, or for cause, or convenience. Those that took IT services back in-house mentioned cost reduction as a factor. Deloitte said factors included:

– the need for additional internal quality control due to poor quality from the outsourcer

– an increase in the price of service delivery through scope creep and excessive change orders.

Firecontrol disaster and NPfIT – two of a kind?

By Tony Collins

Today’s report of the Public Account Committee on the Firecontrol project could, in many ways, be a report on the consequences of the failure of the National Programme for IT in the NHS in a few years time.

The Firecontrol project was built along similar lines to the NPfIT but on a smaller scale.

With Firecontrol, Whitehall officials wanted to persuade England’s semi-autonomous 46 local fire authorities to take a centrally-bought  IT system while simplifying and unifying their local working practices to adapt to the new technology.

NPfIT followed the same principle on a bigger scale: Whitehall officials wanted to persuade thousands of semi-autonomous NHS organisations to adopt centrally-bought technologies. But persuasion didn’t work, in either the fire services or the NHS.

More similarities

The Department for Communities and Local Government told
the PAC that the Firecontrol control was “over-specified” – that it was unnecessary to have back-up to an incident from a fire authority from the other side of the country.

Many in the NHS said that NPfIT was over-specified. The gold-plated trimmings, and elaborate attempts at standardisation,  made the patient record systems unnecessarily complicated and costly – and too difficult to deliver in practice.

As with the NPfIT, the Firecontrol system was delayed and local staff  had little or no confidence it would ever work, just as the NHS had little or no faith that NPfIT systems would ever work.

Both projects failed. Firecontrol wasted at least £482m. The Department of Communities and Local Government cancelled it in 2010. The Department of Health announced in 2011 that the NPfIT was being dismantled but the contracts with CSC and BT could not be cancelled and the programme is dragging on.

Now the NHS is buying its own local systems that may or may not be interoperable. [Particularly for the long-term sick, especially those who have to go to different specialist centres, it’s important that full and up-to-date medical records go wherever the patients are treated and don’t at the moment, which increases the risks of mistakes.]

Today’s Firecontrol report expresses concern about a new – local – approach to fire services IT. Will the local fire authorities now end up with a multitude of risky local systems, some of which don’t work properly, and are all incompatible, in other words don’t talk to each other?

This may be exactly the concern of a post-2015 government about NHS IT. With the NPfIT slowly dying NHS trusts are buying their own systems. The coalition wants them to interoperate, but will they?  

Could a post-2015 government introduce a new (and probably disastrous) national NHS IT project – son of NPfIT – and justify it by drawing attention to how very different it is to the original NPfIT eg that this time the programme has the buy-in of clinicians?

The warning signs are there, in the PAC’s report on Firecontrol. The report says there are delays on some local IT projects being implemented in fire authorities, and the systems may not be interoperable. The PAC has 

” serious concerns that there are insufficient skills across all fire authorities to ensure that 22 separate local projects can be procured and delivered efficiently in so far as they involve new IT systems”.

National to local – but one extreme to the other?

The PAC report continues

“There are risks to value for money from multiple local projects. Each of the 22 local projects is now procuring the services and systems they need separately.

“Local teams need to have the right skills to get good deals from suppliers and to monitor contracts effectively. We were sceptical that all the teams had the appropriate procurement and IT skills to secure good value for money.

“National support and coordination can help ensure systems are compatible and fire and rescue authorities learn from each other, but the Department has largely devolved these roles to the individual fire and rescue authorities.

“There is a risk that the Department has swung from an overly prescriptive national approach to one that provides insufficient national oversight and coordination and fails to meet national needs or achieve economies of scale. 

Comment

PAC reports are meant to be critical but perhaps the report on Firecontrol could have been a little more positive about the new local approach that has the overwhelming support of the individual fire and rescue authorities.  

Indeed the PAC quotes fire service officials as saying that the local approach is “producing more capability than was expected from the original FiReControl project”. And at a fraction of the cost of Firecontrol.

But the PAC’s Firecontrol Update Report expresses concern that

– projected savings from the local approach are now less than originally predicted

– seven of the 22 projects are running late and two of these projects have slipped by 12 months

– “We have repeatedly seen failures in project management and are concerned that the skills needed for IT procurement may not be present within the individual fire and rescue authorities, some of which have small management teams,” says the PAC.

On the other hand …

The shortfall in projected savings is small – £124m against £126m and all the local programmes are expected to be delivered by March 2015, only three months later than originally planned.

And, as the PAC says, the Department for Communities and Local Government has told MPs that a central peer review team is in place to help share good practice – mainly made up of members of fire and rescue authorities themselves.

In addition, part of the £82m of grant funding to local fire services has been used by some authorities to buy in procurement expertise.

Whether it is absolutely necessary – and worth the expense – for IT in fire services to link up is open to question, perhaps only necessary in a national emergency.

In the NHS it is absolutely necessary for the medical records of the chronically sick to link up – but that does not justify a son-of-NPfIT programme. Linking can be done cheaply by using existing records and having, say, regional servers pull together records from individual hospitals and other sites.

Perhaps the key lesson from the Firecontrol and the NPfIT projects is that large private companies can force their staff to use unified IT systems whereas Whitehall cannot force semi-autonomous public sector organisations to use whatever IT is bought centrally.

It’s right that the fire services are buying local IT and it’s right that the NHS is now too. If the will is there to do it cheaply, linking up the IT in the NHS can be done without huge central administrative edifices.

Lessons from FireControl (and NPfIT?) 

The National Audit Office identifies these main lessons from the failure of Firecontrol:

– Imposing a single national approach on locally accountable fire and rescue authorities that were reluctant to change how they operated

–  Launching the programme too quickly without applying basic project approval checks and balances

– Over optimism on the deliverability of the IT solution.

– Issues with project management including consultants who made up half of the management team and were not effectively managed

MP Margaret Hodge, chair of the Public Accounts Committee, today sums up the state of Firecontrol

“The original FiReControl project was one of the worst cases of project failure we have seen and wasted at least £482 million of taxpayers’ money.

“Three years after the project was cancelled, the DCLG still hasn’t decided what it is going to do with many of the specially designed, high-specification facilities and buildings which had been built. Four of the nine regional control centres are still empty and look likely to remain so.

“The Department has now provided fire and rescue authorities with an additional £82 million to implement a new approach based on 22 separate and locally-led projects.

“The new programme has already slipped by three months and projected savings are now less than originally predicted. Seven of the 22 projects are reportedly running late and two have been delayed by 12 months. We are therefore sceptical that projected savings, benefits and timescales will be achieved.

“Relying on multiple local projects risks value for money. We are not confident that local teams have the right IT and procurement skills to get good deals from suppliers and to monitor contracts effectively.

“There is a risk that the DCLG has swung from an overly prescriptive national approach to one that does not provide enough national oversight and coordination and fails to meet national needs or achieve economies of scale.

 “We want the Department to explain to us how individual fire and rescue authorities with varied degrees of local engagement and collaboration can provide the needed level of interoperability and resilience.

“Devolving decision-making and delivery to local bodies does not remove the duty on the Department to account for value for money. It needs to ensure that national objectives, such as the collaboration needed between fire authorities to deal with national disasters and challenges, are achieved.”

Why weren’t NPfIT projects cancelled?

 NPfIT contracts included commitments that the Department of Health and the NHS allegedly did not keep, which weakened their legal position; and some DH officials did not really want to cancel the NPfIT contracts (indeed senior officials at NHS England seem to be trying to keep NPfIT projects alive through the Health and Social Care Information Centre which is responsible for the local service provider contracts with BT and CSC).

PAC report on Firecontrol

What Firecontrol and the NPfIT have in common (2011)

Defra’s agile plan with multiple suppliers risky says NAO

By Tony Collins

The National Audit Office says in a report published today that Defra’s agile plan which involves outsourcing to multiple IT suppliers has “significant” risks.

The Department for the Environment, Food and Rural Affairs plans to implement a single integrated £80m Common Agricultural Policy (CAP) system built on agile methodologies.

Defra has been working with the Government Digital Service (GDS) to plan an agile implementation and learn from the lessons of the past, the department’s chief operating officer Ian Trenholm told Computer Weekly in January 2013.

Today’s NAO report on Defra’s 2012/13 accounts says that the department is planning the procurement, development and implementation of new systems in line with changes to the way the common agricultural policy operates.

“Development and implementation of these [new systems] will present a number of challenges, including the requirement that data cleansing is completed on time, in order to ensure that accurate and complete data is transferred to the new systems,” says the NAO.

It adds that the IT element of the change programme “will be delivered through an agile approach which involves outsourcing to multiple IT providers”. The NAO says that Defra has recognised a number of significant risks relating to the Programme. “It will need a strong relationship between the Programme team and other important stakeholders, and appropriate governance arrangements, to ensure that these risks are adequately managed and that the Department learns the lessons from the implementation of CAP 2005.”

NAO report on Defra’s 2012/13 accounts.

Comment

Defra and its Rural Payments Agency had a disaster with the Single Payment Scheme which was built on conventional lines through one main supplier. If there are risks with the new agile approach involving multiple suppliers they cannot be as great as spending hundreds of millions of pounds with one company; and working through those new agile-related risks may help other departments find a different and much cheaper way of buying IT, and implementing important policy-related business change.

Universal Credit – good for its IT suppliers?

By Tony Collins

The DWP is conceding in its own tangential way that the IT for Universal Credit is not up to scratch; and an article in the Daily Telegraph suggests that Universal Credit this year (and perhaps well beyond) will handle so few claimants that the calculations for the time being could be done by hand, or on a spreadsheet, and not automatically by IT systems. The Register, through anonymous sources, has confirmation of this.

The FT says there will be a progressive national rollout of the coalition’s welfare reform in just six additional jobcentres which it said was the “latest sign the project is falling behind schedule”. It added that a significant shake-up of the IT underpinning universal credit is under way. 

The DWP said David Pitchford, the Whitehall troubleshooter who took over the running of Universal Credit for three months, had been asked to “review” the IT and ministers had “accepted his recommendation that they should explore enhancing the IT for universal credit working with the government digital service”.

“Advancements in technology since the current system was developed have meant that a more responsive system that is more flexible and secure could potentially be built,” said the DWP.

The FT quoted Howard Shiplee, who has led the Universal Credit  project since May, as denying claims from MPs that the original IT had been dumped because it had not delivered. “The existing systems that we have are working, and working effectively,” he said.

He added that he had set aside 100 days not to stop the programme, but to reflect on where it has got to and start to look at the entire total plan.

Iain Duncan Smith, the work and pensions secretary, doesn’t concede that the  timetable for the implementation of Universal Credit has changed. He told the work and pensions committee on Wednesday that numbers of claimants would ramp up during 2014 and he insisted that all claimants would be on the system by 2017, as originally planned.

“We get fixated on things like IT; the reality is it’s about a cultural shift,” Duncan Smith told MPs.

Comment

Iain Duncan Smith makes it clear that his DWP staff and suppliers, with the help of HMRC, are implementing Universal Credit with extreme care. Labour’s  work and pensions spokesman Liam Byrne says the Universal Credit project is a shambles. The truth is hard to fathom.

For years the DWP has rejected press reports that the IT for Universal Credit was in trouble. It is able to do without fear of authoritative contradiction because it keeps secret all its consultancy reports on the state of the Universal Credit project, despite FOI requests.

The Cabinet Office minister Francis Maude and his officials talk much about the need for openness and transparency. Isn’t it time they persuaded DWP officials to release their internal and external reports on the detailed challenges faced by suppliers and civil servants on Universal Credit and other major government IT projects?

All big government IT projects are characterised by secrecy and defensiveness, although a little information about them is in the vague and subjectively-worded Major Projects Authority annual report.

One by-product of departmental defensiveness and secrecy is that the IT suppliers – in Universal Credit’s case HP, IBM and Accenture – are likely to continue to be paid even if the project is halted and redesigned. It’s probable the suppliers would argue that they have successfully done what they were asked to do in the contract. Who knows what the truth is?

The DWP is in effect protecting its suppliers from public and parliamentary scrutiny. It has been this way for decades and nothing has changed.

Is HMRC’s RTI project really a success?

By Tony Collins

On  Eddie Mair’s “PM” programme on R4, I suggested that HMRC’s real-time information project was not the failure many had expected it to be.

“Even some hawk-eyed critics of government IT projects like journalist Tony Collins think that HMRC may have something of a success on its hands,” said BBC reporter Chris Vallance who produced the RTI item.

I was quoted as saying that many had expected RTI to become another government IT disaster. “But given that there are millions of PAYE employees who are on the system at the moment, if there were any major difficulties we’d expect to have seen them by now.”

Now an HMRC expert has questioned whether my comments were justified. He says parts of RTI are in chaos. He doesn’t want to be named. He writes:

“The RTI system was intended to report on a weekly or monthly basis the same information as had previously been reported by employers on an annual basis. Although details of pay and tax would be forwarded to HMRC far more frequently the same core logic applied. Details of the statutory deductions by the employer would have to be reconciled with payments made, and details of the income and tax paid recorded against the employee’s PAYE record.

“What appears to have happened is that HMRC has designed a system that takes details of employees’ earned or pension income, and statutory PAYE deductions, and then makes various illogical assumptions.

“For instance it would appear that where an employee receives no earnings in a particular pay period, the RTI system assumes that no information is “transmitted” for this employee, indicating that the employee has “left the employment”.

“Similarly where an employer undertakes a re-order of the pay identities (codes on the payroll system called Works Numbers that identify employees), the fact that payroll information is transmitted to HMRC with a Works Number different to that used previously triggers an assumption that the employee has two employments, with the same employer.

“This has the consequence of allowing the NPS (New PAYE Computer System – costing in excess of £400 million) to assume that the employee’s estimated income for the tax year has doubled. The NPS then looks to see if the employee has any part-time or other employment, and in many cases it changes the PAYE code number of these part-time employments from Basic Rate, which deducts tax at 20%, to Code D0, which deducts tax at 40%. All because of an incorrect and invalid assumption.

“Similarly, this failure to understand how PAYE and payroll interact has lead to the situation where an employee who leaves an employment that has attracted a PAYE coding deduction for Car Benefit in Kind and starts another Employment, has the PAYE Coding Deduction removed. The fact that the new employment may well involve a company car is completely ignored, with the result that the employee is more than likely to have a large underpayment of income tax at the year end, despite being on PAYE.

“This failure to understand the basic operation and logic of PAYE would appear to be due to that fact that HMRC has been influenced by those who have an understanding of data flows and cash transfers. The rush to modernise PAYE and move away from “a 1940’s system” has completely omitted the fact that basic operations for employments, tax and NI deductions and the accountability of these remains exactly the same, even if the calculations are undertaken electronically rather than with a quill pen and large ledger book.

“The old PAYE system had as part of its reporting system two components: the forms P14 detailing each individual’s pay, tax etc. and a summary of all employees information, the form P35. The P14 passed information to the NPS system and the P35 information was passed to the accounts computer systems. This allowed HMRC to determine the income of the employee and calculate if sufficient income tax etc had been paid. It also allowed HMRC to match the figure of tax / NIC due and payable on the P35 with the amount actually received from the employer. RTI has failed to comply with this basic logic and chaos is ensuing, to the extent that the National Audit Office recently commented

 ‘The financial and accounting systems supporting RTI are not yet fully accredited. Financial accreditation is a formal requirement of HMRC’s Change Programme and provides assurance that any new systems are acceptable for accounting and financial control purposes. The RTI systems went live on the basis that action would be taken to resolve identified financial design issues by 31 October 2013.

‘These issues do not affect an employer’s ability to submit data to HMRC but do weaken HMRC’s ability to produce and report financial information on PAYE. HMRC is currently undertaking work to understand the impact of these issues and how best to address them.’

“Why the RTI system was not designed in the same logical manner is of great concern.

“The system failures that are occurring are not due to computer components or programs not being fit for purpose. Indeed the processing of the PAYE data streamed to HMRC as a result of the RTI system could reasonably be compared to any other large commercial organisation, albeit that the NAO has concerns over the fall-back planning HMRC has in place should there be any hardware failures and commented

‘The resilience needed to maintain the RTI service if there is a major technical failure is not in place. Online and time-sensitive system implementations are usually developed with formal technical resilience and disaster recovery capability.

‘HMRC chose not to pay for full resilience because of the cost implications and because PAYE could be operated in an emergency without RTI. However, although RTI has the potential to be used by other government departments, the lack of full resilience may inhibit its use in areas of activity where a temporary disruption to service cannot be tolerated.

‘Data submissions can be held temporarily in a queue but this would not provide continuity of service in the event of a catastrophic failure. The RTI service failing at a critical processing time could increase the volume of customer communications and lead to more effort for employers.’

“The RTI system is a very clear example of basic failures to properly prepare a Business Analysis Requirement for a system which in essence does no more that increase the number of times payroll information is passed to HMRC. Claims for the reinvention of PAYE for the 21st Century are as invalid as the claim that the ability to write has been done away with due to email and electronic communication. There has been a flawed reliance on the thoughts and views of those who have little or no experience in PAYE or payroll.”

On the PM programme, Ruth Owen, Director General of PersonalTax at HMRC, accepted that all was not perfect. She said

“We have had over 1.4 million PAYE schemes come into Real-Time Information [each PAYE scheme may have many employees on it] and that exceeds our expectations at this point in the year. But there’s still more to do. We have got to get everybody on and there are still people who need our help to get on.”

She added: “We have had a small number of difficult issues… We have had issues where people have got the wrong tax codes.”

Owen said the links between RTI and Universal Credit were “going well” but conceded that there have been only a tiny number of UC claimants so far.

“We have had around 100 claimants who we have helped DWP identify income stream data for. So it’s going to plan at the moment.”

Chris Vallance concluded the item by saying that some of the largest employers have yet to be added to RTI. “It’s only when it works at scale that we will really know how good real-time information really is,” he said.

Update: Chartered accountant Baker Tilly says on its website  that thousands of people have been issued wrong tax codes as a result of RTI-related problems. 

Audio of PM programme item on RTI – 4 July 2013 (approx 5 mins)

EC probes IBM CIO secondment at the Met Office

By Tony Collins

A part of the European Commission is investigating a decision by the Met Office to appoint an IBM executive as CIO while he worked at the same time for IBM, the organisation’s main IT supplier.

The investigation was prompted by concerns of campaigner Dave Orr who wrote to the EC about the Met Office’s appointment of an IBM secondee David Young as CIO for two years between 2010 and December 2012.

Now Michel Barnier, the EC Commissioner responsible for internal market and services, says in a letter to Orr’s MEP Sir Graham Watson that the EC’s Directorate-General for Internal Market and Financial Services has been carrying out “an in-depth analysis” of the facts presented by Orr.

As part of this, the EC has written to the UK government seeking clarification on a number of points.

Some of Orr’s concerns arise from the Met Office’s responses – and non-responses – to his freedom of information requests. One of his concerns is of a potentially cosy relationship between the Met Office as a publicly-funded organisation and its principal IT supplier IBM; and he has wanted to know why the job of Met Office CIO was not openly advertised in a competitive recruitment process and whether its appointment of an IBM secondee had the potential for a possible conflict of interest.

Orr said that the secondment had the potential to confer a unique and significant intelligence and relationship advantage for IBM that other supercomputer suppliers could not hope to match. “In my view, that is anti-competitive and may in spirit at least, fail the EU procurement rules,” said Orr.

Barnier said that the existence of a conflict of interest would “depend on a number of factors such as the precise role and responsibilities the position entails, in particular whether it includes formulating and preparing technical specifications or tender documents for future IT contracts that the Met Office may put out to tender”.

It is also relevant, said Barnier, whether the terms and conditions of the secondment “impose any obligations or restrictions on the head of the department to prevent conflicts of interest, both during the secondment and afterwards”. He also wanted to know if internal rules were in place to prevent conflicts of interest in the course of tendering procedures.

The Met Office and ministers said that Young was not involved in procurement decisions relating to existing supercomputer facilities. Norman Lamb, then minister at the Department for Business Innovation and Skills, said last year:

“Any potential conflicts of interest regarding David Young’s appointment were fully considered prior to his appointment and his terms of engagement specifically cover these …

“David Young had no involvement in the procurement process for existing supercomputing facilities, either for IBM or the Met Office, and he will have completed his secondment and left the Met Office prior to the selection of replacement supercomputer facilities.”

A wise decision?

The decision to second an IBM employee to run the 300-strong IT department, which is based at the Met Office’s supercomputer site in Exeter, raises questions that may go beyond the potential for a conflict of interest.

As Young was unable to be involved in some buying decisions and was unable to attend the technology strategy board to avoid any potential for a conflict of interest, did the Met Office restrict itself unnecessarily in hiring a CIO who faced these constraints?

Did the Met Office waste money – and a precious two years – hiring a lifeguard whose terms of employment required him to wear handcuffs?

The secondment of Young came at a difficult time for the Met Office – and some of the main difficulties it faced in 2010 are largely the same today.

Responses to Orr’s FOI requests and a report by the House of Commons’ Science and Technology Committee highlight some of the Met Office’s challenges:

– A need for modernised software that will take advantage of next-generation supercomputers.

– A need for a replacement supercomputer that has twice the power of the existing one which operates close to one petaflop (one thousand million million floating point operations per second).

– Funding a new supercomputer (with optimised software) at a time of cut-backs in government spending.

A Met Office Executive Board paper said that its executives have had “soft” negotiations with various suppliers about next generation supercomputer technology. They spoke to Bull, Cray, Microsoft, NEC and SGI.

“Vendor presentations indicate that performance increases will come from increasing the number of processors and/or adding co processors designed to process arrays of data efficiently, rather than increasing the speed of individual processors,” said the Met Office paper.

The Met Office says that “significant optimisation work will be needed [on the code] and, if this is not completed around 2014, a delay in the launch of the procurement may be unavoidable.” It has been seeking software engineers with experience of Fortran (which was originally developed by IBM) or C, Unix or Linux and Perl.

A House of Commons report in 2012 emphasised the need for new technology at the Met Office. The report of the Science and Technology Committee “Met Office Science” said in February 2012:

“It is of great concern to us that these scientific advances in weather forecasting and the associated public benefits (particularly in regard to severe weather warnings) are ready and waiting but are being held back by insufficient supercomputing capacity. We consider that a step-change in supercomputing capacity is required in the UK.”

MPs acknowledged that “affordability is an issue.”

The Met Office declined to answer Orr’s FOI requests about the cost to the taxpayer of employing Young.

Since Young’s  secondment ended in December 2012 the Met Office has hired one of its own employees as CIO. Charles Ewen has worked for the Met Office since 2008. He works with science teams to operate the Met Office’s high performance computing facilities. He is responsible for the development and implementation of the Met Office’s ICT Strategy and for the internal technical teams within the Technology Information Services Directorate.

Comment:

The Met Office hired Young for the best of reasons: after a succession of internal management changes it wanted a highly professional, stabilising CIO. But did it need a CIO from IBM, its principal IT supplier?

That the Met Office was sheepish about the appointment of an IBM secondee was, perhaps, revealed by its website which, in giving a profile of Young, did not mention – at first – that he was seconded from IBM. After Dave Orr’s FOI requests the Met Office corrected its website omission, making clear that Young was on secondment from IBM.

The Met Office has been in existence nearly 16o years. It was founded by Vice-Admiral Robert FitzRoy in 1854 as the Meteorological Department of the Board of Trade. It is highly regarded internationally. A testament to the quality of its computer models  – which are used for daily forecasts – is that its “Unified Model” is licensed in Norway, Australia, South Korea, South Africa, India, New Zealand and the US Air Force.

Scientists say that a three-day forecast today is as accurate as a one-day forecast was 20 years ago. But in the UK the Met Office gets a bad press – not always unjustifiably.  There is a perception that the accuracy of forecasting is not improving. Sometimes it seems poor.

The algorithms that form the basis of weather and climate models place huge demands on supercomputing architectures. The models produce exceptionally large volumes of data. Although the Met Office had a new IBM supercomputer in 2008 it soon needed more powerful hardware and modernised software.

So was it a good idea, with all the challenges the Met Office faced in 2010 – including the need to persuade the government of the need to fund  new supercomputer facilities – to appoint a CIO for two years who, because he was an IBM secondee, had understandable restrictions on his freedom to do his job, restrictions the Met Office has been reluctant to reveal, despite Dave Orr’s FOI requests?

Hole in the head

The Met Office may regard an EC inquiry into its appointment of an IBM secondee as the last thing it needs now. But accountability should not be left to the occasional scrutiny by a Commons committee – or to Dave Orr’s FOI requests.

Whitehall to lose its best troubleshooter

By Tony Collins

David Pitchford, who is arguably the civil service’s most able troubleshooter, is to quit the civil service in September and return to his native Australia for undisclosed family reasons. The FT broke the story yesterday.

Pitchford is Executive Director at the understaffed Major Projects Authority. It aims to work in partnership with permanent secretaries and senior civil servants to improve the success rate of major departmental IT and other large projects. 

In practice some senior civil servants in central departments resent the intrusion of the Cabinet Office. They do not like having to present their big schemes to the Major Projects Authority, particularly as it has David Cameron’s mandate to stop or re-scope failing projects.

Fighting intransigence? 

One unanswered question about Pitchford’s quitting is: has his morale been beaten down by departmental intransigence and even ill-will? Has the system defeated Pitchford and the taxpayer – the same system that confronted other Cabinet Office reformers John Suffolk, Chris Chant and Andy Tait?

It is possible that Pitchford feels his work is done now that the Major Projects Authority has finally, and after some departmental resistance, produced its first annual report.

The report’s key feature is its “traffic light” status on the projects it is keeping an eye on. In a foreword to the report, Pitchford wrote:

“April 2013 marks two years of the Major Projects Authority… For the first time, the country’s biggest and most high-risk projects are scrutinised so problems are exposed before they spiral out of control. Over two-thirds of major projects are predicted to deliver their promises on time and on budget, more than double the historic success rate. However, the MPA has studied carefully what goes on in every department, and we have uncovered some weaknesses which we are continuing to address.

“The MPA was established following a landmark report by the National Audit Office in 2010, which recommended a wholesale shift in the administration of major projects. It works closely with individual departments’ project teams and Permanent Secretaries to monitor and improve the management of major projects…the MPA’s Government Major Projects Portfolio has improved the rate of successful project delivery from under 30% to over 70%.

“Our success has been achieved by focusing intensively on the three core elements of successful project management: improving leadership; improving the operating environment; and looking closely at the past lessons.”

Pitchford is a much-valued executive in part because he can see why projects are failing and is straight-talking. He joined the Cabinet Office in November 2009 and in 2010 told a conference what he had discovered so far about the reasons for the failure of UK government projects:

– Political pressure

– No business case

– No agreed budget

– 80% of projects launched before 1,2 & 3 have been resolved

– Sole solution approach (options not considered)

– Lack of Commercial capability – (contract / administration)

– No plan

– No timescale

– No defined benefits

Since then Pitchford has been a little more guarded now about what he says in public. Campaign4Change said in February 2013 that the longer he stays in the innately secretive civil service the more guarded he seems to become but he is still one the best assets the Cabinet Office has. His main advantage is his independence from government departments.

Francis Maude, Cabinet Office minister, said he would “much miss David’s sharp wit and impressive leadership”.

Is Pitchford’s departure a sign that the non-reformers in Whitehall departments are winning the battle against major change?

 

When Whitehall shuns statutory scrutiny

By Tony Collins

In some ways central departments are deeply accountable.

They provide volumes of statistics and reports to the centre of government (Cabinet Office and Treasury) – as far as their limited management information systems will let them – and senior officers will sometimes answer questions from MPs on Parliamentary committees. Their permanent secretaries will meet colleagues in other departments every week.

At the same time, on things that really matter, some central departments – and councils – can be infinitely unaccountable. 

A report by the National Audit Office – which it says was researched and written unusually quickly, partly in response to parliamentary concern – gives a glimpse of how unaccountable central departments (and councils) can be.

When they don’t want to provide information they simply don’t – and nothing it seems can be done to force disclosure.

Power to ignore

With explicit and written approval from David Cameron the Cabinet Office has the power to mandate change in central departments. But senior officials can, if they wish, when faced with central requests for information, ignore, reject, deliberately misunderstand, confuse or minimise answers, or delay until the request no longer need be answered.

This ability of central departments to evade democratic and even statutory scrutiny surfaces in the NAO report Confidentiality clauses and special severance payments.

The report is into the gagging of public servants when they receive payments for ending their employments early. Rightly, the media’s coverage of the report focuses on the NAO’s concerns over gagging clauses that stop officials becoming whistleblowers. The FT said on Friday (21 June 2013)

“More than a thousand civil servants have signed gagging clauses that could stop them speaking out about problems, a system the [NAO] condemned as “unacceptable”.

What the national media apparently did not notice was that the NAO was unable to obtain all the information it had requested of departments.

“Despite the NAO’s statutory access rights, it received only 60 per cent of the compromise agreements requested from departments,” says the NAO.

The NAO has statutory rights of access to information held by departments. Indeed its Comptroller and Auditor General Amyas Morse certifies the accounts of all government departments and many other public sector bodies. The NAO says he has “statutory authority to examine and report to Parliament on whether departments and the bodies they fund have used their resources efficiently, effectively, and with economy”.

Avoiding NAO scrutiny

But some departments have not complied with the NAO’s requests, and one, the Department of Culture, Media & Sport, formally requested not to be involved in the NAO’s investigation.

Says the NAO report

“Unfortunately, some departments did not respond promptly to our requests, and were delayed by their legal teams’ questioning of our access rights.

The NAO adds

“The Department for Culture, Media & Sport requested not to be involved in this piece of work, a position which could not be resolved until after our fieldwork window had closed.

“We found it challenging to gain a complete picture of the use of confidentiality clauses as, by their nature, they are not openly discussed. Our work was also hampered by incomplete records, and access to data as outlined above.

“It took several attempts to identify the appropriate individuals within departments responsible for compromise agreements and the associated payments. We experienced delays in receiving data, and what departments provided was frequently incomplete or in a format that was difficult to collate and analyse.”

So what can the NAO do now it has been snubbed or, to put it in Whitehall-speak, has encountered departmental non-compliance with statutory access requests?

Little or nothing. The NAO has no power to punish. Through MPs on the Public Accounts Committee it can admonish. That is all.

Says the NAO:

“Given the innovative nature of this work, some initial difficulties were anticipated. We will continue to work with departments, the Treasury and Cabinet Office to explore ways in which we can obtain the evidence on a timelier basis. It is important that departments are able to respond more quickly to these investigations in the future.”

Councils too can evade democratic accountability. The NAO has no access rights to local authorities but councils are, in theory, subject to the Freedom of Information Act. In practice they can all but ignore the FOI legislation if they wish.

In March 2010, the Audit Commission published a report on severance payments to council chief executives. The study found that:

• agreed severance packages for 37 council chief executives totalled £9.5 million, 40 per cent of which were in pension benefits;

• three in every ten outgoing council chief executives received a pay-off;

• the average cost to councils of each severance package was almost double the annual basic salary, but in four cases was more than triple; and

• 79 per cent of mutually-agreed severance payments had a confidentiality clause.

But the NAO found that, in a recent survey of councils by a member of the public under the FoI Act, 52 councils refused to disclose information on their use of compromise agreements.

The good news

The NAO says: “Some organisations have chosen to be transparent about severance packages, such as NHS National Services Scotland, who agreed to the disclosure of a director’s remuneration package, despite a confidentiality agreement being in place, following consultation with legal advisers.”

Comment:

How is Francis Maude to reform central government, particularly IT, if officials in central departments can apparently do what they wish?

The NAO found cases of payments that were higher than contractual entitlement, where there was the apparent reward for failure, and no attempt to seek Treasury’s approval.  Is all this lawful? 

On top of this there are departmental officials who avoided the NAO’s statutory requests for information.

If they can circumvent the law they can probably resist any central demands for change. Resistance seems to be regarded within departments as honourable.

One irony is that bureaucrats in Russia probably have little choice but to respond to central demands – whereas officials in Whitehall departments don’t have to.

Radical reform to change Whitehall’s outdated and costly ways is unlikely to happen while senior officers in departments run the system and have the final say.

NAO report “Confidentiality clauses and special severance payments

Francis Maude boasts of £10bn savings but …

By Tony Collins 

This morning Cabinet Office minister Francis Maude held a press conference with his senior officials to announce that civil servants have radically changed the way they work to save £10bn in 2012/13.

The savings are nearly £2bn higher than originally planned and, according to the Cabinet Office, have been “reviewed and verified” by independent auditors.

With a little journalistic licence Maude says: “…we are on the way to managing our finances like the best-run FTSE100 businesses.”

The breakdown of the £10bn savings:

Procurement   £3.8bn
Centralisation of procurement for common goods and services  £1.0bn
Centrally renegotiating large government contracts  £0.8bn
Limiting expenditure on marketing and advertising, consultants and temporary agency staff   £1.9bn
Transformation savings   £1.1bn
IT spend controls and moving government services and transactions onto digital platforms  £0.5bn
Optimising the government’s property portfolio  £0.6bn
Project savings   £1.7bn
Reviewing performance of major government projects  £1.2bn
Taking waste out of the construction process  £0.4bn
Workforce savings   £3.4bn
Reducing the size of the Civil Service   £2.2bn
Increasing contributions to public sector pensions   £1.1bn

Comment

It’s good news and the figures don’t seem plucked out of thin air which sometimes happens when central government announces savings.

The big question is whether the savings are sustainable. Maude has inspired the Cabinet Office’s Efficiency and Reform Group to be motivated and hard-working. But bringing about long-term change in Whitehall – as opposed to restricting consultancy contracts and cutting annual costs of supplier contracts by reducing what’s delivered – is like peddling uphill. How long can you do it without losing motivation and energy? It’s not just parts of the civil service that are resistant to the savings agenda – it is also some IT suppliers, according to Government Computing.

It’s likely that only profound changes in central government operations and working practices will outlast the next general election. At the moment the civil service is like a rubber band that has been stretched a little. It wants to return to its standard shape, which the next government may allow it to do.

The National Audit Office said in its report in April 2012 on the Efficiency and Reform Group in 2011/12:

“Savings to date have differing degrees of sustainability.”

The NAO also said this:

“It is not fully clear how ERG intends to make the reforms necessary to secure enough savings over the rest of the spending review. ERG has yet to translate its ambition for saving £20 billion by 2014-15 into more detailed plans.

“ERG has made progress in developing strategies across its wide range of responsibilities, and is focusing on core activities likely to produce savings. However, until recently ERG’s focus has mainly been on the savings themselves, with less emphasis on delivery of the longer-term changes and improvement in efficiency necessary to make them sustainable.”

And this:

“Departments have still tended to lack a clear strategic vision of what they are to do, what they are not, and the most cost-effective way of delivering it. Much of departments’ 2014-15 savings are likely to come from further reductions in staff. Sustainability of these savings will depend on developing skills and working in new ways while maintaining staff motivation and engagement.”

But the NAO was generally positive about the ERG’s contribution to savings.

“ERG’s actions to date, particularly its spending controls, have helped departments deliver substantial spending reductions.”

We hope the Cabinet Office’s diligent efforts continue  – sustainably.

Efficiency and Reform 2012/13 savings. Summary report.