Firecontrol disaster and NPfIT – two of a kind?

By Tony Collins

Today’s report of the Public Account Committee on the Firecontrol project could, in many ways, be a report on the consequences of the failure of the National Programme for IT in the NHS in a few years time.

The Firecontrol project was built along similar lines to the NPfIT but on a smaller scale.

With Firecontrol, Whitehall officials wanted to persuade England’s semi-autonomous 46 local fire authorities to take a centrally-bought  IT system while simplifying and unifying their local working practices to adapt to the new technology.

NPfIT followed the same principle on a bigger scale: Whitehall officials wanted to persuade thousands of semi-autonomous NHS organisations to adopt centrally-bought technologies. But persuasion didn’t work, in either the fire services or the NHS.

More similarities

The Department for Communities and Local Government told
the PAC that the Firecontrol control was “over-specified” – that it was unnecessary to have back-up to an incident from a fire authority from the other side of the country.

Many in the NHS said that NPfIT was over-specified. The gold-plated trimmings, and elaborate attempts at standardisation,  made the patient record systems unnecessarily complicated and costly – and too difficult to deliver in practice.

As with the NPfIT, the Firecontrol system was delayed and local staff  had little or no confidence it would ever work, just as the NHS had little or no faith that NPfIT systems would ever work.

Both projects failed. Firecontrol wasted at least £482m. The Department of Communities and Local Government cancelled it in 2010. The Department of Health announced in 2011 that the NPfIT was being dismantled but the contracts with CSC and BT could not be cancelled and the programme is dragging on.

Now the NHS is buying its own local systems that may or may not be interoperable. [Particularly for the long-term sick, especially those who have to go to different specialist centres, it’s important that full and up-to-date medical records go wherever the patients are treated and don’t at the moment, which increases the risks of mistakes.]

Today’s Firecontrol report expresses concern about a new – local – approach to fire services IT. Will the local fire authorities now end up with a multitude of risky local systems, some of which don’t work properly, and are all incompatible, in other words don’t talk to each other?

This may be exactly the concern of a post-2015 government about NHS IT. With the NPfIT slowly dying NHS trusts are buying their own systems. The coalition wants them to interoperate, but will they?  

Could a post-2015 government introduce a new (and probably disastrous) national NHS IT project – son of NPfIT – and justify it by drawing attention to how very different it is to the original NPfIT eg that this time the programme has the buy-in of clinicians?

The warning signs are there, in the PAC’s report on Firecontrol. The report says there are delays on some local IT projects being implemented in fire authorities, and the systems may not be interoperable. The PAC has 

” serious concerns that there are insufficient skills across all fire authorities to ensure that 22 separate local projects can be procured and delivered efficiently in so far as they involve new IT systems”.

National to local – but one extreme to the other?

The PAC report continues

“There are risks to value for money from multiple local projects. Each of the 22 local projects is now procuring the services and systems they need separately.

“Local teams need to have the right skills to get good deals from suppliers and to monitor contracts effectively. We were sceptical that all the teams had the appropriate procurement and IT skills to secure good value for money.

“National support and coordination can help ensure systems are compatible and fire and rescue authorities learn from each other, but the Department has largely devolved these roles to the individual fire and rescue authorities.

“There is a risk that the Department has swung from an overly prescriptive national approach to one that provides insufficient national oversight and coordination and fails to meet national needs or achieve economies of scale. 

Comment

PAC reports are meant to be critical but perhaps the report on Firecontrol could have been a little more positive about the new local approach that has the overwhelming support of the individual fire and rescue authorities.  

Indeed the PAC quotes fire service officials as saying that the local approach is “producing more capability than was expected from the original FiReControl project”. And at a fraction of the cost of Firecontrol.

But the PAC’s Firecontrol Update Report expresses concern that

– projected savings from the local approach are now less than originally predicted

– seven of the 22 projects are running late and two of these projects have slipped by 12 months

– “We have repeatedly seen failures in project management and are concerned that the skills needed for IT procurement may not be present within the individual fire and rescue authorities, some of which have small management teams,” says the PAC.

On the other hand …

The shortfall in projected savings is small – £124m against £126m and all the local programmes are expected to be delivered by March 2015, only three months later than originally planned.

And, as the PAC says, the Department for Communities and Local Government has told MPs that a central peer review team is in place to help share good practice – mainly made up of members of fire and rescue authorities themselves.

In addition, part of the £82m of grant funding to local fire services has been used by some authorities to buy in procurement expertise.

Whether it is absolutely necessary – and worth the expense – for IT in fire services to link up is open to question, perhaps only necessary in a national emergency.

In the NHS it is absolutely necessary for the medical records of the chronically sick to link up – but that does not justify a son-of-NPfIT programme. Linking can be done cheaply by using existing records and having, say, regional servers pull together records from individual hospitals and other sites.

Perhaps the key lesson from the Firecontrol and the NPfIT projects is that large private companies can force their staff to use unified IT systems whereas Whitehall cannot force semi-autonomous public sector organisations to use whatever IT is bought centrally.

It’s right that the fire services are buying local IT and it’s right that the NHS is now too. If the will is there to do it cheaply, linking up the IT in the NHS can be done without huge central administrative edifices.

Lessons from FireControl (and NPfIT?) 

The National Audit Office identifies these main lessons from the failure of Firecontrol:

– Imposing a single national approach on locally accountable fire and rescue authorities that were reluctant to change how they operated

–  Launching the programme too quickly without applying basic project approval checks and balances

– Over optimism on the deliverability of the IT solution.

– Issues with project management including consultants who made up half of the management team and were not effectively managed

MP Margaret Hodge, chair of the Public Accounts Committee, today sums up the state of Firecontrol

“The original FiReControl project was one of the worst cases of project failure we have seen and wasted at least £482 million of taxpayers’ money.

“Three years after the project was cancelled, the DCLG still hasn’t decided what it is going to do with many of the specially designed, high-specification facilities and buildings which had been built. Four of the nine regional control centres are still empty and look likely to remain so.

“The Department has now provided fire and rescue authorities with an additional £82 million to implement a new approach based on 22 separate and locally-led projects.

“The new programme has already slipped by three months and projected savings are now less than originally predicted. Seven of the 22 projects are reportedly running late and two have been delayed by 12 months. We are therefore sceptical that projected savings, benefits and timescales will be achieved.

“Relying on multiple local projects risks value for money. We are not confident that local teams have the right IT and procurement skills to get good deals from suppliers and to monitor contracts effectively.

“There is a risk that the DCLG has swung from an overly prescriptive national approach to one that does not provide enough national oversight and coordination and fails to meet national needs or achieve economies of scale.

 “We want the Department to explain to us how individual fire and rescue authorities with varied degrees of local engagement and collaboration can provide the needed level of interoperability and resilience.

“Devolving decision-making and delivery to local bodies does not remove the duty on the Department to account for value for money. It needs to ensure that national objectives, such as the collaboration needed between fire authorities to deal with national disasters and challenges, are achieved.”

Why weren’t NPfIT projects cancelled?

 NPfIT contracts included commitments that the Department of Health and the NHS allegedly did not keep, which weakened their legal position; and some DH officials did not really want to cancel the NPfIT contracts (indeed senior officials at NHS England seem to be trying to keep NPfIT projects alive through the Health and Social Care Information Centre which is responsible for the local service provider contracts with BT and CSC).

PAC report on Firecontrol

What Firecontrol and the NPfIT have in common (2011)

BT gets termination notice on £300m outsourcing contract

By Tony Collins

Sandwell Council has issued BT with a 30-day termination notice on a 15-year £300m outsourcing contract that has yet to reach its half-way point.

The metropolitan borough council says there are various defaults BT needs to resolve. Based at Oldbury, West Midlands, about five miles from Birmingham, Sandwell has been an outsourcing reference site for BT.

The company quoted Sandwell Council in its presentations that formed part of the bidding for Cornwall Council’s planned outsourcing work.

The “guaranteed” savings in Sandwell’s contract with BT appear to be based on a level of spending the council is not maintaining. One point of contention appears to be the council’s wish for BT to reduce its charges to the council in line with the authority’s lower levels of activity.

In June 2012 Sandwell submitted a change request that asked BT to recalculate the annual service charge because the service volumes delivered through the contract had reduced significantly.

The council wanted the recalculation to be based on a reduction in the workforce from around 7,400 in 2007 when the contract with BT was signed to 4,688 in mid 2012.

Government Computing quotes a council document on the dispute as saying

“A reduction in the workforce should have a corresponding reduction in volumes such as the size of the ICT estate, the payroll, HR support and budget holders. There have been volume reductions in invoices, the number of contracts administered and calls to the contact centre for some services.”

Sandwell’s 30-day termination notice to BT was issued on 16 July so it will expire around that time next month. The council says it is prepared to take back staff.

Sandwell council leader, Councillor Darren Cooper, told Government Computing: “Cabinet has approved a recommendation to start the process of ending our contract with BT. That termination will take effect in 30 days’ time unless BT puts right various defaults we have asked them to resolve.

“If we have to, I am confident we will be able to bring the services BT currently supplies to us back to the council and run them in the most effective way in future.”

Guaranteed

In 2007 BT and its joint bidder, outsourcing provider Liberata, had set out to run the council’s back-office functions at what was announced as a “guaranteed” reduced cost over the lifetime of the contract.

The deal was aimed at cutting costs and improving Sandwell’s IT infrastructure, HR, finance, payroll and customer services functions.

There was some success. The BT-led ‘Transform Sandwell’ team won the UK’s Best Customer Services Management Team at the National Customer Services Awards in December 2010.

BT built a 75,000 square foot office block for Transform Sandwell. It accommodated 400 employees of Transform Sandwell and a 300-strong customer service team working for BT.

Massive mistake?

Independent socialist councillor Mick Davies said “Someone somewhere has obviously made a massive mistake and the taxpayers of Sandwell will have to foot the bill… The writing seemed to be on the wall when BT’s partner in the project, Liberata, was dumped unceremoniously a couple of years ago.”

Sandwell Council’s deputy leader and cabinet member for strategic resources Councillor Steve Eling said: “In view of the current climate and public expenditure reductions, the council is engaging with its partner to determine services that are needed over the medium term and to reduce the overall costs in light of public spending reductions.”

Technologies used in the Transform Sandwell contact centre have included Verint Impact 360, Siebel CRM and Nortel Contact Centre 6.0.

A BT spokesman told the Halesowen News

“BT continually looks at ways to improve the service it provides to its customers. The original contract was signed in 2007 and as is normal with long-term partnerships BT constantly looks at ways to service the changing needs of both the council and citizens of Sandwell.”

BT told Government Computing it “has throughout – and remains – fully committed to delivering the commitments it made through the Transform Sandwell Partnership.”

The European Services Strategy Unit which has carried out detailed research on outsourcing contracts lists some of the terminated and reduced local authority strategic partnership contracts.

Sandwell has 72 councillors, 67 of which represent Labour.

Comment

At some point in a 10 or 15-year outsourcing contract a major dispute seems almost inevitable because a supplier’s business objectives will rarely change when the council’s priorities change.

BT’s deal with Sandwell was signed in 2007 – as was Southwest One’s deal with IBM – at a pre-austerity period.

Now that councils have been making, and continue to make, radical savings, they want the flexibility to cut their outsourcing costs too. But it may not be in the supplier’s interests to take profits that are much lower than expected.

No such thing as a free lunch

How can the business interests of outsourcing providers and their council clients ever completely align and move in time like synchronised swimmers?

The growing number of disputes in local authority outsourcing deals suggests that councils are not properly weighing up the risks when they sign deals.

Perhaps small groups of ruling councillors – such as those at Barnet – are too easily persuaded by the “guaranteed” savings on offer at the start of a contract.

There is no such thing as a free lunch. But try telling that to council Cabinet councillors who have cartoon-character pound signs in their eyes in the Disney period before a big outsourcing contract is well underway.

Let’s hope BT and Sandwell kiss and make up. It looks like the lawyers are already in the middle of them, though; and at whose expense?

Sandwell and BT consider end of strategic partnership – Government Computing

Universal Credit – good for its IT suppliers?

By Tony Collins

The DWP is conceding in its own tangential way that the IT for Universal Credit is not up to scratch; and an article in the Daily Telegraph suggests that Universal Credit this year (and perhaps well beyond) will handle so few claimants that the calculations for the time being could be done by hand, or on a spreadsheet, and not automatically by IT systems. The Register, through anonymous sources, has confirmation of this.

The FT says there will be a progressive national rollout of the coalition’s welfare reform in just six additional jobcentres which it said was the “latest sign the project is falling behind schedule”. It added that a significant shake-up of the IT underpinning universal credit is under way. 

The DWP said David Pitchford, the Whitehall troubleshooter who took over the running of Universal Credit for three months, had been asked to “review” the IT and ministers had “accepted his recommendation that they should explore enhancing the IT for universal credit working with the government digital service”.

“Advancements in technology since the current system was developed have meant that a more responsive system that is more flexible and secure could potentially be built,” said the DWP.

The FT quoted Howard Shiplee, who has led the Universal Credit  project since May, as denying claims from MPs that the original IT had been dumped because it had not delivered. “The existing systems that we have are working, and working effectively,” he said.

He added that he had set aside 100 days not to stop the programme, but to reflect on where it has got to and start to look at the entire total plan.

Iain Duncan Smith, the work and pensions secretary, doesn’t concede that the  timetable for the implementation of Universal Credit has changed. He told the work and pensions committee on Wednesday that numbers of claimants would ramp up during 2014 and he insisted that all claimants would be on the system by 2017, as originally planned.

“We get fixated on things like IT; the reality is it’s about a cultural shift,” Duncan Smith told MPs.

Comment

Iain Duncan Smith makes it clear that his DWP staff and suppliers, with the help of HMRC, are implementing Universal Credit with extreme care. Labour’s  work and pensions spokesman Liam Byrne says the Universal Credit project is a shambles. The truth is hard to fathom.

For years the DWP has rejected press reports that the IT for Universal Credit was in trouble. It is able to do without fear of authoritative contradiction because it keeps secret all its consultancy reports on the state of the Universal Credit project, despite FOI requests.

The Cabinet Office minister Francis Maude and his officials talk much about the need for openness and transparency. Isn’t it time they persuaded DWP officials to release their internal and external reports on the detailed challenges faced by suppliers and civil servants on Universal Credit and other major government IT projects?

All big government IT projects are characterised by secrecy and defensiveness, although a little information about them is in the vague and subjectively-worded Major Projects Authority annual report.

One by-product of departmental defensiveness and secrecy is that the IT suppliers – in Universal Credit’s case HP, IBM and Accenture – are likely to continue to be paid even if the project is halted and redesigned. It’s probable the suppliers would argue that they have successfully done what they were asked to do in the contract. Who knows what the truth is?

The DWP is in effect protecting its suppliers from public and parliamentary scrutiny. It has been this way for decades and nothing has changed.

How to cost-justify the NPfIT disaster – forecast benefits a decade away

By Tony Collins

To Jeremy Hunt, the Health Secretary, the NPfIT was a failure. In an interview with the FT, reported on 2 June 2013, Hunt said of the NPfIT

“It was a huge disaster . . . It was a project that was so huge in its conception but it got more and more specified and over-specified and in the end became impossible to deliver … But we musn’t let that blind us to the opportunities of technology and I think one of my jobs as health secretary is to say, look, we must learn from that and move on but we must not be scared of technology as a result.”

Now Hunt has a different approach.  “I’m not signing any big contracts from behind [my] desk; I am encouraging hospitals and clinical commissioning groups and GP practices to make their own investments in technology at the grassroots level.”

Hunt’s indictment of the NPfIT has never been accepted by some senior officials at the DH, particularly the outgoing chief executive of the NHS Sir David Nicholson. Indeed the DH is now making strenuous attempts to cost justify the NPfIT, in part by forecasting benefits for aspects of the programme to 2024.

The DH has not published its statement which attempts to cost justify the NPfIT. But the National Audit Office yesterday published its analysis of the unpublished DH statement. The NAO’s analysis “Review of the final benefits statement for programmes previously managed under the National Programme for IT in the NHS” is written for the Public Accounts Committee which meets next week to question officials on the NPfIT. 

A 22 year programme?

When Tony Blair gave the NPfIT a provisional go-ahead at a meeting in Downing Street in 2002, the programme was due to last less than three years. It was due to finish by the time of the general election of 2005. Now the NPfIT  turns out to be a programme lasting up to 22 years.

Yesterday’s NAO report says the end-of-life of the North, Midlands and East of England part of the NPfIT is 2024. Says the NAO

“There is, however, very considerable uncertainty around whether the forecast benefits will be realised, not least because the end-of-life dates for the various systems extend many years into the future, to 2024 in the case of the North, Midlands and East Programme for IT.”

The DH puts the benefits of the NPfIT at £3.7bn to March 2012 – against costs of £7.3bn to March 2012.

Never mind: the DH has estimated the forecast benefits to the end-of-life of the systems at £10.7bn. This is against forecast costs of £9.8bn to the end-of-life of the systems.

The forecast end-of-life dates are between 2016 and 2024. The estimated costs of the NPfIT do not include any settlement with Fujitsu over its £700m claim against NHS Connecting for Health. The forecast costs (and potential benefits) also exclude the patient administration system Lorenzo because of uncertainties over the CSC contract.

The NAO’s auditors raise their eyebrows at forecasting of benefits so far into the future. Says the NAO report

“It is clear there is very considerable uncertainty around the benefits figures reported in the benefits statement. This arises largely because most of the benefits relate to future periods and have not yet been realised. Overall £7bn (65 per cent) of the total estimated benefits are forecast to arise after March 2012, and the proportion varies considerably across the individual programmes depending on their maturity.

“For three programmes, nearly all (98 per cent) of the total estimated benefits were still to be realised at March 2012, and for a fourth programme 86 per cent of benefits remained to be realised.

There are considerable potential risks to the realisation of future benefits, for example systems may not be deployed as planned, meaning that benefits may be realised later than expected or may not be realised at all…”

NPfIT is not dead

The report also reveals that the DH considers the NPfIT to be far from dead. Says the NAO

“From April 2013, the Department [of Health] appointed a full-time senior responsible owner accountable for the delivery of the [the NPfIT] local service provider contracts for care records systems in London, the South and the North, Midlands and East, and for planning and managing the major change programme that will result from these contracts ending.

“The senior responsible owner is supported by a local service provider programme director in the Health and Social Care Information Centre.

“In addition, from April 2013, chief executives of NHS trusts and NHS foundation trusts became responsible for the realisation and reporting of benefits on the ground. They will also be responsible for developing local business cases for the procurement of replacement systems ready for when the local service provider contracts end.”

The NAO has allowed the DH to include as a benefit of the NPfIT parts of the programme that were not included in the original programme such as PACS x-ray systems.

Officials have also assumed as a benefit quicker diagnosis from the Summary Care Record and text reminders using NHSmail which the DH says reduces the number of people who did not attend their appointment by between 30 and 50 per cent.

Comment

One of the most remarkable things about the NPfIT is the way benefits have always been – and still are – referred to in the future tense. Since the NPfIT was announced in 2002, numerous ministerial statements, DH press releases and conference announcements have all referred to what will happen with the NPfIT.

Back in June 2002, the document that launched the NPfIT, Delivering 21st Century IT for the NHS, said:

“We will quickly develop the infrastructure …”

“In 2002/03 we will seek to accelerate the pace of development …

“Phase 1 – April 2003 to December 2005 …Full National Health Record Service implemented, and accessible nationally for out of hours reference.”

In terms of the language used little has changed. Yesterday’s NAO report is evidence that the DH is still saying that the bulk of the benefits will come in future.

Next week (12 June) NHS chief Sir David Nicholson is due to appear before the Public Accounts Committee to answer questions on the NPfIT. One thing is not in doubt: he will not concede that the programme has been a failure.

Neither will he concede that a fraction of the £7.3bn spent on the programme up to March 2012 would have been needed to join up existing health records for the untold benefit of patients, especially those with complex and long-term conditions.

Isn’t it time MPs called the DH to account for living in cloud cuckoo land? Perhaps those at the DH who are still predicting the benefits of the NPfIT into the distant future should be named.

They might just as well have predicted, with no less credibility, that in 2022 the bulk of the NPfIT’s benefits would be delivered by the Flower Fairies.

It is a nonsense that the DH is permitted to waste time on this latest cost justification of the NPfIT. Indeed it is a continued waste of money for chief executives of NHS trusts and NHS foundation trusts to have been made responsible, as of April 2013, for reporting the benefits of the NPfIT.

Jeremy Hunt sums up the NPfIT when he says it has been a huge disaster. It is the UK’s biggest-ever IT disaster. Why does officialdom not accept this?

Instead of wasting more money on delving into the haystack for benefits of the NPfIT, it would be more sensible to allocate money and people to spreading the word within Whitehall and to the wider public sector on the losses of the NPfIT and the lessons that must be learnt to discourage any future administrations from embarking on a multi-billion pound folly.

Francis Maude boasts of £10bn savings but …

By Tony Collins 

This morning Cabinet Office minister Francis Maude held a press conference with his senior officials to announce that civil servants have radically changed the way they work to save £10bn in 2012/13.

The savings are nearly £2bn higher than originally planned and, according to the Cabinet Office, have been “reviewed and verified” by independent auditors.

With a little journalistic licence Maude says: “…we are on the way to managing our finances like the best-run FTSE100 businesses.”

The breakdown of the £10bn savings:

Procurement   £3.8bn
Centralisation of procurement for common goods and services  £1.0bn
Centrally renegotiating large government contracts  £0.8bn
Limiting expenditure on marketing and advertising, consultants and temporary agency staff   £1.9bn
Transformation savings   £1.1bn
IT spend controls and moving government services and transactions onto digital platforms  £0.5bn
Optimising the government’s property portfolio  £0.6bn
Project savings   £1.7bn
Reviewing performance of major government projects  £1.2bn
Taking waste out of the construction process  £0.4bn
Workforce savings   £3.4bn
Reducing the size of the Civil Service   £2.2bn
Increasing contributions to public sector pensions   £1.1bn

Comment

It’s good news and the figures don’t seem plucked out of thin air which sometimes happens when central government announces savings.

The big question is whether the savings are sustainable. Maude has inspired the Cabinet Office’s Efficiency and Reform Group to be motivated and hard-working. But bringing about long-term change in Whitehall – as opposed to restricting consultancy contracts and cutting annual costs of supplier contracts by reducing what’s delivered – is like peddling uphill. How long can you do it without losing motivation and energy? It’s not just parts of the civil service that are resistant to the savings agenda – it is also some IT suppliers, according to Government Computing.

It’s likely that only profound changes in central government operations and working practices will outlast the next general election. At the moment the civil service is like a rubber band that has been stretched a little. It wants to return to its standard shape, which the next government may allow it to do.

The National Audit Office said in its report in April 2012 on the Efficiency and Reform Group in 2011/12:

“Savings to date have differing degrees of sustainability.”

The NAO also said this:

“It is not fully clear how ERG intends to make the reforms necessary to secure enough savings over the rest of the spending review. ERG has yet to translate its ambition for saving £20 billion by 2014-15 into more detailed plans.

“ERG has made progress in developing strategies across its wide range of responsibilities, and is focusing on core activities likely to produce savings. However, until recently ERG’s focus has mainly been on the savings themselves, with less emphasis on delivery of the longer-term changes and improvement in efficiency necessary to make them sustainable.”

And this:

“Departments have still tended to lack a clear strategic vision of what they are to do, what they are not, and the most cost-effective way of delivering it. Much of departments’ 2014-15 savings are likely to come from further reductions in staff. Sustainability of these savings will depend on developing skills and working in new ways while maintaining staff motivation and engagement.”

But the NAO was generally positive about the ERG’s contribution to savings.

“ERG’s actions to date, particularly its spending controls, have helped departments deliver substantial spending reductions.”

We hope the Cabinet Office’s diligent efforts continue  – sustainably.

Efficiency and Reform 2012/13 savings. Summary report.

Some suppliers still resistant to change? – Government Computing.

Is Major Projects annual report truly ground-breaking?

By Tony Collins

Francis Maude, the Cabinet Office minister, describes as “nothing short of groundbreaking” a report of the Major Projects Authority which gives the RAG (Rred/Amber/Green) status of more than 100 major projects.

That the report came out late on Friday afternoon as most journalists were preparing to go home, some of them for the whole bank holiday weekend, suggests that the document was a negotiated compromise: it would be published but in such a way as to get minimal publicity.

Indeed the report is a series of compromises. It has the RAG status of projects but not the original text that puts the status into context.

Another compromise: senior civil servants in departments have persuaded Maude to publish the RAG decisions when they are at least six months old.

This enables departmental officials to argue their case in the “narrative” section of the MPA annual report that a red or amber/red decision is out-of-date and that there has been significant improvement since. This is exactly the DWP’s justification for the amber/red status on Universal Credit.

The DWP says in the MPA report: “This rating [amber/red] dates back to September 2012, more than seven months ago. Since then, significant progress has been made in the delivery of Universal Credit. The Pathfinder was successfully launched and we are on course both to expand the Pathfinder in July 2013 and start the progressive national roll-out of Universal Credit in October.”

That the Pathfinder was launched successfully might have nothing to do with Universal Credit’s amber/red status which could be because of uncertainties over how the IT will perform at scale, given the complexities and interdependencies.  The MPA report says nothing about the uncertainties and risks of Universal Credit.

More compromises in the MPA annual report: the Cabinet Office appears to have allowed departments to hide their cost increases on projects such as HMRC’s Real-time Information [RTI] in the vague phrase “Total budgeted whole life costs (including non-government costs).”

The Cabinet Office has also allowed departments to write their own story to accompany the RAG status. So when HMRC writes its story on RTI it says that “costs have increased” but not by how much or why. We know from evidence that HMRC gave to the Public Accounts Committee that RTI costs have risen by “tens of millions of pounds”. There is nothing to indicate this in the MPA annual report.

Another compromise in the MPA annual report: there are no figures to compare the original forecast costs of a project with the projected costs now. There are only the 2012/13 figures compared with whole-life projected costs (including non-government projected spend).

And the MPA report is not comprehensive. It came out on the same day the BBC announced that it was scrapping its Digital Media Initiative which cost the public £98m. The MPA report does not mention the BBC.

The report is more helpful on the G-Cloud initiative, showing how cheap it is – about £500,000. But there is little information on the NHS National Programme for IT [NPfIT] or the Summary Care Record scheme. 

Yet the MPA annual report is ground-breaking. Since Peter Gershon, the then head of the Office of Government Commerce, introduced Gateway reviews of risky IT projects about 12 years ago with RAG decisions, they have remained unpublished, with few exceptions. The Cabinet Office is now publishing the RAG status of major departmental projects for the first time. Maude says

“A tradition of Whitehall secrecy is being overturned. And while previous Governments buried problems under the carpet, we are striving to be more open. By their very nature these works are high risk and innovative.

“They often break new ground and dwarf anything the private sector does in both scale and complexity. They will not always run to plan. Public scrutiny, however uncomfortable, will bring about improvement. Ending the lamentable record of failure to deliver these projects is our priority.”

Comment

The MPA annual report is a breath of fresh air.

Nearly every sentence, nearly every figure, represents compromise. The report reveals that the Universal Credit project was last year given an amber/red status – but it doesn’t say why. Yet the report has the DWP’s defence of the amber/red decision. So the MPA report has the departmental defences of the RAG decisions, without the prosecution evidence. That’s a civil service parody of openness and accountability: Sir Humphrey is allowed to defend himself in public without the case against him being heard.

But it’s still useful to know that Universal Credit is at amber/red.  It implies well into the project’s life that the uncertainties and risks are great. A major project at amber/red at this stage, a few months before go-live, is unlikely to turn green in the short term, if ever.

Congratulations

The Cabinet Office deserves congratulations for winning the fight for publication of the RAG status of each major project. Lord Browne, the government’s lead non-executive director and a member of the Cabinet Office’s Efficiency and Reform group, has said  that billions of pounds of taxpayers’ money is being frittered away because of “worryingly poor” management of government projects.

“Nobody ever stops or intervenes in a poor project soon enough. The temptation is always to ignore or underreport warning signs,” he says.

The management of some large projects – usually not the smaller ones – is so questionable that departments ignore advice to have one senior responsible owner per major project, says the MPA.

The MPA annual report will not stop the disasters. Its information is so limited that it will not even enable the public – armchair auditors – to hold departments to account. Senior civil servants have seen to that.

But the report’s publication is an important development: and it provides evidence of the struggle within Whitehall against openness. Francis Maude and Sir Bob Kerslake, head of the civil service, have had to fight to persuade departmental officials to allow the RAG status of projects to be published. The Guardian’s political editor Patrick Wintour says of the MPA annual report

“Publication led to fierce infighting in Whitehall as government departments disputed the listings and fought to prevent publication.”

Large-scale change

If Maude and Kerslake struggled to get this limited distance, and there is still so much left to reform, will large-scale change ever happen?

Maude and his officials have as comprehensive mandate for change from David Cameron as they could hope for. Yet still the Cabinet Office still seems to have little influence on departments. When it comes to the big decisions, Sir Humphrey and his senior officials hold onto real power. That’s largely because the departments are responsible to Parliament for their financial decisions – not the Cabinet Office.

Maude and his team have won an important battle in publishing the MPA annual report. But the war to bring about major change is still in its very early stages; and there’s a general election in 2015 that could halt Maude’s reform plans altogether.

The Major Projects Authority Annual Report.

Report on status of big Gov’t projects to be published at last

By Tony Collins

The Telegraph reports that the Cabinet Office’s Major Projects Authority is about to publish its first annual report – and it will reveal the status of schemes that include Universal Credit, says the article.

The Cabinet Office said in 2011 that the MPA’s annual report would be published by the end of December that year. In 2012 Sir Bob Kerslake, head of the civil service, told the Public Accounts Committee’s Conservative MP Richard Bacon that the MPA’s annual report would be published in June 2012.

But senior departmental  civil servants have objected repeatedly to the red-amber-green “traffic light” status of projects being published, which contradicts the wishes of Kerslake and Francis Maude, the Cabinet Office minister.

One reason for the delay in publishing the MPA annual report is that Maude and Kerslake have been weighing objections to the reporting of the red-amber-green status against the need for departmental cooperation to implement civil service reforms.

From the Telegraph article it appears that Maude has persuaded (or forced) departmental heads to accept the publication of the traffic light status on big and risky projects. The Major Projects Authority reviews IT and other projects costing more than £50m.

The Telegraph says the MPA annual report will reveal Government troubleshooters’ concerns about multi-billion pound projects like the Universal Credit.

The article says the MPA annual report will show that about a third of projects it has reviewed are late or over budget. Says the Telegraph: “Government sources said that the MPA will show that management of big projects has improved significantly since 2010, when two-thirds of programmes were in trouble.

“But the report, expected later this month, will confirm that Whitehall ‘still has a long way to go’ to improve its handling of major projects, a source said.”

The article adds that publication of the annual report “follows a lengthy internal struggle between ministers and civil servants about the disclosure of problems with big Government schemes”.

Some ministers, says the article, are privately concerned that civil servants are bad at managing big, expensive projects but repeatedly cover up their failings and refuse to tell ministers about problems.  Disclosing “candid” assessments about big projects will improve management, ministers believe.

The Telegraph says that a “new publication scheme that will start later this month” will publicly rate each project at red, amber, or green. 

Each central department will be told to publish details of its major projects every six months, including the red-amber-green ratings and the data behind them, says the article.

The Telegraph quotes as a coalition source as saying: “Releasing a candid report about Whitehall’s major projects is a big and brave step for Government…”

Management of big projects better but still generally poor? 

Lord Browne, a lead non-executive in the Cabinet Office and the man appointed to recruit business leaders to Whitehall departmental boards, has criticised the management of major projects as “worryingly poor”.

He said that insufficient attention was given to identifying risks in the planning stage, and that there had been a “consistent failure” to appoint leaders with the right skills and experience.

Browne said the creation of the Major Projects Authority (MPA) in the Cabinet Office in 2011 had improved their delivery, but “nobody ever intervenes in a poor project soon enough” and that warning signs were often ignored or under-reported.

He called for an “ongoing and rigorous review process with real teeth” which would monitor measures of progress and call “time out” on failing projects, allowing them either to be fixed or stopped.

Browne said the government could learn from the private sector, where projects are scrutinised to a “very high standard” before work begins. In line with this, he suggested that the MPA should have a strengthened “stage-gate approval process” to ensure that projects achieve objectives.

He said that projects should not be allowed to begin until a team with the right skills – including a leader who had previously delivered a large, complex project – had been identified.

He also suggested that the MPA nominate leaders and veto unsuitable candidates. He said that expensive projects should “never be seen as a personal development opportunity”.

He advocated using pay, benefits and bonuses to give team members incentives to work on the project “until appropriate milestones are reached”. This, Browne said, had been key to the success of major projects delivered by the private sector.

Departments still sceptical of Maude’s reforms?

Meanwhile the FT has reported that Maude’s attempts to inject commercial acumen into Whitehall by putting leading business figures on departmental boards is failing to live up to its billing, with some departments rarely consulting their external non-executive directors.

The FT says that the Treasury department’s supervisory board met only once in the year to April 2012, according to a report by Insight Public Affairs, a consultancy. The energy department’s board met twice, compared to 15 meetings in the transport department, reflecting the inconsistent involvement of non-executive directors.

John Lehal, managing director of Insight Public Affairs, said the ad hoc manner in which departments held board meetings reflected the need for greater accountability – as underlined by the Treasury’s failure to engage its non-executives.

Comment

At long last the Major Projects Authority, under the straight-talking Australian David  Pitchford, will publish its annual report; and it may contain more detail on major projects than has been published by any government.

As departments fear public embarrassment more than any other sanction, publication of the traffic light status of projects – with the underlying detail – should genuinely discourage the starting of ill-considered projects.

Although the MPA annual report is much delayed Maude has succeeded in getting agreement for it to be published. Provided it contains enough detail to allow the status of projects to be judged by armchair auditors, it should begin to make a real difference.

Telegraph article

Could HMRC have a major IT success on its hands?

By Tony Collins

It’s much too soon to say that Real-Time Information is a success – but it’s not looking  like another central government IT disaster.

A gradual implementation with months of piloting, and HMRC’s listening to comments from payroll professionals, software companies and employers, seems to have made a difference.

The Cabinet Office’s high-priority attempts to avoid IT disasters, through the Major Projects Authority, seems also to have helped, by making HMRC a little more humble, collegiate and community-minded than in past IT roll-outs. HMRC is also acutely sensitive to the ramifications of an RTI roll-out failure on the reputation of Universal Credit which starts officially in October.

On the GOV.UK website HMRC says that since RTI started on 6 April 2013 about 70,000 PAYE [pay-as-you-earn] returns have been filed by employers or their agents including software and payroll companies.

About 70,000 is a small number so far. HMRC says there are about 1.6 million PAYE schemes, every one of which will include PAYE returns for one or more employees. About 30 million people are on PAYE. Nearly all employers are expected to be on RTI by October 2013.

The good news

 Ruth Owen, HMRC’s Director General Personal Tax, says:

“RTI is the biggest change to PAYE in 70 years and it is great news that so many employers have started to report PAYE in real time. But we are under no illusions – we know that it will take time before every employer in the country is using RTI.

“We appreciate that some employers might be daunted by the change but …we are taking a pragmatic approach which includes no in-year late filing penalties for the first year.”

It hasn’t been a big-bang launch. HMRC has been piloting RTI for a year with thousands of employers. Under RTI, employers and their agents give HMRC real-time PAYE information every time the employee is paid, instead of yearly.

When bedded down the system is expected to cut administrative costs for businesses and make tax codes more accurate, though the transitional RTI costs for some businesses, including training, may be high and payroll firms have had extra costs for changes to their software.

RTI means that employers don’t have to complete annual PAYE returns or send in forms when new employees join or leave.

The bad news

The RTI systems were due to cost £108m but HMRC’s Ruth Owen told the Treasury sub-committee that costs have risen by tens of millions:

“… I can see that it [RTI] is going to cost £138m compared with £108m. I believe that is going to go up again in the scale of tens of millions.”

She said that in October 2012.

Success?

The Daily Telegraph suggested on Monday that RTI may be “ready to implode”.

But problems with RTI so far seem to be mainly procedural and rule-based – or are related to long waits getting queries answered via the helpline – rather than any major faults with the RTI systems.

In general members of the Chartered Institute of Payroll Professionals report successes with their RTI submissions, and some comment on response times being good after initial delays at around the launch date.

Payroll software supplier Sage says the filing of submissions has been successful. There was a shaky start, however, with HMRC’s RTI portal being under maintenance over the weekend.

Jonathan Cowan from the Sage Payroll Team said: “There was understandable confusion and frustration over the weekend with businesses unable to file due to HMRC site issues.”

Accountingweb’s readers have had many problems – it said RTI “stumbled into action –  but few of the difficulties are, it seems, serious. “Have I missed something, but RTI despite all the commotion doesn’t seem that bad,” says an accountant in a blog post on the site.

Payrollworld says RTI problems have been minor. “The launch of Real Time Information (RTI) has encountered a number of minor issues, though payroll suppliers broadly report initial filing success.”

Comment

It’s not everyday we report on a big government IT project that shows signs of succeeding. It’s too early to call RTI a success but it’s difficult to see how anything can go seriously wrong now unless HMRC’s helplines give way under heavy demand.

It’s worth remembering that RTI is aimed at PAYE professionals – not the general public as with Universal Credit. Payroll specialists are used to solving complex problems. That said, RTI’s success is critical to the success of Universal Credit. A barrier to that success has, for now, been overcome.

Perhaps HMRC’s RTI success so far shows what a central department can achieve when it listens and acts on concerns instead of having a mere consultation; and it has done what it could to avoid failure. They’re obvious precepts for the private sector – but have not always in the past been characteristics of central government IT schemes such as the NPfIT.

Cornwall Council’s cabinet approves BT deal after hurried talks

By Tony Collins

Independent Cornwall councillor Andrew Wallis has revealed on his blog that the councils’s cabinet has approved a tender from BT which involves the transfer of 132 staff in information services, 76 in shared services, 46 in document management and 28 in telecare.

Cornwall Council has rushed through agreement of a deal with BT – whether deliberate or not – ahead of the voting in of a new council in May. A formal consultation with the staff affected will begin next month.

All cabinet members apart from one, independent Bert Biscoe, approved the tender. Wallis says that a meeting today has brought to an end a “long, emotive, and fraught process”.

He adds: “I am pleased the Cabinet meeting today, and the information surrounding the bid, was all done in open session. It might bring some confidence back in to the process of partnership working.”

Cornwall’s cabinet ratified the recommendation that

“…  award of the contract to BT plc for the Strategic Partnership for Support Services, as set out in the Invitation to Submit Final Tender issued by the Council on 4 March 2013, be approved.”

The cabinet also gave authority for the signing of the contract to the Interim Chief Executive in consultation with the Leader, the Corporate Director of Resources, the Head of Legal, Democratic and Procurement Services and the Head of Finance.

Wallis says the deal guarantees the creation of 197 new jobs by end of year 4 and 313 new jobs to be delivered through reasonable endeavours by end of year 5.

“I am told the term reasonable endeavours has legal meeting, but for me, it still sounds wishy-washy,” says Wallis. “I am there will be some nervous staff wanting to know how they will fit into this new utopia.

Fifty two jobs have been identified to go by the end of year 4. There is a contractual commitment for most of the affected staff to be re-deployed.

Says Wallis: “The deed is done, and I just hope it will not turn into the disaster like so many other councils’ joint ventures up and down the land.”

There is a warning in a report to the cabinet about the risks of not signing a deal with BT. The report implies that BT would have to receive compensation for its bidding costs.

“If Cabinet chooses not to award a contract the Council will face a different set of risks (when compared to the risks of signing a contract).

“These risks would be higher in relation to finance and similar in relation to legal and delivery. As the bid meets the requirements as set out in the Evaluation Guidance … there are financial and legal risks in deciding not to award a contract.

“The ‘in-scope’ services have developed proposals with bidders over the past 12 months and if a contract is not awarded, work will need to be undertaken to ensure a level of continued service delivery in these areas in light of recent budget decisions.”

The report to the cabinet gives no projected cost of the deal. Officers are expected to sign a contract anytime after 24 March 2013.

Comment

BT’s promises, contractual commitments and guarantees are built into a concrete frame. Except that the frame can be broken apart by any legal dispute that throws clauses in the contract into doubt.

Let us hope Cornwall Council understands that its failure to keep its contractual commitments may bring BT’s litigation lawyers into play – and BT has more experience in outsourcing legal disputes than Cornwall Council.

Councillors will assume that Cornwall’s officers will be monitoring BT’s performance from day one of the contract. They may not realise that, perhaps with impressive diligence,  BT will be monitoring Cornwall Council’s performance from day one.

But not all councillors will need care how the contract progresses – for there will be a new council in May and some councillors may not stand or be re-elected.

If things go sour the new council could claim it wasn’t in any way responsible for the BT contract. All of this is within the context of rushed talks and a rushed agreement to sign the contract.

As Churchill said in the House of Commons in 1947:

“Democracy is the worst form of government, except for all those other forms that have been tried from time to time.”

Things run well and efficiently now at Cornwall Council. How can BT guarantee  197 jobs, invest more (Trading investment in bidding for new work – £1.9m plus £7.8m investment in transformation), make savings (£17.4m over 10 years) and run services more efficiently – and make a profit?

The Council says that BT will invest £157.5m in the partnership over 10 years, excluding an additional £16m spent outside Cornwall trying to win bids. The cabinet was told in a report that BT has made an “excellent offer”. But is it too good to be true? Indeed the one figure the report to the cabinet doesn’t give is the projected cost to Cornwall’s council taxpayers.

With the prices charged by BT for inevitable and as yet unforeseen changes, could the costs to the council more than wipe out savings?

It may be that all but one of Cornwall’s cabinet councillors, perhaps encouraged by council officers, have been naive. I hope I am proved wrong.

Andrew Wallis’s blog

Cornwall Council rushes to sign BT deal ahead of elections

Cornwall Council rushes to sign BT outsourcing deal before elections

By Tony Collins

Cornwall council logoCornwall Council was a model of local democracy in the way it challenged and then rejected a large-scale outsourcing plan. Now it has gone to the other extreme.

Amid extraordinary secrecy the Council’s cabinet is rushing through plans to sign a smaller outsourcing contract with BT – a deal that will include IT – before the May council elections.

Councillors who have been given details are not allowed to discuss them. No figures are being given on the costs to the council, or the possible savings. The Council’s cabinet is not releasing information on the risks.

Councillors are being treated like children, says ThisisCornwall. Documents with details of the BT outsourcing plans have to be handed back by councillors, and cabinet papers are being printed individually with members’ names as a watermark, on every page, to guard against copying and to help identify any whistleblowers.

The council’s Single Issue Panel has a timetable for the IT outsourcing plan.

– Recommendation to Cabinet to approve release of ITT – 27 February 2013

– Evaluation of bid – March 2013

– If contract awarded, commencement of implementation work – April 2013

– Staff transfer date – July 2013

The SIP report emphasises that the timetable for signing a deal is tight. “Evidence received is that there is little room for slippage in the timetable, but that potential award of contract is achievable by the end of March 2013… It is expected that a contract could be ready to be issued as part of the ITT [invitation to tender] pack by early in the week commencing 4 March 2013.”

The SIP report concedes that the plan is “fast moving”.

In the past, the SIP group of councillors has been open and challenging in its reports on the council’s plans with BT (and CSC before the company withdrew from negotiations). Now the SIP’s latest report is vague and unchallenging. The risks are referred to in the report as a tick-box exercise. Entire paragraphs in the SIP report appear to have little meaning.

“Risk log and programme timelines are reviewed and updated on a regular basis… 

“The Council and health partners have been working on and have reached agreement on their positions in relation to commercial aspects in the contract and their expectations have been part of the dialogue with BT.”

“Previous concerns of the Panel relating to the area of new jobs have been addressed with BT in contract discussions and contract clauses have been revised to reflect this…”

It is also unclear from the SIP report why the council is outsourcing at all, only perhaps a hint that the deal will be value for money.

“The contract will be fully evaluated by the Head of Finance and her team to ensure value for money once the final bid is received. No savings have been assumed for 2013/14 budgetary purposes, although there are assumptions of savings for the indicative figures for future years,” says the SIP report.

Comment

It is a pity that Cornwall Council’s cabinet is rushing to sign a deal for which it won’t be accountable if things go wrong. In a few weeks a new council will be voted in and, if the outsourcing deal with BT ends up in a dispute or litigation, the new council will simply blame the old, as happened when Somerset County Council’s joint venture deal with IBM, Southwest One, went into dispute.

In essence, with the local elections only two months away, Cornwall Council’s cabinet has a freedom to make whatever decision it likes with impunity; and it appears to be taking that freedom to an extreme, almost to the point of sounding, in the latest SIP report, as if the council is an arms-length marketing agent of BT.

Cornwall Council’s cabinet has a mandate from the full council to move to a contract with BT. The full council has voted to “support” a deal. But that vote was a mandate to negotiate, not to sign anything BT wants to sign.

Openness has gone out of the window and BT, it seems, is no longer being rigorously  challenged – by Cornwall’s cabinet, the full council, the public or the media.

How exactly can BT guarantee jobs and make savings? We don’t know. The Cabinet isn’t saying, and its members are doing all they can to stop councillors saying.

Are BT’s promises reliant on the fact that IT is subject to constant and sometimes costly change – often unforeseen change – and that is bound to continue, at least in the form of supporting changing legislation and reorganisations?

Unforeseen changes could add unforeseen costs which the council may have to pay because IT is at the heart of business continuity.  In any dispute with the council  – and BT knows its way around the world of contested contracts – the company would have the upper hand because of its experience with litigation and the fact that the council would need undisrupted IT at a time of change and could not afford, without risk, to take the service back in-house.

We have seen how normality broke down at Mid Staffs NHS Foundation Trust amid a lack of openness and excessive defensiveness;  and we have seen, in Somerset County Council’s joint venture with IBM, Southwest One, what can happen when a contract signing is rushed.

Cornwall Council’s cabinet is doing both. It is rushing to sign a contract; and it is rushing to sign it amid excessive secrecy.

Surely Cornwall Council can do better than slip into the shadows to sign a deal with BT before the council elections in May?  If it is such a good deal, the new council will want to sign it. A new council should have the chance to do so.

For Cornwall Council to outsource now what is arguably its single most important internal resource – IT – is bad for local democracy: it is snub to anyone who holds true the idea that local councillors are accountable to local people.

Thank you to campaigner Dave Orr who drew my attention to information that made this post possible.

* Cornwall Council, by the way, has one of the best local authority websites I have seen.  If the website is a reflection of the imagination and efficiency of its IT department, Cornwall Council should be selling its IT skills to BT for a small fortune – not giving staff away.