Why does truth on Universal Credit emerge only now?

By Tony Collins

For nearly a year the Department for Work and Pensions, its ministers and senior officials, have told Parliament that Universal Credit IT is on track and on budget.

Together with DWP press officers, they have criticised parts of the media and some MPs for suggesting otherwise.

Now the truth can be held back no longer: the National Audit Office is expected tomorrow to report on UC’s problems. Ahead of that report’s publication, and perhaps to take the sting out of it, work and pensions secretary Iain Duncan Smith has allowed Howard Shiplee, the latest DWP lead on delivery of UC, to own up to the project’s difficulties.

IDS has given permission for Shiplee to write an article for the Telegraph on the UC project. Every word is  likely to have been checked by senior DWP communications officers.

It’s the first time anyone on the UC project has publicly acknowledged the project’s difficulties though, as with nearly every government response to critical NAO reports, the administration depicts the problems as in the past. Shiplee’s article says

“… it’s also clear to me there were examples of poor project management in the past, a lack of transparency where the focus was too much on what was going well and not enough on what wasn’t and with suppliers not managed as they should have been.

“There is no doubt there have been missteps along the way. But we’ve put that right…

“I’m not in the business of making excuses, and I think it’s always important to acknowledge in any project where things may have gone wrong in order to ensure we learn as we go forward.

“To that end, the key decision taken by the Secretary of State to reset the programme to ensure its delivery on time and within budget has been critical.

“When David Pitchford arrived from the Major Projects Authority earlier this year, at the Secretary of State’s request, he began this process in line with those twin objectives…

“I’ve also ensured that as a programme we have a tight grip on our spending, and I have put in place a post for a new Director who will be dedicated to ensuring that suppliers deliver value for money. I am confident we are now back on course and the challenges are being handled.”

Parliament has a right to ask why nearly every central government IT project that goes wrong – whatever the government in power – is preceded for months and sometimes years in the case of the NPfIT by public denials.

From the over-budget and fragmented Operational Strategy project for welfare benefits in the 1980s, to the repeatedly delayed and over budget air traffic control IT at the New En Route Centre at Swanwick, Hampshire, and the abandoned Post Office “Pathway” project in the 1990s, to the failed National Programme for IT – NPfIT –  in the NHS in the last decade, ministers and senior officials were telling Parliament that all was well and that the project’s critics were misinformed. Until the facts became only too obvious to be denied any longer.

These are some of the reassurances ministers and DWP officials have been giving Parliament and the media about the UC project. None of their statements has given a hint of the  “missteps along the way” that Shiplee’s article refers to now.

House of Commons, 20 May 2013

Universal Credit (IT System)

Clive Betts (Lab): What assessment he [the secretary of state for work and pensions] has made of the preparedness of the universal credit IT delivery system.

Iain Duncan Smith: The IT system to support the pathfinder roll-out from April 2013 is up and running…

Betts: I thank the Secretary of State for that answer, but will he confirm that three of the pathfinders are not going ahead precisely because the computer system is not ready? …

Duncan Smith: The hon. Gentleman is fundamentally wrong. All the pathfinders are going ahead. The IT system is but a part of that, and goes ahead in one of the pathfinders. The other three are already testing all the other aspects of universal credit and in July will, essentially, themselves roll out the remainder of the pathfinder, and more than 7,000 people will be engaged in it. All that nonsense the hon. Gentleman has just said is completely untrue.”

**

BBC – 9 Sept 2012

 “A Department for Work and Pensions spokeswoman said: “Liam Byrne [Labour] is quite simply wrong. Universal Credit is on track and on budget. To suggest anything else is incorrect.”

**

Iain Duncan Smith, House of Commons, 20 May 2013

“This [Universal Credit] system is a success. We have four years to roll it out, we are rolling it out now, we will continue the roll-out nationwide and we will have a system that works—and one that works because we have tested it properly.”

Howard Shiplee – FT July 2013

“… Howard Shiplee, who has led UC since May, denied claims from MPs that the original IT had been ‘dumped’ because it had not delivered. ‘The existing systems that we have are working, and working effectively,’ he said. He added, however, that he had set aside 100 days ‘not to stop the programme, but to reflect on where we’ve got to and start to look at the entire total plan’.”

**

DWP spokesperson 16 August 2013

“… a DWP spokesperson said: “The IT supporting Universal Credit is working well and the vast majority of people are claiming online.”

**

Howard Shiplee Work and Pensions Committee, House of Commons, 10 July 2013.

“…The pathfinder, first of all, has demonstrated that the IT systems work…”

Mark Hoban, DWP minister, House of Commons, 6 March 2013.

The shadow Secretary of State has been touting this story for months. No it has been longer than that. The last outing was in today’s Guardian. I want to make it clear that nobody has walked off the project; all the contractors are in place and the project is on schedule to be delivered at the end of April. Now, if he thinks the idea is good in theory, it is about time he supported it. It is working and the contractors are in place, doing the job and ensuring that the pilots will be up and running at the end of April.”

[Hoban’s response was to a question on whether personnel or contractors at Accenture, Atos Origin, Oracle, Red Hat, CACI or IBM UK had been stepped down, or in any way notified by the Department, that they were to suspend work on Universal Credit. The main IT contractors for UC are Accenture, Hewlett Packard and BT plus input from Agile specialists Emergn. The DWP awarded UC IT contracts without any specific open competitive tender.]

Comment

On this site various posts have questioned whether Iain Duncan Smith has been getting the whole truth on the state of the UC IT project. He repeatedly went before MPs of the Work and Pensions Committee and gave such confident reassurances on the state of the UC project that it was difficult to believe that he knew what was really going on.

What we now know about the UC project’s “missteps along the way” shows, if nothing else, how gullible ministers are in believing their officials.

It is hard or impossible to believe that officials would lie but it is probable they would tell their ministers what they want to hear – and IDS has been in no mood to hear about problems.

Every big IT-based project in government that is failing ends up in a pantomime. From the back of the auditorium the media and MPs shout out when they receive leaks about problems. “Look behind you – there’s chaos,” they call out to departmental ministers and officials who don’t look behind them and reply “Oh no there isn’t!”

One reason this pantomime is repeated over decades is that independent reports on the progress or otherwise on big IT-based projects and programmes in central government are kept under departmental lock and key.  Even FOI requests for the keys consistently fail

So it’s usual for ministers and officials to answer media and Parliamentary questions about departmental projects without fear of authoritative contradiction.

Until the NAO is in imminent danger of publishing  a revealing report.

Perhaps it’s a lack of openness and accountability that contributes to IT-enabled change projects in central government going seriously awry in the first place.

With openness would come early and public recognition of a scheme that’s too ambitious to be implementable. With secrecy and the gung-ho optimism that seems to pervade projects like Universal Credit many on the project pretend to each other and perhaps even themselves that it’s all doable, while money continues to be thrown away.

When will the pantomime of misinformation and long-delayed revelation stop? Perhaps when Whitehall becomes genuinely open and accountable on the progress or otherwise of its IT-enabled projects. In other words: never.

Thank you to David Moss for drawing my attention to Howard Shiplee’s article in the Telegraph.

Time for truth on Universal Credit

Millions of pounds worth of secret DWP reports

Universal Credit – good for its IT suppliers?

By Tony Collins

The DWP is conceding in its own tangential way that the IT for Universal Credit is not up to scratch; and an article in the Daily Telegraph suggests that Universal Credit this year (and perhaps well beyond) will handle so few claimants that the calculations for the time being could be done by hand, or on a spreadsheet, and not automatically by IT systems. The Register, through anonymous sources, has confirmation of this.

The FT says there will be a progressive national rollout of the coalition’s welfare reform in just six additional jobcentres which it said was the “latest sign the project is falling behind schedule”. It added that a significant shake-up of the IT underpinning universal credit is under way. 

The DWP said David Pitchford, the Whitehall troubleshooter who took over the running of Universal Credit for three months, had been asked to “review” the IT and ministers had “accepted his recommendation that they should explore enhancing the IT for universal credit working with the government digital service”.

“Advancements in technology since the current system was developed have meant that a more responsive system that is more flexible and secure could potentially be built,” said the DWP.

The FT quoted Howard Shiplee, who has led the Universal Credit  project since May, as denying claims from MPs that the original IT had been dumped because it had not delivered. “The existing systems that we have are working, and working effectively,” he said.

He added that he had set aside 100 days not to stop the programme, but to reflect on where it has got to and start to look at the entire total plan.

Iain Duncan Smith, the work and pensions secretary, doesn’t concede that the  timetable for the implementation of Universal Credit has changed. He told the work and pensions committee on Wednesday that numbers of claimants would ramp up during 2014 and he insisted that all claimants would be on the system by 2017, as originally planned.

“We get fixated on things like IT; the reality is it’s about a cultural shift,” Duncan Smith told MPs.

Comment

Iain Duncan Smith makes it clear that his DWP staff and suppliers, with the help of HMRC, are implementing Universal Credit with extreme care. Labour’s  work and pensions spokesman Liam Byrne says the Universal Credit project is a shambles. The truth is hard to fathom.

For years the DWP has rejected press reports that the IT for Universal Credit was in trouble. It is able to do without fear of authoritative contradiction because it keeps secret all its consultancy reports on the state of the Universal Credit project, despite FOI requests.

The Cabinet Office minister Francis Maude and his officials talk much about the need for openness and transparency. Isn’t it time they persuaded DWP officials to release their internal and external reports on the detailed challenges faced by suppliers and civil servants on Universal Credit and other major government IT projects?

All big government IT projects are characterised by secrecy and defensiveness, although a little information about them is in the vague and subjectively-worded Major Projects Authority annual report.

One by-product of departmental defensiveness and secrecy is that the IT suppliers – in Universal Credit’s case HP, IBM and Accenture – are likely to continue to be paid even if the project is halted and redesigned. It’s probable the suppliers would argue that they have successfully done what they were asked to do in the contract. Who knows what the truth is?

The DWP is in effect protecting its suppliers from public and parliamentary scrutiny. It has been this way for decades and nothing has changed.

Big IT suppliers and their Whitehall “hostages”

By Tony Collins

Mark Thompson is a senior lecturer in information systems at Cambridge Judge Business School, ICT futures advisor to the Cabinet Office and strategy director at consultancy Methods.

Last month he said in a Guardian comment that central government departments are “increasingly being held hostage by a handful of huge, often overseas, suppliers of customised all-or-nothing IT systems”.

Some senior officials are happy to be held captive.

“Unfortunately, hostage and hostage taker have become closely aligned in Stockholm-syndrome fashion.

“Many people in the public sector now design, procure, manage and evaluate these IT systems and ignore the exploitative nature of the relationship,” said Thompson.

The Stockholm syndrome is a psychological phenomenon in which hostages bond with their captors, sometimes to the point of defending them.

This month the Foreign and Commonwealth Office issued  a pre-tender notice for Oracle ERP systems. Worth between £250m and £750m, the framework will be open to all central government departments, arms length bodies and agencies and will replace the current “Prism” contract with Capgemini.  

It’s an old-style centralised framework that, says Chris Chant, former Executive Director at the Cabinet Office who was its head of G-Cloud, will have Oracle popping champagne corks. 

“This is a 1993 answer to a 2013 problem,” he told Computer Weekly.

In the same vein, Georgina O’Toole at Techmarketview says that central departments are staying with big Oracle ERP systems.   

She said the framework “appears to support departments continuing to run Oracle or, indeed, choosing to move to Oracle”. This is “surprising as when the Shared Services strategy was published in December, the Cabinet Office continued to highlight the cost of running Oracle ERP…”

She said the framework sends a  message that the Cabinet Office has had to accept that some departments and agencies are not going to move away from Oracle or SAP.

“The best the Cabinet Office can do is ensure they are getting the best deal. There’s no doubt there will be plenty of SIs looking to protect their existing relationships by getting a place on the FCO framework.”

G-Cloud and open standards?

Is the FCO framework another sign that the Cabinet Office, in trying to cut the high costs of central government IT, cannot break the bond – the willing hostage-captive relationship –  between big suppliers and central departments?

The framework appears to bypass G-Cloud in which departments are not tied to a particular company. It also appears to cock a snook at the idea of replacing  proprietary with open systems.

Mark Thompson said in his Guardian comment: 

– Administrative IT systems, which cost 1% of GDP, have become a byword for complexity, opacity, expense and poor delivery.

– Departments can break free from the straitjackets of their existing systems and begin to procure technology in smaller, standardised building blocks, creating demand for standard components across government. This will provide opportunities for less expensive SMEs and stimulate the local economy.

– Open, interoperable platforms for government IT will help avoid the mass duplication of proprietary processes and systems across departments that currently waste billions.

–  A negative reaction to the government’s open standards policy from some monopolistic suppliers is not surprising.

Comment

It seems that Oracle and the FCO have convinced each other that the new framework represents change.  But, as Chris Chant says, it is more of the same.

If there is an exit door from captivity the big suppliers are ushering senior officials in departments towards it saying politely “you first” and the officials are equally deferential saying “no – you first”. In the end they agree to stay where they are.

Will Thompson’s comments make any difference?

Some top officials in central departments – highly respected individuals – will dismiss Thompson’s criticisms of government IT because they believe the civil service and its experienced suppliers are doing a good job: they are keeping systems of labyrinthine complexity running unnoticeably smoothly for the millions of people who rely on government IT.

Those officials don’t want to mess too much with existing systems and big IT contracts in case government systems start to become unreliable which, they argue, could badly affect millions of people.

These same officials will advocate reform of systems of lesser importance such as those involving government websites; and they will champion agile and IT-related reforms that don’t affect them or their big IT contracts.

In a sense they are right. But they ignore the fact that government IT costs much too much. They may also exaggerate the extent to which government IT works well. Indeed they are too quick to dismiss criticisms of government IT including those made by the National Audit Office.

In numerous reports the NAO has drawn attention to weaknesses such as the lack of reliable management information and unacceptable levels of fraud and internal error in the big departments. The NAO has qualified the accounts of the two biggest non-military IT spending departments, the DWP and HMRC.

Ostensible reformers are barriers to genuine change.  They need to be replaced with fresh-thinking civil servants who recognise the impossibility of living with mega IT contracts.

Mark Thompson’s Guardian article.

Universal Credit – the ace up Duncan Smith’s sleeve?

By Tony Collins

Some people, including those in the know, suspect  Universal Credit will be a failed IT-based project, among them Francis Maude. As Cabinet Office minister Maude is ultimately responsible for the Major Projects Authority which has the job, among other things, of averting major project failures.

But Iain Duncan Smith, the DWP secretary of state, has an ace up his sleeve: the initial go-live of Universal Credit is so limited in scope that claims could be managed by hand, at least in part.

The DWP’s FAQs suggest that Universal Credit will handle, in its first phase due to start in October 2013, only new claims  – and only those from the unemployed.  Under such a light load the system is unlikely to fail, as any particularly complicated claims could managed clerically. 

The second phase of Universal Credit, which is due to begin in April 2014, is the important one, in terms of number of claimants. But this phase may be delayed with a general election approaching, according to Government Computing, which quotes the FT.

This is from the DWP’s website:

“Universal Credit will start to take new claims from unemployed people in October 2013.”

It continues:

“For people in work this process will begin in April 2014. The remainder of current claims will be moved to Universal Credit from 2014, with the process being complete by 2017.”

Comment: 

The projected costs of real-time information, an HMRC project on which the success of Universal Credit depends, have increased by tens of millions from an initial estimate of £108m, according to Ruth Owen, Director General, Personal Tax, HMRC.  At least HMRC is being open about RTI – relative to the DWP which continues to deny FOI requests for the risk register or independent assessments of the progress or otherwise of the Universal Credit IT project.

Auditors at the National Audit Office found that the Rural Payment Agency’s Single Payment Scheme for farmers dealt with so few claims that it could have been handled manually for a fraction of the cost of an IT system that went awry. Perhaps Iain Duncan Smith has learnt from that episode.

As Universal Credit phase one will handle only new claims from the unemployed, there may be no need initially for complicated monthly interactions with HMRC’s Real-time information [PAYE] systems. 

There may be further restrictions on go-live UC candidates. The DWP may insist that unemployed new claimants are single, childless, between certain ages and not receiving certain benefits or tax credits. They may have to have a valid bank account.

So the numbers of claimants and simplified processing will maximise the chances of a go-live success.

This may explain why the Major Projects Authority has not intervened (yet) to delay the October 2013 go-live date.   

It makes sense to minimise complications when going live. But the Passport Agency found that although the go-live of new systems in 1999 went well, extra IT-related security checks slowed down the issuing of passports, such that backlogs built up, people lost their holidays and queues built up at passport offices. It was a project disaster. 

The real test of the agile-based Universal Credit project will be when existing benefit claimants move onto the new systems in large numbers. This will not happen before the next general election. The plan is for the roll-out to be completed by the end of 2017.

Meanwhile does Iain Duncan Smith plan to claim a victory for the go-live of Universal Credit when the initial transactions are so simple, and the numbers involved  so insignificant, they could be managed clerically if necessary?

 As long as Universal Credit does not reduce payments to the genuinely disabled and the most needy, it is generally regarded as a good idea. It should cut fraud and administrative costs. 

It’s a pity though that no central department can be open about the progress of its major  IT-related projects; and on forcing these progress reports out of dark departmental corners the coalition has made no difference at all.

Will GDS delay Universal Credit by a year? – David Moss’s blog

A Secretary of State talks about agile

By Tony Collins

Iain Duncan Smith, the Secretary of State for Work and Pensions, told MPs about agile at a hearing of the Work and Pensions Committee this week on Univeral Credit.

He told the Committee:

“The thing about the agile process which I find frustrating at times, because we cannot quite get across to people, is that agile is about change. It is about allowing you to get to a certain point in the process, check it out, make sure it works, come up with something you can  rectify, and make it more efficient.

” So you are constantly rolling forward, proving, and making more efficient.”

He was answering concerns that the IT for Universal Credit may not work. Tomorrow the Department for Work and Pensions starts a publicity campaign on Universal Credit. Part of it will focus on how agile enables the UC project to adapt to change.

Agile does work in government – GDS

Agile will fail in Government IT  – corporate lawyer

Agile can fix failed GovIT says lawyer

PR campaign on Universal Credit starts tomorrow (20 September 2012).

DWP starts media campaign on Universal Credit IT tomorrow

By Tony Collins

The Work and Pensions Secretary Iain Duncan Smith has told MPs his department is launching a “major exercise” tomorrow to inform the media about Universal Credit, including progress with the IT project.

The public relations push will include a demonstration to journalists of the Univeral Credit front-end, and an explanation of the ability of “agile” to rectify problems as you go along. Duncan Smith said there is a lot of ignorance in the media, and suppositions, that need tackling head on.

His full statement on the PR campaign is at the foot of this article.

Comment

Iain Duncan Smith’s remarks to MPs sound remarkably like the statements that were made in the early part of the National Programme for IT in the NHS, when DH ministers and senior officials were anxious to correct ignorance and suppositions in the media – and to show journalists the front end of new electronic patient record systems.

Several times journalists were invited to Richmond house in Whitehall, the HQ of the DH, to hear how well the NPfIT was going. So anxious were the minister and leading officials to give a good impression of the programme that, on one occasion, trade journalists who had an insight into the NPfIT’s progress and could ask some awkward questions in front of the general media were barred from attending.

I would like Universal Credit to succeed. In concept it simplifies the excessively complex and costly benefit system. The worrying thing about the scheme, apart from the DWP’s overly sensitive reactions to scepticism in the media, is the way UC seems to be following the path which led to NPfIT’s downfall.

The Secretary of State attacks the media while trying to show UC in a glowing light and at the same time keeps secret all the DWP’s interview reviews and reports on actual progress. Duncan Smith says that the DWP wants to be open on UC but his department is turning down FOI requests.

There is no doubt that Duncan Smith has a conviction that the programme is on course, on budget, and will deliver successfully. But there still a morass of uncertainty for the DWP to contend with, and lessons to be learnt from pilots, some of which could be important enough to require a fundamental re-think. That’s to say nothing of HMRC’s Real-Time Information project which is part of UC.

Duncan Smith says the UC project is not due to be complete until 2017 which gives the DWP ample time to get it right. But ministers and officials in the last administration gave the NPfIT 10 years to complete; and today, nine years later, the scheme is being officially dismantled.

Did NPfIT ministers really know or understand the extent of the project’s true complexities and uncertainties?  Did they fully grasp the limited ability of suppliers to deliver, or the willingness of the NHS to change?  But they were impressed with the patient record front-end system and they organised several Parliamentary events to demonstrate it to MPs.

The NPfIT public relations exercises – which included DH-sponsored DVDs and a board game to market the NPfIT – were all in the end pointless.

Should Duncan Smith be running Universal Credit?

This is another concern. Duncan Smith is much respected and admired in Parliament but he appears too close to UC to be an objective leader. At a hearing of the Work and Pensions this week Duncan Smith took mild criticism of UC as if it were a verbal attack on his child.

It is doubtful anyone working for Duncan Smith would dare give him bad news on UC , though he attends lots of departmental meetings. Doubtless he listens to all those who agree with him, those who are walking press releases on the progress of the UC programme. He’d be a good marketing/PR man on UC. But surely not its leader. Not the one making the most important decisions. For that you would need somebody who’s free from the politics, who is independently minded, and who welcomes informed criticism.

Is there any point in a demo of front-end systems?

Seeing a front-end system means little or nothing. The question is will it work in practice when it is scaled up, when exceptions come to light, and when large numbers of people try to contact the helpdesks because they cannot get to grips with the technology and the interfaces,  or have particular difficulties with their claim.

What will a media campaign achieve?

If the NPfIT experiences are anything to go by, journalists who criticise the UC project will be made to feel stupid or uninformed.

In a totalitarian regime the media could be forced to publish what the government wants people to believe. Will the DWP’s PR campaign be designed to achieve the same end without the slightest attempt at coercion?

Duncan Smith’s comments to MPs

Below is some of what Iain Duncan Smith told Work and Pensions Committee MPs this week. He had been asked by a Committee MP to have a dialogue with the media to ensure that people believe that Universal Credit is a good thing.

Duncan Smith:

“On Thursday we are carrying out a major exercise in informing the median about what we are doing, looking at the system front-end, about budgets and all the elements the committee has been inquiring into.

“We will take them through that, show them that. We are going to open up much more. It is such an important system that I want people to learn what it is all about.  There is a lot of ignorance in the media and suppositions made; things that are important to tackle head on. Everyone says you mustn’t have a big bang; you are not going to be ready in time. The time we deliver this is 2017 when it is complete.  That is over four years…”

Universal Credit – a chance to do things differently.

By Tony Collins

Comment

In his comment on the article “Is Univeral Credit really on track – the DWP hides the facts”  Nik Silver asks in essence: why shouldn’t progress reports by IBM and McKinsey on Universal Credit be kept between the parties and not made public?

He says that criticism is usually helpful if the two parties can speak frankly without external interference.

It’s a reasonable point – if you are judging the public sector by the private sector’s standards. A private company would not make public consultancy reports it has commissioned on the progress or otherwise of a particularly costly project. Why should it?

Private v public sector approaches on big projects

But if the project goes wrong the private sector board will be accountable for the loss of money, or opportunity, or both. A private company’s board cares about a failed project because it cares about the bottom line.  If there is cogent criticism in a consultancy report, it will ignore that criticism at its peril.

Those standards don’t always apply in the public sector. There is no bottom line to worry about, no individual responsibility. What matters is reputation. We have seen too many public sector failed projects where the desire to maintain face, politically and internally, distorts the truth on projects.

Several ministers were proclaiming the £11bn NHS IT plan, the NPfIT, to be a success while it was going disastrously wrong. On the Rural Payment Agency’s IT-based Single Payment Scheme Parliament discovered that bad news was covered up. Ministers Lord Bach and Lord Whitty said they were misled by their officials.

When the truth financially came out it was too late to turn around the project cheaply and easily. The Environment, Food and Rural Affairs Committee said that if such a failure had happened at a major plc, the board would have faced dismissal.

Cover up when a project goes wrong also happens in the private sector. But case studies indicate that when a private sector board finds out it has been lied to, it does its utmost to put things right. The bottom line is the motivation.

In the public sector it sometimes happens that nothing is done to put serious problems right because there is no acceptance there are any serious problems. Nobody is allowed to accept internally that things are going wrong. A state of unreality exists. Some know the project is doomed.  Some at the top think it’s on track. The truth in the consultancy reports remains hidden, even internally. [The DWP couldn’t find the IBM and McKinsey reports when we first asked for them.]

Like Nik Silver, we would like Universal Credit to succeed. We are not sure it will, because the truth is not coming out. Unless serious problems are admitted they cannot be tackled.

Public sector

In the public sector a disaster does not usually become apparent until things are so bad the seriousness of the problems cannot be denied. It may be that Universal Credit will be a success if it is delayed or changed substantially in scope. That won’t be possible without reports such as IBM’s and McKinsey’s being published.  In the meantime Iain Duncan Smith, the Work and Pensions Secretary, will  continue to be given papers showing that all is well.  If the IBM and McKinsey reports are published now, and they contain some serious high-level criticisms, perhaps impinging on policy and excessive complexity, the ills may be cured or at least tackled. If these and other progress reports are made public now the corrigible criticisms could create a political climate to address those ills.

At present Universal Credit looks like so many IT-based change programmes of the past.  One side says the project is becoming a disaster and the other side says all is well.  The truth I am sure is that some things look good and some things bad. The bad probably won’t be addressed unless Parliament, together with all those who have a professional interest in the project – and the public – know about it.

The way of the past is to keep everything hushed up until it’s too late. Now there’s a chance to do things differently.

Is Universal Credit really on track? – The DWP hides the facts.

Nik Silver’s website

Is Universal Credit really on track? The DWP hides the facts.

By Tony Collins

The Department for Work and Pensions has told Campaign4Change that consultancy reports it commissioned on Universal Credit would, if disclosed under FOI, cause “inappropriate concern”.

Who’s to say the concern would be inappropriate?

At the weekend a spokesman for the Department for Work and Pensions told the BBC: “Liam Byrne (Shadow Work and Pensions Secretary) is quite simply wrong. Universal Credit is on track and on budget. To suggest anything else is incorrect.”

But the DWP has decided not to disclose reports by consultants IBM and McKinsey that could throw light on whether the department is telling the truth. Though the reports cost taxpayers nearly £400,000, the public has no right to see them.

The DWP told us: “Disclosure [under FOI] would … give the general public an unbalanced understanding of the [Universal Credit] Programme and potentially undermine policy outcomes, cause inappropriate concern (which in turn would need to be managed) and damage progress to the detriment of the Government’s key welfare reform and the wider UK economy.”

Comment

In refusing to publish the costly reports from IBM and McKinsey the Department for Work and Pensions makes the  assumption that the Universal Credit IT programme will be better off without disclosure. But does the  DWP know what is best for the Universal Credit project?  Is the DWP’s own record on project delivery exemplary? Some possible answers:

–  The DWP has a history of big IT project failures, some of which pre-date the “Operational Strategy” project in the 1980s to computerise benefit systems. MPs were told the Operational Strategy, as it was called, would cost about £70om; it cost at least £2.6bn.  Today, decades later, the DWP still has separate benefit systems and relies on “VME” mainframe software that dates back decades.

– NAO reports regularly criticise the DWP’s management of projects, programmes or  suppliers. One of the latest NAO reports on the DWP was about its poor management of a contract with Atos , which does fit-to-work medical assessments.

– The DWP hasn’t broken with tradition on the awarding of megadeals to the same familiar names. Though Universal Credit is said to be based, in part, on agile principles, Accenture and IBM are largely in control of the scheme and the department continues to award big contracts to a small number of large companies. HP, Accenture, IBM and Capgemini are safe in the DWP’s hands.

–  The NAO has qualified the accounts of the DWP for 23 years in a row because of “material” levels of fraud and error.

So is the DWP in an authoritative position to say that the taxpayer and the Universal Credit IT project are better off without disclosure of consultancy reports when the DWP has never done it differently; in other words it has never disclosed its consultancy reports?

Can we trust what DWP says?

Without those reports being put in the public domain can we trust what the DWP says on the success so far of the Universal Credit programme?

Unfortunately departments cannot always be trusted to tell the truth to the media, or Parliament, on the state of major projects.

In 2006 the then health minister Liam Byrne praised the progress of the NHS National Programme for IT, NPfIT. He told the House of Commons that the NPfIT had delivered new systems to thousands of locations in the NHS. “Progress is within budget, ahead of schedule in some areas and, in the context of a 10-year programme, broadly on track in others.”

That was incorrect. But it was what the Department of Health wanted to tell Parliament.

Now it is the DWP that is praising Universal Credit and it is Liam Byrne criticising the programme. This time Byrne may have a point. The problem is we don’t know; the DWP may or may not be telling the truth – even to its Work and Pensions Secretary Iain Duncan Smith.

It would not be the first time ministers were kept in the dark about the real state of big IT projects: ministers were among the last to know when the Rural Payment Agency’s Single Payment Scheme went awry.

And while the NPfIT was going disastrously wrong, progress on the programme was being praised by ministers who included Caroline Flint, Lord Hunt, Lord Warner, John Reid, Andy Burnham, Ivan Lewis and several others. Even a current minister, Simon Burns, gave Parliament a positive story on the NPfIT while the programme was dying.

So while DWP spokespeople and Iain Duncan Smith praise the Universal Credit IT programme can anyone trust what they say? Though Duncan Smith sits on an important DWP steering group on Universal Credit, does he know enough to know whether he is telling the truth when he says the programme is on track and on budget?

At arm’s length to ministers, officialdom owns and controls the facts on the state of all of the government’s biggest projects – and the facts on Universal Credit’s IT programme will continue to stay in locked cupboards unless the Information Commissioner rules otherwise, and even then the DWP will doubtless put up a fight against disclosure.

The IBM and McKinsey reports were so well hidden by the DWP that, for a time, it didn’t know it had them.

The DWP gave the reasons below for rejecting our appeal against the decision not to publish. The DWP’s arguments against publishing the reports on Universal Credit are the same ones that, hundreds of years ago, were used to ban the publication of Parliamentary proceedings: that reporting would affect the candour of what needed to be said. That proved to be nonsense.

By hiding the reports the DWP gives the impression it doesn’t want the truth about Universal Credit to come out – leaving the department and Iain Duncan Smith free to continue saying that the scheme is on track. Indeed Duncan Smith said yesterday that he “has nothing to hide here”. That is evidently not true.

The reports we’d requested were:

– Universal Credit end-to-end technical review” (IBM – cost £49240).
– Universal Credit delivery model assessment phases one and two. ( McKinsey and Partners – cost £350,000).

DWP’s letter to us:

7 September 2012
Dear Mr Collins,

…You asked for a copy of the Universal Credit Delivery Model Assessment Phase 1 and 2, and the Universal Credit End to End Technical Review.

I am writing to advise you that the Department has decided not to disclose the information you requested.

The department has conducted an internal review and the information you requested is being withheld as it falls under the exemptions at section 35(1)(a) and (formulation of Government policy) and Section 36 (2) (b) and (c) (prejudice to the effective conduct of public affairs) of the Freedom of Information Act. These exemptions require the public interest for and against disclosure to be balanced.

These reports from external consultants discuss the merits or drawbacks of the UC delivery model and an assessment of whether the IT architecture is fit for purpose. This must be candid otherwise; the Department and the taxpayer will not secure value for money. Such reports can therefore be negative by nature in their outlook.

The Department considers that premature disclosure of these reports could lead to future consultants’ reports being less frank. In addition, there is a risk that this may lead to an absence of a recorded audit trail of the more candid elements. This is not in the public interest. Similarly, key staff selected to be interviewed by consultants are likely to be inhibited if they think their candour is likely to be recorded and released.

It is vital that the Department’s ability effectively to identify, assess and manage its key risks to delivery is not compromised. The willingness of senior managers to fully engage in a timely manner and support consultants assessment and assurance of key IT projects in an unrestrained, frank and candid way is vital to the effectiveness of the process.

Disclosure would also give the general public an unbalanced understanding of the Programme and potentially undermine policy outcomes, cause inappropriate concern (which in turn would need to be managed) and damage progress to the detriment of the Government’s key welfare reform and the wider UK economy.

While we recognise that the publication of the information requested could provide an independent assessment of the key issues and risks, we have to balance this against the fact that these reports includes details of ongoing policy formulation and sensitive information the publication of which would be likely to prejudice the effective conduct of public affairs.

The Department periodically publishes information about the introduction of Universal Credit, and this can be found on the Departments website here http://www.dwp.gov.uk/policy/welfare-reform/universal-credit/

Yours sincerely
Ethna Harnett

We have appealed the DWP’s refusal so the matter is now before the Information Commissioner’s Office.

Universal  Credit programme on course for disaster – Frank Field

Has the DWP lost £400,000 of reports it commissioned on Universal Credit?

Millions of pounds of secret DWP reports

NAO criticises Atos benefits contract

DWP scraps £141m IT project three months after assurance to MPs

Timetable for HMRC’s work on Universal Credit is “challenging” says NAO

By Tony Collins

Today’s report of the National Audit Office on the accounts of HMRC is, perhaps diplomatically, silent on the performance of HMRC’s work so far on Universal Credit, other than to say the timetable for roll-out beginning in October next year is “challenging”.

There have been internal assessments of HMRC’s “Real Time Information” [RTI] project, on which the success of Universal Credit is dependent, but none has been published other than the “Starting Gate”.

Today’s NAO report on HMRC says the “timetable for implementation of RTI is challenging”. It adds:

“The Department for Work and Pension’s timetable to implement Universal Credit is driving the timetable to roll-out RTI. The Department for Work and Pensions requires real time PAYE information on employment and pension income to award and adjust Universal Credit.

“It is rolling out Universal Credit from October 2013 to 2017. All employers and pension providers need to be using RTI by October 2013 to meet this timetable.

“The Department met its milestone to start its RTI pilot in April 2012 with ten employers. By July 2012, it expects a further 310 employers will be using RTI. At 31 May 2012, 209 PAYE schemes covering 1.5 million individual records were using RTI.”

NAO report on HMRC’s 2011/12 accounts

HMRC still plagued by IT problems.

Time for truth on Universal Credit

How CIOs and IT suppliers view GovIT change

By Tony Collins

CIOs and IT suppliers give their views on Government ICT in an authoritative report published today by the Institute for Government

Inside the wrapper of generally positive words, a report published today on government ICT by the Institute for Government suggests that major change is unlikely to happen, despite the best efforts of  CIOs and the Cabinet Office minister Francis Maude.

The report “System upgrade? The first year of the Government’s ICT strategy”  says progress has been made. But its messages suggest that reforms are unlikely to  amount to more than tweaks.

These are some of the key messages in the report:

If the minister and CIOs cannot direct change who can?

–          “… while the Minister for the Cabinet Office and government CIO are viewed as being responsible for delivering the ICT strategy (for example by the Public Accounts Committee) they currently lack the full authority to direct change.”

Not so agile

–           “While just over half of government departments may be running an agile project, there were concerns that these were often very minor projects running on the fringe of the departments.”

–          “We heard concerns from the supplier community and those inside government that in some areas projects may be being labelled as ‘agile’ without having really changed the way in which they were run.”

–          “CIOs should question whether they are genuinely improving the ways that they are working in areas such as agile, or whether they are just attaching a label to projects to get a tick in the box,” says the Institute for Government.

Savings not real?

–          “There was also an element of challenge to the savings figures provided by government. For example, some from government and the supplier community questioned whether the numbers represented genuine savings or just cuts in the services provided or deferred expenditure. “

–          “Others … cautioned that project scope creep or change requests could reduce actual savings in time. It was pointed out that the NAO [National Audit Office] will scrutinise whether savings have been achieved in future, which was seen as a clear incentive for accuracy – but there were, nonetheless, concerns that pressure to provide large savings figures meant that inadequate attention might be paid to verifying the savings …”

CIOs want faster ICT progress

–          “Among the CIOs we interviewed, there was a clear recognition that government ICT needed to improve.  ‘You expect an Amazon experience from a government department…’ ”

Lack of money good for change

–          “As one ICT lead noted, a lack of money was ‘always helpful’ in driving change as it promoted cross-government solution-sharing and led to more rigour in approving new spend.”

–          “Both ICT leaders and suppliers felt that the ICT moratorium had been a helpful stimulus for increased focus on value for money.”

–          “Though some of the larger suppliers felt bruised by the ‘smash and grab’ of initial interactions with the Coalition government, there was a recognition that the moratorium had been about ‘stopping things which were inappropriate’”.

GDS challenges norms

–          “New ways of working in the new Government Digital Service and the opening up of government through the Transparency agenda were also seen as providing a challenge to existing norms.”

–          The new Government Digital Service (GDS) is providing an example of a new way of doing things, and was pointed to by those inside and outside of government as embodying mould-breaking attitudes, using innovative techniques and … delivering results on very short timescales. Several interviews mentioned being invigorated by the positive approach of the GDS and their focus on delivering services to meet end-user needs.

ICT so poor staff circumvent it

–          “Public servants are increasingly frustrated that the ICT they use in their private lives appears to be far more advanced than the tools available to them at work. Indeed, there are already examples of employees circumventing the ICT that government provides them as they attempt to perform their job more effectively: creating what is known as a system of ‘shadow ICT’ that creates significant challenges for maintaining government security, collaborative working and government knowledge management.”

Joined-up Govt impossible?

–          “The possibility that departmental incentives continue to trump corporate contributions is further suggested by our survey results. Individuals do not yet feel that corporate contributions are valued or rewarded … elements of the [ICT] strategy call for departments to give up an element of autonomy and choice for the ‘greater good’. Several CIOs expressed concerns that by adopting elements of the strategy that were being developed or delivered by another department, they would end up having to accept a service that had been designed  around the needs of a different department.”

–          “Similarly, there were concerns that the host department would be at the top priority in the event of any problems or opportunities to develop services further. This speaks to a strongly department-centric culture. Suppliers noted, for example, that certain parts of government were still happy to ‘pay a premium for their autonomy’.”

–          “… the vast majority of those we spoke to suggested that departmental interests would almost always ultimately trump cross-government interests in the current government culture and context.”

–          “CIOs felt that they would be rewarded for delivery of departmental priorities – not pan-government work …”

CIO Council frustrations

“CIOs noted that there could be a discrepancy between what got agreed at the old CIO Council meetings and what people actually went away and did. Larger department CIOs also expressed frustration that – despite holding the largest budgets and carrying the largest delivery risks – their voices could easily be outweighed by the multitude of other people round the table.”

“The delivery board model [which has superseded CIO Council] has been recognised by both big and small departments as pragmatically dealing with both sides of this issue. Larger departments now form part of an inner-leadership circle, but with this recognition of their clout comes additional responsibility to own and drive through parts of the strategy… the challenge will now be to ensure that the ICT strategy doesn’t become a ‘large department-only’ affair and that other ICT leads can be effectively engaged.”

Canny suppliers?

–          The majority of ICT leads …stated that they believed the ICT strategy would benefit their department and government as a whole. This confidence was less apparent in the attitudes of suppliers who were, on the whole, more sceptical of government’s ability to drive change, though again generally supportive of the direction of travel.

A toothless ICT Strategy is of little value?

–          “…There was also a lack of clarity on how different elements of the [ICT] strategy would be enforced. As one ICT leader commented … ‘Is this a mandatable strategy or a reference document?’ ”

–          … “there are risks that the strategy could be delivered in a way that still doesn’t transform ICT performance.”

Francis Maude an asset

–          “Government ICT has also been a priority of the Minister for the Cabinet Office, Francis Maude – giving the [change] agenda unprecedented ministerial impetus. He has been a visible face of ICT to many inside and outside of government, from demanding departmental data on ICT to being heavily involved in negotiations with ICT suppliers. Though few of his ministerial colleagues appear as passionate about improving government ICT, the CIOs we interviewed overwhelmingly expressed confidence that they would receive the support they needed to implement the changes in ICT.”

Smaller-budget CIOs out of the loop?

–          “With the CIO Council in hiatus for most of the last year, the CIOs of smaller departments felt out of the loop …”

Most ICT spending is outside SW1

–          “Suppliers and other ICT leaders pointed out, rightly, that the vast majority of ICT expenditure happens outside SW1 – with agencies, local government and organisations like primary care trusts and police forces still determining much of the citizen and workforce experience of ICT.”

SMEs still left out?

–          “Smaller suppliers … were generally encouraged that government was trying to use more contractual vehicles which would be open to them – but noted that it was ‘still extremely difficult to get close to government as an SME’.”

Who knows if use of ICT is improving?

–          “Government still lacks the information it needs to judge whether use of ICT across government is improving.”

System upgrade? The first year of the Government’s ICT Strategy.

Too early to claim success on GovIT – Institute for Government