Category Archives: managing outsourced services

G4S is off the naughty step

By Tony Collins

The BBC says that G4S is again being considered for government business after being barred from bidding for new contracts in a row about overcharging.

In 2012 the Cabinet Office issued a notice to all departments, agencies and other public organisations saying that they should take into account a bidder’s past performance when considering a new contract.

The notice said that officials should satisfy themselves:

– that the principal contracts of those who would provide the goods and/or services have been satisfactorily performed in accordance with their terms

– where there is evidence that this has not occurred in any case, that the reasons for any such failure will not recur if that bidder were to be awarded the relevant contract.

If the Departmental Body remains unsatisfied that the principal contracts of those who would provide the goods and/or services have been satisfactorily performed, it should “exclude that bidder on the grounds that it has failed to meet the minimum standards of reliability set”, said the notice.

It appears that G4S was excluded from bidding on these grounds.

But the company agreed to repay £109m after an audit found it charged too much for providing electronic prisoner tags. The Serious Fraud Office is examining G4S and Serco over the contracts.

The firm has not bid for any government work since the Ministry of Justice started an investigation a year ago into its supply of electronic monitoring tags for prisoners in England and Wales since 2005.

After an audit by accountancy firm PricewaterhouseCoopers, it emerged that G4S – which insisted it had asked for the review itself – and Serco had overcharged the government by “tens of millions of pounds”.

Now the Cabinet Office has nothing but good to say about G4S. The CO’s statement says that the payments made by G4S to reimburse the taxpayer are a “positive step”.

Cabinet Office minister Francis Maude says:

“Following the material concerns that emerged last year, relating to overcharging on Ministry of Justice electronic monitoring contracts, G4S has engaged constructively with the government…

“Throughout, the government has engaged closely with G4S to understand their plans for corporate renewal. These discussions have been constructive; and following scrutiny by officials, review by the Oversight Group and reports from our independent advisors (Grant Thornton), the government has now accepted that the corporate renewal plan represents the right direction of travel to meet our expectations as a customer.

“This does not affect any consideration by the Serious Fraud Office, which acts independently of government, in relation to the material concerns previously identified. However, we are reassured that G4S is committed to act swiftly should any new information emerge from ongoing investigations.

“The changes G4S has already made and its commitment to go further over coming months are positive steps that the government welcomes. However, corporate renewal is an ongoing process and the government places a strong emphasis on their full and timely implementation of the agreed corporate renewal plan.

“The Crown Representative together with Grant Thornton will continue to monitor progress as their plan is implemented, reporting to government on a regular basis. I hope this will enable our confidence to grow.”

Comment:

A company has to do something very serious to be excluded from bidding – and it may be thought that G4S has come off the naughty step too quickly. On the other hand the notice on barring poor suppliers from bidding has a requirement that bidders provide a list of their main customers in the previous three years.  Certificates of satisfaction should be obtained from the customers. If necessary suppliers should obtain the certificates.

This is a useful incentive to suppliers to keep their customers happy.  But will departments implement what would be, in essence, a blacklist?

Thank you to openness campaigner Dave Orr for alerting me to G4S developments.

Should Liverpool Council smile now it’s ending BT joint venture?

By Tony Collins

Liverpool Direct Ltd describes itself as the largest public/private partnership of its kind in the UK. BT and Liverpool City Council formed the joint venture in 2001. At one point it employed more than 1,300 people.

Last year the joint venture had a visit from  Prince Edward who met its apprentices and trainees.

Now Liverpool City Council is taking full ownership of the joint venture. BT is handing back its 60% share in Liverpool Direct to the council. But the way the dissolution is being handled is like a theatre compere smiling exaggeratedly at the audience while he pushes off stage a performer who has overstayed his welcome.

Indeed the council’s report on why BT is being pushed out has an oversized grin on every page. Too much self-conscious praise for BT, perhaps. Which may show how political outsourcing deals have become.

This is the first sentence of the council’s report on why the joint venture with BT is ending:

“BT and Liverpool City Council have enjoyed a long and successful partnership through the joint venture company Liverpool Direct Limited.”

And then:

“The ethos of the Partnership was to place the ‘customer at the heart’ of the organisation through the development of innovative new ways of working building on BT’s global brand and reputation.”

There’s much more praise for BT. From the council’s report:

Groundbreaking achievements have included:

  • Establishment of the first ever 24x7x365 local government contact centre including a call centre which is top quartile
  • The only ‘Benefits Plus’ service in the UK.
  • A comprehensive and integrated network of One Stop Shops serving 350,000 visitors each year.
  • First class ICT infrastructure.
  • Creation of 300 new jobs supporting 3nd party business won by LDL.

But there’s a give-away line in one of the sets of bullet points on some of the benefits of the partnership. In 2011 came a refresh of the 10 year-old deal. The benefits of the refresh:

  • Further price reduction of £22.5m.
  • Increased share of third party business. Potential investment of £17m.
  • Continued sponsorship of ( e.g. BT Convention Centre 2012-2017)
  • The ‘write off’ by both parties of potential legal claims against Liverpool City Council estimated by BT of approximately £56m.
  • Increased ownership level from 20% to 40% in favour of the council.

Spot the anomaly – a write-of legal claims against each other of £56m? So the partnership wasn’t quite so wonderful. But that was 2011. Why is the council now pushing out BT from the Liverpool Direct joint venture – what the council calls officially “The Way Forward”?

Amid all the praise for BT it is not easy to see at first glance why Liverpool Direct is being taken into the council’s full ownership. It turns out that austerity is the reason. The council needs to make more cuts than BT is willing to make, and it recognises that BT needs to make a profit. Which raises the question of whether the council was willing to pay BT a decent profit during bountiful times until cuts began to bite.

From Liverpool Council’s report:

“In the early Autumn of 2013, both parties were in active discussions in an effort to resolve the serious financial savings Liverpool City Council needed to make between 2014 and 2017.

“As a result of these discussions and negotiations, BT agreed a further price reduction of £5m contribution to the budget process for 2014/15 together with a further £5m for the following financial year.

“Whilst the Council really appreciated BT’s continued commitment to the city, the current budget deficit would require a far more substantive financial contribution from the Contract both for 2014/15 and for future years.

“Unfortunately BT feels unable to commit to any further price reduction within the Contract as they need to sustain their own financial position. Moreover, the City Council is now well placed, as a result of the long collaboration with BT and the learning gained from the Partnership, to continue to drive forward business transformation and run the services with consequent cost savings to the city.”

The result is that negotiations will continue with a view to transferring BT’s 60% share in Liverpool Direct to the council by 31 March 2014; and the good news doesn’t stop there.

“The City Council and BT both believe that the transfer will enable additional savings to flow to the council including all income from third party contracts.

“BT remains committed to serving residents and businesses in Liverpool and its long and successful relationship with Liverpool City Council will carry on with BT continuing to provide a range of services to the council. During negotiations in late 2013 BT announced it plans to recruit a further 240 staff in Liverpool to support the growth of high-speed broadband services and has recently committed to being a major sponsor of the 2014 International Festival of Business.”

A dark side?

Behind the smiles Liverpool City Council has, it seems, an unusually secretive side.   Richard Kemp CBE has been a member of Liverpool City Council for 30 years having held major portfolios in both control and opposition. He is leader of the Liberal Democrats on the Council. He was Vice Chair of the Local Government Association of England & Wales for more than 6 years.

He says on his blog that has “taken the very unusual step of asking for two independent enquiries into activities of Liverpool City Council”. He adds: “The cases are related and refer to the tangled web of relationships which surround the Liverpool/Liverpool Direct Ltd/Lancashire/One Call Ltd/BT activities.

“In the first instance I have asked that the Lancashire Police extend their Lancashire investigation into Liverpool. In the second I have asked the Information Commissioner to look at the appalling record of the council in responding to freedom of information requests about any matter relating to Liverpool Direct Ltd.”

He says the council has an excellent record of responding to FOI requests – except when it comes to LDL. “When I raised this with the Mayor at the Mayoral Select Committee I didn’t get any answers …”

He also says:

“I find it amazing that I have been told that no contract exists between Liverpool, Lancashire and BT only to find that there is a legal agreement! As a layman I am unclear as to what the difference is between these two positions.

“We now need external scrutiny and investigation to examine these tangled relationships and work out not only who agreed what and when but also whether Liverpool and Lancashire tax payers are getting value for money for this deal.

“In a system where there is no internal scrutiny, Liverpool Labour members have to ask permission to raise issues in the scrutiny process, I feel that I have no alternative but to ask for help in looking at these affairs outside the council.

“In my career I have not only been a councillor for a long time but also asked to work in other councils which were in severe difficulties with their governance structures. Liverpool feels as bad as any council that I have worked in. There is no clear definition of Member and Officer roles.

“ No effective challenges exist within the system and a centralised almost Stalinist decision-making process pertains … I hope that these external investigations will take place and then that they force change in this secretive and opaque council.”

Infighting

A local paper, the Liverpool Echo, has also been investigating the council and its deal with BT.

It says the deal “has been dogged by accusations of infighting between BT and the Council, after top QCs were brought in to settle disputes over how much work would be awarded to LDL under the terms of its contract”.

An internal council report obtained by the Echo before agreement for the contract refresh in 2011 “showed the it took place amid the threat of costly legal claims by BT if city bosses pulled the plug and did not stay in partnership with them until 2017”.

Private/public deals too secretive – MPs today

A report by the Public Accounts Committee published today Private Contractors and Public Spending says private and public partnerships are too secretive – and they lie largely outside the FOI Act. Indeed a BBC File on 4 investigation into the growing influence of accountancy companies such as Capita in public life reached similar conclusions. File on 4 suggested that even if the contract between Service Birmingham, Capita and Birmingham City Council were published in full it could prove impenetrably complicated.

Margaret Hodge MP, chairman of the Public Accounts Commitee, said today:

 “There is a lack of transparency and openness around Government’s contracts with private providers, with ‘commercial confidentiality’ frequently invoked as an excuse to withhold information.

“It is vital that Parliament and the public are able to follow the taxpayers’ pound to ensure value for money. So, today we are calling for three basic transparency measures:

– the extension of Freedom of Information to public contracts with private providers;

– access rights for the National Audit Office; and

– a requirement for contractors to open their books up to scrutiny by officials.

Comment:

It’s remarkable how council outsourcing deals are becoming more cabalistic despite many initiatives toward more open government.

It’s a pity that things have reached a point where Richard Kemp, a Liverpool councillor of 30 years, ends up reporting his authority to the police and the Information Commissioner.

Meanwhile Liverpool City Council, which is one of the most self-image-protecting authorities in the UK, ends a long-standing joint venture with BT by giving the supplier nothing but praise – in public.

Democracy is a form of government in which all eligible citizens participate equally, either directly or indirectly through elected representatives. Clearly that’s not happening properly in Liverpool – or  some other parts of local government.

Reasons I have asked police and Information Commissioner to come in 

BT ad Capita  –  outsourcing joint ventures under pressure in Liverpool and Birmingham 

Private contractors and public spending – Public Accounts Committee report published today

BBC World at One’s focus on Government IT

By Tony Collins

The lead item on BBC R4’s World at One on Friday was about Government IT contracts.

On the programme were the government’s Chief Procurement Officer Bill Crothers, Cabinet Office minister Francis Maude, the chairman of the Public Accounts Committee Margaret Hodge, the UK IT Association, and me.

Some of the points made:

–  Bill Crothers gave an example of what he called “abuse” by some big IT suppliers. He said a young man who works for him lost his power cable. The supplier quoted £65 for a replacement. The price should have been £5 or £6.  When Crothers queried it, the supplier justified its price on grounds of security. Crothers could not believe that a power lead had security implications so he questioned the price again and received several pages of explanation from the supplier, which he did not read. Eventually the supplier “was good enough to reduce the price to £37”.

– HMRC was charged £30,000 for changing some text on its website.

– Francis Maude said a DWP team and a further 12 people from the Cabinet Office’s Government Digital Service had built – in only three months – a prototype of a digital solution to support the introduction of Universal Credit. The system cost just over £1m, he said. [Separately big IT suppliers at DWP have been paid £303m up to March 2013 for Universal Credit work.] Maude declined to predict the outcome of the “twin-track” work on the UC project.

– Some big legacy systems may soon need replacing – those that pay about £60bn a year in state pensions and collect nearly £100bn a year in VAT. “Those are going to be big projects,” said Margaret Hodge. “I don’t think we have seen the end of big projects, or the end of disasters.”

World at One in detail

Presenter Shaun Ley and BBC political correspondent Ross Hawkins focused on government IT because of an announcement by the Cabinet Office that it is drawing the line on “bloated and wasteful IT contracts”. The Cabinet Office was pitching its announcement as marking a “massive change,” said Hawkins.

Ley said Francis Maude announced the safeguards  in an attempt to ensure that IT contracts don’t become multi-billion pound failures. He said that the abandoned NPfIT had cost close to £10bn.

Hawkins quoted the UK IT Association as saying that  government did not know how to do deals with smaller suppliers. On the government’s relationship with big suppliers UKITA said the government was like a “battered wife or husband who doesn’t seem to know how to leave.”

Appalling

Hawkins said Crothers has the air of a man going to war. Crothers’ conclusion on the way things are at the moment:

“This is about the oligopoly, the cluster of big suppliers that have had it took good for too long. It’s reflective of monopolistic or oligopolistic behaviour.  It is not acting as if they are in hungry and in a competitive market.  That’s appalling.”

Universal Credit

Hawkins asked Francis Maude how confident he was that what was being put in place on Universal Credit would work.

“I hope it will work,” said Maude. “The digital solution was created by a team within DWP with a dozen or so GDS [Government Digital Service] staff assisting.

“They created a working prototype for a digital solution within 3 months at a cost of only a bit over £1m. That certainly can be basis of a successful long-term solution.”

Hawkins [to Maude] “I asked you whether you were confident the approach with DWP would work and you said you hoped it would. That suggests to me that maybe you are not (confident).”

Maude: “N0-one knows with these things. Anyone who says you are certain everything is going to succeed … the way we do things now is build something quickly, test it, prove it, test it with users, and so you can’t have certainty about any of these outcomes.”

Outsourcing failures

Hawkins said “We have had story after embarrassing story about outsourcing failures [such as the] government being charged for tagging dead people … now ministers  have an interest in coming out on the front foot and just for once being on the attack and having a whack at the IT companies.

“You don’t need to be a political genius to work out why they would like to do that rather than be endlessly explaining themselves after embarrassing stories in the papers.”

Ley (to me): “Is this the best way to deal with the problems government has experienced? The journalist Tony Collins has written widely  about project failures in IT in both the public and private sectors.”

I replied that big companies have sometimes charged a lot to make small software changes.  The Cabinet Office’s “red lines” were a good idea though they were a formalising of restrictions that had been in place some time.

The Cabinet Office doesn’t have the power to make changes happen because departments are accountable to Parliament for their spend and so don’t want much interference from the Cabinet Office. But the Cabinet Office is right to try and reduce the amounts spent on big projects.

Ley: “What will be the effect of breaking up contracts?”

I said I hoped the Cabinet Office’s restrictions would bring about a change in culture in departments against the assumption that big is beautiful. Big projects should be split into components which would give SMEs a greater involvement and could reduce the risks of projects failing.

More project disasters?

Hodge gave her reaction to the Cabinet Office’s restrictions in the context of the Universal Credit project.

“Francis Maude and Cabinet Office have been trying really hard to get some sense into the way that project has developed. But sadly the news we have had lately suggests to me that they have failed. It is about £400m so far on IT.

“What went wrong there was that the department [DWP] thought it [UC] was a big IT project instead of thinking:  we are going to be changing our business; we are going to get 6 benefits rolled into one. They [the DWP] have not written off that money [£303m] which is what my committee thinks they should have done, because they want to save face. Down the line I think we’ll see some disasters there.

“There are a lot of projects around  government, what are called legacy projects, where old systems need to be replaced . They are big projects – pensions in DWP where £60bn is given out a year;  VAT receipts  in HMRC where nearly £100bn is collected. Those are going to be big projects. I don’t think we have seen the end of big projects, or the end of disasters.”

Ley: “What about breaking them up into smaller projects? Won’t that reduce potential risks?”

Hodge: “The important thing is what Tony Collins was saying to you. What we find is that the skills don’t exist within departments, either to commission the IT properly or to manage the suppliers once they have the IT in place.

“We are about to examine the army recruitment contract – I think that is what we’ll find.  The MoD hasn’t got the skills to manage it.

Ley: “Do you welcome the ending of automatic contract extensions?”

“I warmly welcome that. This is a small step in the right direction. Having an expert as we have in Bill Crothers in the Cabinet Office is really important. What we haven’t got are skills in the departments. It is not like a business. If it was, Bill Crothers would probably run IT across the whole of government. Our departments run in silos. They haven’t got the skills. They have this demand for big, big programmes in the future and I don’t think we have seen, sadly, the end of IT disasters.”

Update

Thank you to Dave Orr for drawing my attention to an excellent piece on the World at One item by procurement expert Peter Smith who concludes:

“… There is a big issue – large suppliers have not covered themselves in glory, but small suppliers just can’t develop huge systems for DWP or MOD.

“The large suppliers must have a role, but we have to manage these contracts better. And the answer can’t just be a small hit squad in Cabinet Office. This needs real capability development across government, which we haven’t really seen as yet in a coordinated fashion.”

BBC World at One – Government IT contracts

Bill Crothers on BBC Radio 4 – suppliers get another good kicking

Will Universal Credit be complete by 2020?

By Tony Collins

Comment

Much of what Iain Duncan Smith said at the Work and Pensions Committee yesterday made sense. In essence the DWP’s plan is to delay putting most of the  claimants onto the Universal Credit system until the technology is proven to work.

But there is little evidence it will work at scale, handling reliably and accurately millions of claimants and complex cases. It emerged yesterday that the DWP has still not yet agreed with suppliers a specification for the UC systems, and the latest business case has yet to be approved. How can anyone say on the basis of the limited work so far that the technology will work?

And Howard Shiplee,  Director General of Universal Credit, made the point yesterday that the technology is only part of the story. For UC to work there have to be changes in culture, operational procedures within the DWP and the retraining of tens of thousands of staff.

IDS is doing what various sets of ministers and officials did during the distended failure of the NHS’s £11bn computer programme, the National Programme for IT [NPfIT]: in assuring Parliament all was well they always used the future tense. The programme “will” give everyone in England an electronic patient record. But nothing was delivered that provided evidence the promises would be fulfilled. It took a new government to admit the NPfIT was a failure.

UC differs from the NPfIT in a crucial way. The NPfIT did not need to work. It was conceived at the top without support from the NHS. Many hospitals didn’t want centrally-bought IT foisted on them. The NPfIT was wanted, in the main, by a small number of politicians, officials and big suppliers. UC is needed and wanted. Simplifying the horrifying complex benefit systems has all-party support. Shiplee is right when he says UC has to work. But he didn’t yesterday commit himself to a timeframe.

The last major benefits computerisation project – called “Operational Strategy” – took about 10 years to finish. It did not achieve the promised financial benefits and benefit systems were not combined as originally intended but, in the end, the technology worked well for its time.

If UC does work there’s every reason to believe it will be in a similar timeframe to Operational Strategy: about 10 years. But could IDS keep his job while saying UC will be fully delivered in 2020 or beyond? I doubt it.

Patient records go-live “success” – or a new NPfIT failure?

By Tony Collins

John Goulston says the go-live of a new patient records system at his trust is a “success”.

He should know. He’s Chief Executive of Croydon Health Services NHS Trust. He’s also chair of the trust’s Informatics Programme Board which has taken charge of bringing Cerner Millennium to Croydon’s community health services and the local University Hospital, formerly the Mayday.

He was formerly Programme Director of the London Programme for IT at NHS London – a branch of the NPfIT.

In a report two weeks ago Goulston said the trust deployed the “largest number of clinical applications in a single implementation in the NHS”. Croydon went live with Cerner Millennium on 30 September and 1 October 2013.

Said Goulston in his report:

“Administrative functions do not engage clinicians; providing them with a suite of clinical functionality has been justified as each weekday approx. 1,000 staff are logged on and using the system. CHS [Croydon Health Services] has in Phase 1 deployed, in addition to patient administration, the largest number of clinical applications in a single implementation in the NHS England.”

BT helped install Millennium at Croydon under the National Programme for IT.  The trust’s spokesman says the Department of Health provided central funding, and the trust paid for implementation “overheads”.  The Health and Social Care Information Centre was the trust’s partner for the go-live.

The Centre is the successor for Connecting for Health. It has taken on CfH’s officials who continue to help run the NPfIT contracts with BT and  CSC.

Goulston said that Cerner and BT have paid tribute to the trust which installed Millennium in A&E, outpatients, secretarial support and cancer services, and elsewhere.

“Our partners Cerner, BT and Ideal have commented that the Trust has undertaken one of the most efficient roll-outs of the system they have worked on, with more users adopting the system more quickly and efficiently than other trusts … the success we have achieved to date is the result of the efforts of every single system user and all staff members,” said Goulston.

Best Cerner implementation yet?

Optimistic remarks about their launch of Cerner Millennium were also made in 2012 by executives at the Royal Berkshire NHS Foundation Trust.  Their optimism proved ill-judged.

Of the Millennium go-live at Royal Berkshire, trust executives said that it “had been considered to be the best implementation of Cerner Millennium yet and that despite staff misgivings, the project was progressing well”.   This positive message should be disseminated, they said.

Months later they told the Reading Chronicle of patient safety issues and a financial crisis arising from the Millennium implementation.

A Royal Berkshire governors Rebecca Corre was quoted as saying: “There is a patient safety issue when staff write down observations and then there is an hour before they can get it onto the computer. If it is an experienced nurse, they may pick up a problem, but others may not.”

Ed Donald, Chief Executive of Royal Berkshire was quoted as saying:

“Unfortunately, implementing the EPR [electronic patient record] system has at times been a difficult process and we acknowledge that we did not fully appreciate the challenges and resources required in a number of areas.”

Are executives and managers at Croydon Health Services NHS Trust  now similarly afflicted with an unjustified optimism about the success of their Cerner go-live?  

Past consequences of NPfIT go-lives hidden?

The Department of Health has claimed benefits for the NPfIT of £3.7bn to March 2012 but there have been trust-wide failures: thousands of patients have had their appointments, care or treatment delayed by difficulties arising from past implementations of patient record systems under the NPfIT.  For thousands of patients waiting time standards have been exceeded or “breached” because of disruption arising from troubled go-lives.

In nearly every case trusts made it difficult for the facts to come out publicly. Vague or unexplained fragments of information about the consequences of the NPfIT implementation appeared  in different board papers over several months. The facts only emerged after a journalistic investigation that required scrutiny of many board papers and follow-up questions to the trust’s press office.

So Campaign4Change investigated Croydon Health’s implementation of Cerner Millennium to see if the Francis report’s call for a “duty of candour” over mistakes and problems in the NHS have made any difference to the traditional fragmentation of facts after NPfIT go-lives of patient record systems.

The Francis report called for “openness, transparency and candour“.  Trusts were told not to hide sub-standard practices under the carpet. The health secretary Jeremy Hunt said it can be “disastrous” when bad news does not emerge quickly and the public are kept in the dark about poor care.

To my questions about the Cerner Millennium implementation Croydon trust’s spokesman always responded promptly and tried to be helpful. But it appears that trust executives have given him limited information about consequences of the go-live, and have preferred to indulge the “good news” NHS culture that Jeremy Hunt warned about.

On being asked what problems the trust has faced since the go-live the spokesman gave various answers that made no mention of the problems.

“All of our staff received training on the system, and we are continuing to offer our teams support as it is embedded.”

What of the problems arising from the implementation, and has the board been fully informed?

“Millennium has featured regularly on the Corporate Risk Register presented to each Part 1 Board meeting.   In addition, implementation has received detailed confidential consideration at Part 2 of Board meetings, (which is why you won’t find it in our public board papers).”

Given Francis’s call for duty of candour,  should the trust be more open about its problems?

“The initial roll out for CRS Millennium was introduced over three days at the Trust, with a phased approach.  We did this to ensure the system was working in each department, before introducing it in another area.

“We are monitoring waiting time performance and records management so we can identify any issues if they emerge. The system is still being introduced in some services and when this is completed we will be able to assess the overall programme,” said the spokesman.

Does Croydon’s unwillingness to give in its statements to me any details of problems indicate that the culture of a lack of transparency in the NHS will be hard to change, no matter how many times Jeremy Hunt talks about the need for candour when things go wrong?

The spokesman:

“I’d like to be clear about the Trust’s approach:

  • The Trust board has been cited on the roll out of CRS Millennium and any potential risks throughout the process.  As I previously noted, the board received an update in September.  The board meeting, which will take place on Monday of next week, will receive a further update from the Chief Executive.  The papers from this meeting will be published on our website and the meeting takes place in public;
  • A meeting chaired by the Chief Operating Officer has reviewed any operational matters arising on a daily basis.  This is an internal meeting for clinicians and managers which has informed the implementation process;
  • Patients and visitors to the hospital have been kept fully appraised of the introduction of the system and were made aware that they may experience some delays to the check-in process while staff became familiar with the new computer system;

“These actions would suggest that the Trust has been transparent in its approach.  You are welcome to review the board papers when they are published.”

Serious problems now emerge

Croydon did indeed publish its board papers on 25 November 2013 – which is to its credit because not all NHS trusts publish timely board papers.

But it’s mostly in the small print of various board papers that details emerge of Millennium-related problems. The shortcomings are mentioned as individual items rather than in a single, detailed Cerner Millennium deployment report.  This leaves one to question whether trust directors have an overview of the seriousness of the difficulties arising from its implementation of a new patient records system.

These are some excerpts from deep inside Croydon’s latest board papers:

Breaches in waiting time standards

– “CRS Millennium (Cerner) Deployment -Network downtime – Week 1.  In particular, the significant network downtime in week 1 (BT N3 problem) led to no electronic access to Pathology and Radiology which resulted in longer waits for patients in the Emergency Department (ED) leading to a large number of breaches. This was a BT N3 problem which has been rectified with BT providing CHS with the required scale of N3 access (>600 concurrent users and >1,600 users on any day – which is the largest network usage of any trust in England).”

– • “Hospital Based Pathways: The deployment of CRS Millennium was a particular challenge in the month across the multiple service areas within the Directorate of A&E, Surgery and Maternity.

• “Cancer & Core Functions: With the implementation of CRS Millennium, the open pathways part of RTT [referral to treatment – patient waiting times) may fail the standard – validation will be completed after the narrative for this report… “

Excessive waits in A&E

– “The main drivers adversely affecting the performance in the month [October 2013) for A&E were the deployment of CRS Millennium and the commencement of winter pressures due to the seasonality change.  A&E  4-Hour Total Time in Department Target: 95.00%. Actual: 91.57%.”

Over budget

“The Trust position as at October is an adverse variance of £4.1m. This is a significant deterioration on the Month 6 position. The movement is mainly due to a significant reduction in income mainly as a result of operating issues caused by the Cerner deployment (£0.9m)…  Actual £14.8 (£14.8)m; Budget £10.7m; Variance £4.1m.”

“Cerner Millennium: Plan YTD [year-to-date] £245,000; Actual YTD  £621,000;

Significant loss in income

“… A new patient administration system was deployed in the Trust on the 30th September and 1st October (Cerner Millennium). The deployment has resulted in significant loss in income in September and October £ 1.1m. Trust performance on Activity Planning Assumptions and Key Performance Indicators is substantially worse than plan …”

Extra costs

“Medical £412k and admin £148k agency levels continue to be high due to cover for vacancies, annual leave, sickness and release of staff for Cerner training. The Trust has also incurred additional costs associated with the Cerner deployment (£600k) including overtime payments to administration staff and training costs.”

Bid to recover Cerner costs?

“… The Trust is currently forecasting a deficit position of £17.8m, which is £3.3m off the plan submitted to the NHS Trust Development Authority. This is a £3m movement from the month 6 forecast and is as a result of operational issues caused by the Cerner deployment. The current projected impact is an additional costs £1.7m and a loss in activity £1.1m . An application is to be made to recover the additional cost/losses relating to the Cerner deployment [of £2.9m] …”

HSCIC support for delays

“Cerner Millennium – Revised implementation date to Sept 2013 (achieved) ,with resultant additional costs including additional PC requirements of £146k, specialist support services £300k, procurement costs £91k, data cleansing costs £200k.

“Health& Social Care Information Centre (HSCIC) has confirmed support for the delayed implementation will be provided, accounting treatment of support to be confirmed with Department of Health.”

More money to stabilise operational position?

“As a result of operational issues caused by the Cerner deployment , Income is significantly reduced in October. The forecast assumes that the Trust will resume normal operating levels from November and that an element of the income lost will be will be recovered in the latter part of the year. A business case is being submitted to the Trust Board for additional investment in Cerner to stabilise the operational position.

“If there are further operational issues due to the Cerner deployment then this will significantly impact on the year end forecast…”

Over-optimism?

Principal risk -reporting output from Cerner is not accurate or timely. Officer in charge: CEO. Before go-live risk scores: June 2013 – 16; July – 16; Aug  – 10; Sept – 10. After go-live risk score (for Oct): 20 [high risk of likelihood and consequences]

Principal risk – operational readiness following the implementation of Cerner. Officer in charge: COO.  Before go-live risk score 15. Post go-live: 20. Risk rating before go-live – Green. After go-live – Red.

Red risks

Corporate Risk Assurance Framework

Nine risks are reported as Red [two of which relate directly to Millennium]:

“… Reporting output from Cerner is not accurate or timely. Data migration was successful. However reliance on external provider as internal knowledge has not yet been fully gained. A data quality dashboard with exception reporting is in place.

“… Operational readiness following the implementation of Cerner CRS Millennium impact conveyed to Trust Development Authority e.g. ED [Emergency Department] reporting and cost overruns

Risk scores

– Failure of CRS millennium to deliver anticipated benefits – 12. Officer in charge: CEO

– Reporting output from Cerner is not accurate or timely – 20. Officer in charge: CEO

– Operational readiness following the implementation of Cerner – 20. Officer in charge: COO

Croydon’s trust’s response to problems

Said John Goulston, Croydon’s CEO, in his latest [November 2013] report to the board of directors:

“The issues being encountered now with CRS Millennium are not due to any lack of integration testing with legacy applications or testing of workflow. They can be attributed to changing from a 25 year old Patient Administration System (Patient Centre) which did not require working in real time, was simple and intuitive to use, easily configurable and flexible to our needs.

“CRS Millennium’s patient administration functions are almost the complete opposite and the language used is new for our staff i.e. conversations, encounters etc. For our staff it has been a big ask for them to step into and up to such a complex application.”

He added: “The benefits of the new system are that each patient will have a single accurate electronic record that can be viewed and kept up-to-date by hospital and community clinical staff. This will eventually mean less time searching for patient notes, missing documentation and duplicating patient information…

“As with any massive change, there are still some challenges to tackle in making the system work effectively for every single user, in a diverse and complex organisation.

“However the success we have achieved to date is the result of the efforts of every single system user and all staff members. I would like to thank all our staff for their hard work in getting the Trust to this important stage.”

The trust spokesman gave me this statement on the problems:

“The Trust board has been given regular reports on the roll out of CRS Millennium and any potential risks throughout the process, not least through its regular reviews of the Corporate Risk and Board Assurance Frameworks.  As I previously noted, the board received a specific update in September.

“As you already know, November’s board meeting received a further update from the Chief Executive.  The papers from this meeting were published and the meeting takes place in public;  Those attending are invited to put forward questions.

“A meeting chaired by the Chief Operating Officer continues to review operational matters.  This is an internal meeting for clinicians and managers which has informed the implementation process;

“Patients and visitors to the hospital have been kept fully appraised of the introduction of the system and were made aware that they may experience some delays to the check-in process while staff became familiar with the new computer system;

“As you highlight from the board report, Cerner & BT noted that ‘the Trust has undertaken one of the most efficient roll-outs of the system they have worked on’   The papers also note some operational challenges as the system was rolled out.  These have been addressed as part of the daily meetings I reference above – these are mainly concerned with users familiarising themselves with the system and have been addressed through the support and training staff received.

“In terms of the costs, the introduction of CRS Millennium has been supported by central funding from the Department of Health with the Trust paying the implementation overheads.   These costs are a matter of public record and the Trust publishes annual Accounts as part of its Annual Report.”

Comment

When you go into hospital it’s reassuring to know the directors will be well informed and open about problems that could affect you.

The approach of Croydon Health Services NHS Trust to openness about its problems is not reassuring. It is no better or worse than other trusts that have implemented Cerner’s Millennium. In fact the timely publication of its board papers means it is more open than some.

But it should not require a time-consuming journalistic investigation to establish the consequences for patients of an NPfIT go-live. It has required just such an investigation after the go-live of Millennium at Croydon.

Board directors will not have the time to dig for, and piece together, information about internal problems that could delay patient appointments, treatment and care. They need the unpalatable facts in one place. Croydon Health Services has failed to make it easy for patients or board directors to see what has gone wrong.

NPfIT deployments at other trusts have led, cumulatively, to thousands of patients having appointments that were disrupted, or who had to wait longer to be seen than necessary, or whose records were not available, or who were seen with another patient’s records.

In shying away from telling the whole truth trusts take their cue from the top: the Department of Health has always made it hard to establish facts about anything to do with the NPfIT.  Said the Public Accounts Committee in its report The National Programme for IT in the NHS: an update on the delivery of detailed care records systems in July 2011:

 “It is unacceptable that the Department [of Health] has neglected its duty to provide timely and reliable information to make possible Parliament’s scrutiny of this project.

“Basic information provided by the Department to the National Audit Office was late, inconsistent and contradictory.”

Unanswered questions

Croydon has questions to answer, such as how many breaches of waiting time standards it has had, and may still be having, due to problems arising from the go-live. Other unanswered questions:

– What does a “a large number of breaches” in the Emergency Department mean? Have each the patients affected been told?

– Why are the risks related to the implementation much higher after go-live than before, given that the trust has had years to prepare for the go-live, and the many lessons it could have learned from other trusts?

– Exactly what problems are still affecting patients?

In a post-Francis NHS, Jeremy Hunt has demanded openness about mistakes and problems. There is an agreed need for change – but how can Hunt change an NHS culture – indeed a public sector culture – in which senior executives, in troubled IT implementations, will always emphasise the good news over the bad, perhaps hoping the bad will always remain hidden?

Did DWP mislead MPs and media over Universal Credit?

By T0ny Collins

Today’s report of the all-party Public Accounts Committee “Universal Credit: early progress” goes beyond criticisms of the scheme in a National Audit Office report of the same name on 5 September 2013.

Public Accounts MPs say the Department for Work and Pensions gave “misleading interviews to the press regarding progress after it became aware of difficulties with the programme”.

And as recently as July 2013 the “Department denied that there were problems with the programme’s IT when it gave evidence to the Work and Pensions Committee”.

These criticisms are against a background of the DWP’s refusal to publish any of the many internal and external reports the department has commissioned on the project’s progress, problems and challenges since 2011.

The Times today says that work and pensions secretary Iain Duncan Smith and members of his parliamentary team are “understood to have approached at least three Tory MPs on the cross-party [Public Accounts] committee to ask them to ensure that Robert Devereux, Permanent Secretary at the Department for Work and Pensions, was singled out for censure”.  In the end there was only limited criticism in the PAC report of Devereux – under his formal title of “Accounting Officer”.

Comment

If the DWP has been misleading the press, giving incorrect evidence to Parliament, and keeping secret its reports on the problems and challenges facing one of the government’s most important IT-based programmes – all of which seem to be the case – is it an institution that regards itself as uniquely outside the democratic process?

On big IT projects, officials are not motivated by money and concern for their jobs as are private sector boards of directors. When a private company gets it wrong and loses tens of millions on a project, the share price may fall, individual bonuses may be hit, and jobs, including the CEO’s, may be at risk.

In the public sector getting it wrong rarely has any implications for officials. They have only the threat of departmental embarrassment as a deterrent to getting it wrong. But they need not fear even embarrassment if they can mislead the press and Parliament and keep secret all their internal and external reports.

If a lack of transparency, culture of denial, and the misleading of Parliament continue to characterize big risky IT-based ventures in central government, one has to ask whether Whitehall is congenitally ill-suited to running such programmes.

The Public Accounts Committee warned in a report in 1984 about the risks of large public sector computer programmes. That report came after a series of project disasters.

So what has been learned in the last 30 years – other than that central departments are poorly equipped managerially – or democratically – to handle big IT-based programmes and projects?

These are some of the Public Accounts Committee’s findings:

MPs try to be positive

“We believe that meeting any specific timetable is less important than delivering the programme successfully. There is still the potential for Universal Credit to deliver significant benefits, but there is no clarity yet on the amount of savings it will achieve.”

Culture of denial

“The programme had also developed a flawed culture of reporting good news and denying that problems had emerged. This culture resulted from the desire of senior staff within the programme to show publically that they were able to push the programme forward, at the expense of ensuring that adequate controls were in place or listening to concerns raised about its delivery.

“Although the Department has tried to tackle this culture, it gave misleading interviews to the press regarding progress after it became aware of difficulties with the programme, and as recently as July 2013 the Department denied that there were problems with the programme’s IT when it gave evidence to the Work and Pensions Committee.”

Shocking absence of control over suppliers

“There has been a shocking absence of control over suppliers with the Department neglecting to implement basic procedures for monitoring and authorising expenditure…

“The Department recognises its supplier management has been weak, risking value for money.  Four main suppliers – Accenture, IBM, Hewlett Packard and British Telecom – have provided IT systems for Universal Credit, and by March 2013 the Department had paid them £265m out of the £303m spent with suppliers on IT systems.

“In February 2013 the Major Projects Authority found no evidence of the Department actively managing its supplier contracts, resulting in suppliers being out of control and financial controls not being in place.  The Department has yet to provide a comprehensive assessment of how much of this expenditure has proved nugatory, although the Major Projects Authority believes it will be a substantial figure running into hundreds of millions of pounds.”

Lack of oversight

The lack of oversight allowed the Department’s Universal Credit team to become isolated and defensive, undermining its ability to recognise the size of the problems the programme faced and to be candid when reporting progress…

“Oversight has been characterised by a failure to understand properly the nature and enormity of the task, a failure to monitor and challenge progress regularly, and a failure to intervene promptly when problems arose.

“Senior managers only became aware of problems through ad hoc reviews, mostly conducted by external reviewers, as inadequate management information and reporting arrangements had not alerted them that things were amiss.

“Given its huge importance to the Department, the Accounting Officer [Robert Devereux] and his team should have been more alert to identifying and acting on early warning signs that things were going wrong with the programme

Blinkered culture remains?

“Risk was not well managed and the divergence between planned and actual progress could and should have been spotted and acted upon earlier. The Department only reported good news and denied the problems that had emerged. The risk of a similarly blinkered culture remains as the Department will be working to tight timescales to get the programme back on track.”

Problems hidden

“It is extremely disappointing that the litany of problems in the Universal Credit Programme were often hidden by a culture prevalent in the Department which promoted only the telling of ‘good news’.

“For example, officials were aware that a critical report highlighting many of these issues had been discussed internally for months. Indeed, there are real doubts over when officials became aware of these problems and it is difficult to conceive, based on the evidence we were presented with, that officials within the Department did not know of them before July 2012.”

Shocking absence of financial and other controls

“There has been a shocking absence of financial and other internal controls and we are not yet convinced that the Department has robust plans to overcome the problems that have impeded progress.”

Did the DWP do anything well?

“The Department initially adopted a piecemeal approach to delivering the programme.

“In 2011 it identified over a hundred different types of users for Universal Credit, and initially sought to design IT solutions for each set of circumstances individually. It was only in early 2012 that the Department decided to stand back and try to establish a clearer picture of what the programme’s overall shape might look like.

“During the summer of 2012 the Department became aware of the problems that Universal Credit faced. It was first alerted by concerns raised in a supplier-led review, commissioned by the Secretary of State, which reported in July.

“The Department subsequently established that the programme’s progress was stalling because there were a number of unresolved issues which had become intractable, particularly relating to the level of security needed for identity assurance and protection against fraud and error and cyber-attack.

“The Department had been previously unaware of the programme’s difficulties because its internal lines of monitoring, intervention and defence, intended to identify and mitigate such problems, were not working properly. Governance arrangements were not remotely adequate, and the Accounting Officer [Robert Devereux] discussed progress with the head of the Universal Credit programme only every two or three weeks.

“The Department had inadequate performance information to scrutinise and challenge the programme’s reports of its progress, so internal reporting arrangements did not flag up that things were amiss. The Department’s corporate finance undertook insufficient work to ensure there was an appropriate control environment in place, and the Department’s process for ministers to sign-off higher-value contracts was weak.

“The Department’s senior management had relied on ad hoc reviews, mostly conducted by external reviewers, which only provided an occasional snapshot of the programme, instead of ensuring effective internal systems were in place to monitor and challenge progress. However, during 2012 the problems surfaced more clearly as the Universal Credit team became unable to respond to recommendations made by such reviews.”

Will Universal Credit ever work?

“The Department remains uncertain about key details of its final plans. It does not know how much can be delivered online, when this will be available, and what activities will continue to require face-to-face meetings.

“ The Department also does not know what the final cost of the IT will be, or the savings the programme is expected to deliver. Nor does it know when it will close down the other benefits that Universal Credit will replace.”

The Department has a target of enrolling 184,000 claimants on Universal Credit by April 2014 and has launched limited pilot schemes.”

Says the PAC report: “The current rate of progress is significantly below target, however. Only around 2,500 claimants were registered at the time of our hearing in September, and the Department was unwilling to speculate what number will be enrolled by next April.”

In a steady state Universal Credit is expected to deal with 10 million people in about 7.5 million households, making 1.6 million changes in circumstances each month.

Security versus usability

“The Department is aware that the system must include suitable security arrangements if Universal Credit is to operate effectively and deliver its intended benefits.  However, the Department has not yet finalised such a solution, and was unable to say when two key components – those countering fraud and error and confirming claimants’ identity- would be completed.

“The Department has found it particularly hard to establish the right balance between security and usability. The development of an effective security system has been hindered by security not being integral to the design of IT components from the outset, but instead being retro-fitted into systems, and suppliers working on different assumptions and to different standards. To address this, the Department told us it has now brought security issues together in one place, with one senior official responsible for overseeing this part of the programme.”

DWP response to PAC report

A Department for Work and Pensions spokesperson told the BBC

“This report doesn’t take into account our new leadership team, or our progress on delivery,” it said. “We have already taken comprehensive action including strengthening governance, supplier management and financial controls.”

The DWP said it did not accept “the write-off figure quoted by the committee” and expected it to be substantially less”.

A spokesman for Iain Duncan Smith told the BBC that he had “every confidence” in the team now running the programme, including Mr Devereux – whose position  some newspapers have suggested is under threat.

“Both the National Audit Office and the public accounts committee acknowledged a fortress mentality within the Universal Credit programme,” he said.

“Iain was clear back in the summer about how he and the permanent secretary took action to fix those problems.”

PAC report: Universal Credit: early progress

National Audit Office report: Universal Credit: early progress

More IT-based megaprojects derail amid claims all is well

By Tony Collins

If one thing unites all failing IT-based megaprojects in the public sector it is the defensive shield of denial that suppliers and their clients hold up when confronted by bad news.

It has happened in the US and UK this week. On the Universal Credit  project, the minister in charge of the scheme, Lord Freud, accepted none of the criticisms in a National Audit Office report “Universal Credit: early progress”.   In a debate in the House of Lords Lord Freud quoted from two tiny parts of the NAO report that could be interpreted as positive comments.

“Spending so far is a small proportion of the total budget … and it is still entirely feasible that [universal credit] goes on to achieve considerable benefits for society,” said Lord Freud, quoting the NAO report.

But he mentioned none of the criticisms in the 55-page NAO report which concluded:

“At this early stage of the Universal Credit programme the Department has not achieved value for money. The Department has delayed rolling out Universal Credit to claimants, has had weak control of the programme, and has been unable to assess the value of the systems it spent over £300 million to develop.

“These problems represent a significant setback to Universal Credit and raise wider concerns about the Department’s ability to deal with weak programme management, over-optimistic timescales, and a lack of openness about progress.”

And a shield of denial went up in the US this week where newspapers on the east and west coast published stories on failing public sector IT-based megaprojects.  The LA [Los Angeles] Times said:

As many as 300,000 jobless affected by state software snags

“California lawmakers want to know why Deloitte’s unemployment benefits system arrived with major bugs and at almost double the cost estimate. The firm says the system is working.”

The LA Times continued:

“Problems are growing worse for the state’s Employment Development Department after a new computer system backfired, leaving some Californians without much-needed benefit cheques for weeks.”

The Department said the problems affected 80,000 claims but the LA Times obtained internal emails that showed the software glitches stopped payment to as many as 300,000 claimants.

Now lawmakers are setting up a hearing to determine what went wrong with a system that cost taxpayers $110m, almost double the original estimate.

Some blame the Department’s slow response to the problems. Others point the finger at a Deloitte Consulting.

The LA Times says that Deloitte has a “history of delivering projects over budget and with problematic results”. Deloitte also has been blamed, in part, for similar troubles with upgrades to unemployment software in Massachusetts, Pennsylvania and Florida, says the paper.

“We keep hiring the same company, and they keep having the same issues,” said Senator Anthony Cannella.  “At some point, it’s on us for hiring the same company. It’s faulty logic, and we’ve got to get better.”

In 2003 California planned to spend $58m upgrading its 30-year-old unemployment benefits system. By the time the state awarded Deloitte the contract in 2010  the cost estimate had grown by more than $30m.

The Department handed out $6.6bn to about 1 million unemployed Californians in 2012. The software was expected to ease the agency’s ability to verify who was eligible to receive benefits.

Problems began when the Department transferred old unemployment data to the new system. The software flagged claims for review — requiring state workers to manually process them.

The LA Times says that officials thought initially the workload would be manageable, but internal emails showed the agency was quickly overwhelmed. Phone lines were jammed. For weeks, the Department’s employees have been working overtime to clear the backlog.

A poor contract?

In a contract amendment signed two months ago California agreed to pay Deloitte $3.5m for five months of maintenance and operations costs. Those costs should have been anticipated in the contract said Michael Krigsman, a software consultant who is an expert on why big IT-based contracts go awry. He told the LA Times:

“It’s a striking oversight that maintenance was not anticipated at the beginning of the contract when the state was at a much stronger negotiation position.”

By the time the middle of a project is reached, the state has no choice but to stick with Deloitte to work out bugs that arise when the system goes live, he said.

System works

Loree Levy, a spokeswoman for the Department, said the system is working, processing 80% of claims on time. As for the troubles, she said, “There is a period of transition or adjustment with any large infrastructure upgrade like this one.”

Deloitte spokeswoman Courtney Flaherty said the new California system is working and that problems are not the result of a “breakdown or flaw in the software Deloitte developed”.

System not working?

While there seems to be no project disaster in the eyes of the Department and Deloitte Consulting, some of the unemployed see things differently. One wrote:

“I am a contract worker who had to fight for my unemployment benefits. I won my case and yet they still cannot pay me… It’s been more than 3 weeks since I won my appeal and as of this moment, I am owed 13 weeks of back payments. To add insult to injury, they cannot send me current weeks to certify and they refuse to even try to help me to get back into the online system.

“I blame Deloitte, but it is California that carries the heaviest burden of fault… We’re nearing November and they still haven’t fixed an issue that began over Labor Day? Nonsense!

“This is untenable for everyone affected …We are owed reparations as well as our money at this point. It’s a funny word, affected. That means families and individuals are going hungry but can’t get food stamps or welfare. It means evictions and repossessed cars. It means destroyed credit, late fees, years of turmoil and shame for people already dealing with unemployment. Shame on you California.”

Another wrote:

“ … Not communicating is NOT an answer. Unemployed individuals caught up in the nightmare were told to be patient.  Rents and other expenses were still accumulating.  But [when you] add on additional fees: late fees, restoral fees, interest fees, etc…….you get the picture.

“Dear Governor Brown,

“Please reimburse me for all additional fees I’ve had to absorb to survive this fiasco.  You are going to make me payback any overpayments, but ignore the cost to the unemployed taxpayer.  This is  appears to unfair.  Perhaps Deloitte should pay us back from their contracted funds before they receive their final payment.  I am saving all of my receipts to deduct from my 2013 tax return.

“BTW Gov Brown – I am still waiting on additional payments as of today and DMV registration for my vehicle was due on 10/20/13.  Are you going to waive the penalty for late payment? Am I the only one with this question?”

Scrutiny

California’s state Assembly has set a date of 6 November 2013 for a hearing into the Department’s system upgrade.

“We’re going to look at EDD, the contractors and others to see how the system broke down so we can avoid this in the future,” said Henry Perea, chair of the Assembly’s Insurance Committee, which has oversight over the jobless benefits program.

On its website Deloitte says:

“Deloitte continues to help EDD [Employment Development Department] transform the level of service it provides to unemployed workers and improve the quality of information collected by EDD. The next time unemployment spikes, California should be ready to meet the increased demand for services.”

Massachutsetts IT disaster?

On the opposite coast the Boston Globe reported on an entirely separate debacle (which also involved Deloitte):

          None admit fault on troubled jobless benefits system

“… even with the possibility that unemployed workers could face months more of difficulties and delays in getting benefits, officials from the Labor Department and contractor, Deloitte Consulting of New York, testified before the Senate Committee on Post Audit that the rollout of the computer system was largely a success.

“‘I am happy with the launch,’ said Joanne F. Goldstein, secretary of Labour and Workforce Development, noting that she would have liked some aspects to have gone better.

“Mark Price, a Deloitte principal in charge of the firm’s Massachusetts business, acknowledged that software has faced challenges during the rollout, but insisted, ‘We have a successful working system today. ‘’’

NPfIT shield

A shield of denial was up for years at the Department of Health whose CIOs and other spokespeople repeatedly claimed that the NPfIT was a success.

Comment

If you didn’t know that Universal Credit IT wasn’t working, or that thousands of people on the east and west coasts of the US hadn’t been paid unemployment benefits because of IT-related problems, and you had to rely on only the public comments of the IT suppliers and government spokespeople, you would have every reason to believe that Universal Credit and the jobless systems in Massachusetts and California were working well.

Why is it that after every failed IT-based megaproject those in charge can simply blow the truth gently away like soap bubbles?

When confronted by bad news, suppliers and their customers tend to join hands behind their defensive shields. On the other side are politicians, members of the public affected by the megaprojects and the press who have all, according to suppliers and officials, got it wrong.

Is this why lessons from public sector IT-based project disasters are not always learned? Because, in the eyes of suppliers and their clients, the disasters don’t really exist?

None admit fault on troubled jobless benefit system

State fired Deloitte

Complaints continue despite claims system is under control

As many as 300,000 affected by California’s software problems

California’s predictable fiasco?

Does outsourcing make corruption more likely?

By Tony Collins

Few journalists want to write about corruption in local government unless they have specific evidence from a court case. Which helps to explain why a well-researched report on the subject last week attracted little mainstream publicity, although there was a piece in the Professional section of The Guardian .

Journalists assume, perhaps like many people, that local government doesn’t have a problem with corruption. But by its nature a subtle exploitation of the opportunities provided by a lack of oversight and accountability – at worst indifference – will remain hidden.

Who would say anything to the police – and if the police were informed would they act? – if officers or councillors shaped policy or a decision in favour of a certain company, with a view to opening up a path to future employment? Could such subtle deviance be proven?

“The temptation might be exacerbated by the risk of redundancy, providing a greater incentive for officers to use their position to build a network with a view to future employment,” says last week’s report Corruption in UK local government – the mounting risks.

The report was not written by a marginal organisation. It was researched and drafted for Transparency International by Elizabeth David-Barrett, Research Fellow at Said Business School and Director, Corruption and Transparency Research Centre, Kellogg College, Oxford University. Funding was from the Joseph Rowntree Charitable Trust.

Transparency International defines corruption as the abuse of entrusted power for private gain. David-Barrett says a disturbing picture emerges of conditions in which corruption is likely to thrive, what she calls:

“low levels of transparency, poor external scrutiny, networks of cronyism, reluctance or lack of resource to investigate, outsourcing of public services, significant sums of money at play and perhaps a denial that corruption is an issue at all”.

High standards in public life are the norm but David-Barrett notes that a “feature of researching this report has been the lack of agreement among the many experts we consulted about the scale and prevalence of corruption in UK local government”.

Some argued that the cases that have come to light represent the tip of the iceberg. Others said the small number of obvious corruption cases, and their disclosure by existing oversight structures, indicated there was no iceberg.

The report makes no comment on current levels of corruption but points out that, by its nature, it will usually remain hidden. Corruption in local government does exist, says the report, and it gives a few examples that have been publicised.

Outsourcing

“If local authority employees abuse their access to insider information or their ability to shape policy or contracts whilst in office in order to create opportunities for themselves, their friends, or for private-sector companies for which they will later work, this is corrupt,” says the report.

Such corruption could manifest itself in poor services and value for money. It may shut out companies of unquestionable integrity that could offer better deals.

That said, some suppliers may be concerned about the risks to their reputation of hiring through the revolving door. One unnamed interviewee quoted in the report says:

“We’ve been approached by individuals who are retiring from local government but don’t want to stop working. They come to us and say they can help us, they have a lot of experience. We look at it very carefully and err on the side of caution if we are going to be working with that council.”

But another interviewee is quoted in the report as saying

“There are situations where local authority staff end up working for contractors and implicit agreements to scratch backs in return for contracts will arise.”

The report claims that a council officer who had written the specification for a tender for a particular contract resigned from the council and successfully bid for the contract as a private-sector supplier.

Undue influence

“Research conducted for this report suggested that revolving-door type corruption is difficult to prove, but may not be uncommon and is certainly creating suspicions which, in themselves, undermine public confidence.”

Change requests

An interviewee is quoted in the report as saying

“…the number of variations – that’s where people make money. The profit is often determined by the award of work under the framework contracts, particularly where the pricing basis is not clearly defined, so that you can end up with charging for extra work by hourly rates.”

Another interviewee said

“The sharp operator in terms of the outsourcing contractor company will have agreed a contract based on a lump sum, invariably based on a local authority which, at the time that the contract was let, was much larger.

“If you have a company which provides HR, IT and admin, where can it make its savings? If they are prepared to make the investment, they can usually make significant savings for themselves, that’s where they are legitimately making some of their profit, but if the local authority has downsized over the years, then there is less to provide.

“So if it’s a 20-year contract, every 5 years there is a review and renegotiation based around head count. But normally councils are not very good at negotiating soft-side deliverables.”

The report says that corruption can arise if favoured sub-contractors are not held accountable, or the use of sub-standard goods is overlooked, or if a corrupt company and corrupt supervising official collude to agree on price increases or changes in specifications.

“There is a key weakness in the governance of this area because the contract implementation phase is often managed by the local authority department which uses the procured goods or services, rather than by the central procurement function. This department may be unaware of the precise terms of the contract and may not notice if corners are cut.”

A procurement expert is quoted in the report as saying

“There might be a disconnect between a procurement department that does this first part [pre-tender and tender] and the ‘client’, for example, the council’s IT dept. It is the IT department that is supposed to monitor the contract, and see how it is performing, but the disconnect reduces accountability. The supplier might be able to provide sweeteners to the IT department to re-negotiate the contract without going back through the procurement department.”

Another procurement specialist said that relatively few resources are devoted to contract management.

“The central functions in local authorities often focus on contract letting and not contract management. Many of the same skills are involved, but less [sic] resources are devoted to contract management. And departments are often left to manage contracts – raising risks not just of corruption but also of inefficiency.”

Does outsourcing reduce accountability?

“When services are outsourced, local authorities retain a statutory obligation to ensure that all of the rules that would have applied to them are equally followed by the external providers. However, the extent to which that obligation is fulfilled varies… there are concerns that local government officers do not adequately monitor contract performance or respond to complaints. Councils sometimes seek to claim that decisions made by contractors on long-term contracts are beyond their control.

“Without the Audit Commission to exert pressure and with the decline of local investigative journalism, there is a risk that corruption in this area will become more common.

“The Institute for Government’s 2012 report, Commissioning for Success, argues that decisions about when to outsource need to be made on a more robust basis, that monitoring and stewardship of outsourced services needs to be strengthened, and that accountability arrangements need to be clarified.”

Auditors enfeebled?

The report says

“The system of checks and balances that previously existed to limit corruption has been eroded or deliberately removed.

“These changes include the removal of independent public audit of local authorities, the withdrawal of a universal national code of conduct, the reduced capacity of the local press and a reduced potential scope to apply for freedom of information requests. We have identified 16 areas in which we find a marked decline in the robustness of local government to resist corruption…”

The lack of independent audits is a particular concern. Audits are carried out by companies that can be sacked if they’re too critical.

“We believe that the new system – in which local authorities themselves are solely responsible for awarding their audit contracts and where there is no back-stop support for auditors who are challenging the local authority – will narrow the scope and effectiveness of local audits, while increasing potential conflicts of interest…”

External auditors risk being sued if they try to highlight suspected corruption in a report, even if they have the appetite to do it “which is less likely given their commercial priorities and the expected relative reduction in the scope of audits”.

The report goes further and says that external auditors “may face incentives to avoid undertaking investigations or raising concerns about suspicions of fraud or corruption”.

Audit professionals interviewed for this report saw these as serious concerns. One commented, “If you come down tough on a client, and it creates ruffles, you’ve got an eye to what will happen when it goes to open competition.”

Another said “external auditors now have nominal independence but they will probably feel pressure to keep their clients happy so as to avoid losing this contract, future contracts, or non-audit contracts with the local authority.”

Risks

Particular risks of corruption include:

1. public procurement at needs assessment stage;

2. public procurement at bid design stage;

3. public procurement at award stage;

4. public procurement at contract implementation stage;

5. control and accountability over outsourced services;

6. the revolving door of personnel between local authorities and private companies bidding to provide services;

7. planning discretion and influence regarding ‘permissions to build’ decisions;

8. planning discretion and influence regarding ‘changes of use’ decisions;

The report says:

“We feel it is important to emphasise, as has been noted in a number of public consultations and inquiries, that the majority of local councillors and council officers observe high standards of conduct and very few misuse their positions to further their own ends.

“There is no substitute for a commitment to ethics and integrity in public service. However, when accountability is absent, public officials may exercise their power for private ends unchecked by scrutiny, complaint, or the threat of punishment.

“Clear opportunities exist for unethical officers and members to exploit public trust for private gain. In any sector, corruption tends to increase as oversight and enforcement are weakened…

“Irrespective of how much corruption currently occurs, we believe that under the new and proposed arrangements for local government, corruption is likely to increase and there will be less reporting of that corruption.”

Media enfeebled?

The report says there is little scrutiny of local authority work by a “largely emasculated local media”; and the ballot box “provides only feeble discipline given that turnout is low and in many areas one party dominates or seats go uncontested”.

Corruption scandals over the years have revealed that individuals are sometimes able to capture local politics, exercising informal power over the local party and their political group as well as council officers, “so that they can shape policy to serve their own interests unchallenged by their peers”.

Countering corruption

The report highlights a need for:

–  Effective assessment of corruption risks;

–  Independence of the units or authorities whose duty is to prevent or investigate corruption;

–  Visible and effective whistleblowing mechanisms.  “Whistleblowing has been more effective than audit, internal monitoring, or police investigations in revealing corruption in local government … Suitable mechanisms should be established to provide an easy-to-use and confidential channel for reporting corruption suspicions or incidents.”

– The institutional will to mount effective investigation and prosecution of corruption;

– A nominated individual in every local authority who is responsible for counter-corruption and who conducts a regular corruption risk assessment and liaises closely with law enforcement authorities.

– Strong sanctions implemented against those who are caught – both legal and other;

– A commitment to transparency.

– Firms providing an audit function for local authorities not being allowed to provide other commercial and consultancy services to the same local authority.

–  Internal investigations being adequately resourced and sufficiently independent. “Internal audit teams are vulnerable to manipulation by the corrupt, and this vulnerability increases if they are under-resourced, unsupported by the leadership or have their terms of reference and freedom to investigate curtailed.”

– Strict procedures requiring officers always to report (i) major price discrepancies among procurement bids and (ii) details of contract variations to the council’s Audit Committee and senior management.

– Greater monitoring of elected officials’ interests

–  Private companies, when operating services in the public interest, to be required to comply with the Freedom of Information Act with regards to those services. Specifically audit reports from local authorities should be covered under the Freedom of Information Act or published directly as public documents.

Thank you to openness campaigner Dave Orr for drawing my attention to the Transparency International report.

Comment

Lack of firm oversight, and a tolerance of bad practice contributed to the financial crisis of 2007/8. It was normal to give mortgages to people who had no means of paying them back. Only when the crisis became manifest did people realise that what had been regarded as normal behaviour was in fact deviant.

Is there a danger of tolerance in local government to aberrant behaviour such as the shaping of policy to favour outsourcing which could later benefit some individuals?

Those who claim corruption hardly exists can point to the strong ethos of public service in many councils – and indeed countless councillors do important public work for very little money – but that doesn’t remove concerns about what may remain hidden.

Transparency International’s report rings alarm bells. It points out that auditors, the media and whistleblowers are unlikely to expose deviant practices, and are even less likely to in the future. The report suggests that local government provides unprecedented opportunities for corruption.

“The accomplice to the crime of corruption is frequently our own indifference.”  – Bess Myerson, columnist. 1974.

Corruption in UK local government – the mounting risks.

NPfIT central costs rise by tens of millions – even after “dismantling”

By Tony Collins

On 22 September 2011 the Department of Health announced the dismantling of the NPfIT. As the press release was being issued some officials at the department were aware that they were continuing to spend tens of millions on central administrative costs of the programme.

Today’s report of the Public Accounts Committee has a figure for the central costs of the NPfIT until the end of March 2012 of about £890m. Before the DH announced the dismantling of the programme, in March 2011, the DH put the central costs at £817m.

So there has been a rise in central admin costs of about £70m since the NPfIT was supposedly dismantled.

The administrative costs are separate from spending on the contracts with BT or CSC. The admin costs don’t include the delivery of a single laptop to the NHS under the NPfIT. They are simply the central costs of administering the programme – including day rates for consultants – such as day rates of £1,700 to help senior officials prepare for appearances before MPs on the Public Accounts Committee.

The central costs have never been explained, not even by the National Audit Office which has published several reports on the NPfIT.  It is known that some central costs are explained by items of questionable benefit such as the commissioning of DVD films that marketed the NPfIT.

Some of the cost categories have emerged as a result of an FOI request (below).  Officials made regular visits to various parts of the globe to promote the success of the NPfIT. It’s thought that the DH has spent more than £100m on consultants for the programme.

Millions of pounds have been spent with public relations companies. The DH spent about £30,000 on press cuttings in two years alone.  Released central costs for just two years of the NPfIT between 2005 and 2007 include:

  • £1.23m with Expotel Hotel Reservations
  • £1.87 Harry Weeks Business Travel
  • BT conferencing – £1.15m
  • Intercall video conferencing – £274,973
  • MWB (Serviced Offices) – £15.8m
  • Regus – offices and meeting rooms – £3.17m
  • Spring International Express (courier and other services) – £192, 662
  • Cision UK (press cuttings) – £30,000
  • Fishburn Hedges (includes public relations) – £559,310
  • Good Relations (public relations] – £1.55m
  • Porter Novelli (public relations and information) – £943,000
  • ASE Consulting – £31.7m
  • Capgemini – £15m
  • Deloitte MCS – £42.8m
  • Atos Consulting – £32.3m
  • Gartner – £3.8m
  • QI Consulting – £14.5m
  • Tribal Consulting – £6.9m

Comment

Central administrative costs of nearly £900m on a single IT programme are breathtaking. That makes the National Programme for IT in the NHS one of the world’s largest public sector IT projects – before a penny has been spent on deliveries of hardware or software to the NHS.

It’s almost as surprising that not even the National Audit Office has been able to obtain a breakdown. Has central spending been properly controlled? Perhaps not, given that the DH, even this year, spent up to £1,700 a day on consultants to brief a senior official for a hearing of the Public Accounts Committee in June 2013.

Maybe the taxpayer should be grateful that the consultants were hired for only 52 days between February and June 2013 to prepare for the Committee’s hearing, and that the DH managed to renegotiate the day rate down from £1,714 to £1,000 a day between April and June.

Maybe the taxpayer should be grateful that the total cost of the consultancy for preparing for the PAC hearing was only £73,563.

But the £73,563 was spent after the DH estimated its central administrative costs on the NPfIT at nearly £900m – which are costs up to 31 March 2012.

It’s also remarkable that some at the DH still consider the NPfIT a success. This was the NAO’s conclusions on the NPfIT in its May 2011 report on the NPfIT Care Records Service:

“Central to achieving the Programme’s aim of improving services and the quality of patient care, was the successful delivery of an electronic patient record for each NHS patient. Although some care records systems are in place, progress against plans has fallen far below expectations and the Department has not delivered care records systems across the NHS, or with anywhere near the completeness of functionality that will enable it to achieve the original aspirations of the Programme.

“The Department has also significantly reduced the scope of the Programme without a proportionate reduction in costs, and is in negotiations to reduce it further still. So we are seeing a steady reduction in value delivered not matched by a reduction in costs.

“On this basis we conclude that the £2.7 billion spent on care records systems so far does not represent value for money, and we do not find grounds for confidence that the remaining planned spend of £4.3 billion will be different.”

But this was the Department of Health’s view on NPfIT Care Records Service value for money:

“The Department considers, however, that the money spent to date has not been  wasted and will potentially deliver value for money… The Department believes that the flexibility provided by the future delivery model for the programme will deliver functionality that best fits the needs of the clinical and managerial community. The future architecture of the programme allows many sources of information to be connected together as opposed to assuming that all relevant information will be stored in a single system. This approach has been proven in other sectors and is fully consistent with the Government’s recently published ICT strategy.”

This contradiction between the DH’s view of the NPfIT, and the NAO’s, indicates, perhaps, that the DH continues to live in a world not entirely attached to reality.

From April 2013, the DH’s central team and some local programme teams responsible for the NPfIT moved to the Health and Social Care Information Centre which has taken over the local service provider contracts with BT and CSC. Will it be able to control central spending on the very-much-alive NPfIT?

Update:

The central costs could rise much further – possibly by more than £100m – if the eventual settlement of the legal case between the DH and Fujitsu works out badly for the taxpayer. Legal costs on the case so far are about £31m.

MPs dig hard for truth on Universal Credit IT

By Tony Collins

“Just answer the question … please!”

Rarely has any chair of the Public Accounts Committee pleaded so frequently with a permanent secretary not go round the houses when answering questions.

Margaret Hodge’s irritation was obvious on Tuesday [9 September] at a hearing of the Committee into a National Audit Office report on the Universal Credit IT-based programme: Universal Credit: early progress.

Before the Committee was Robert Devereux, the top civil servant at the Department for Work and Pensions. Beside him was UC’s latest project director Howard Shiplee who successfully led and managed construction contracts, budgets and timelines for all permanent and temporary venues for the Olympics. He has a CBE for services to construction.

It’s unclear how much experience Shiplee has had with IT-based projects and dealing with IT suppliers, though given his success as a big projects leader and construction expert,  IT leadership experience may be unnecessary.

There were signs from the hearing that Universal Credit project is following the events that have typically preceded IT-related disasters in government, especially in the way facts were interpreted in opposing and irreconcilable ways by the project’s defenders on one side and the “independents” on the other.

The “independents”, whose criticisms of the project have been withering, include a director at the National Audit Office Max Tse who led the NAO’s inquiry into the UC programme, and Dr Norma Wood, who has held several relevant positions in recent months, first as review team leader for a UC review in February, then as Transformation Director for the UC programme “re-set” in May 2013 and then as Interim Director General for the Cabinet Office’s Major Projects Authority. She is a consultant, not a civil servant. She appeared before the PAC on Wednesday.

Another “independent” is the auditor and consultancy PWC which reported to the government on financial mismanagement on the UC project. The NAO revealed the existence of the PWC report, which Hodge said was even more damming the NAO’s. [see separate blog post.]

A possible outcome of deeply conflicting views on the success or otherwise of a big and controversial project is that truth remains beyond anyone’s grasp within the life of the project and emerges only within the scheme’s post mortem audit report.

At Tuesday’s PAC hearing, the evidence given by Devereux and Shiplee on one hand, and Wood on the other was at times conflicting.

Wood’s evidence

Wood said that one of the lessons from the Universal Credit programme so far was that it was not conceived as a business transformation but was “very IT driven”. Of the £303m that has been spent on IT so far a sizeable part will need to be written off, beyond the £34m write-off so far.

Conservative MP Richard Bacon asked her how much could eventually be written off on the IT spend. “I think it will be substantial. I could not give you a figure,” she said.

When Bacon asked if it could be more than £140m she replied: “It will be at least that I would think.”

Her answer implied that the DWP will need to write off a large part of the £162m it currently estimates its IT assets are worth, after the £303m IT spend. Hodge said the write-off could be in excess of £200m – but this was later denied by Devereux, who also denied the write-off would be at least £140m.

Wood revealed that the figure for the write-off so far was derived from information given by suppliers, after the DWP asked them to judge how much of their equipment and software would be of use.

Conservative MP Stephen Barclay asked Wood whether suppliers were assessing the usability of their own work.

“Yes they were,” replied Wood.

Barclay: “So they were marking their own homework?”

“Yes they were.”

“Does that not carry a conflict of interest?”

“Yes it does.”

“Does it concern you?”

“It did,” replied Wood. “Therefore in the review we recommended an independent investigation.”

Barclay: “Building on Mr Bacon’s point, it is highly likely that with the initial write-off, if they have been marking their homework, comes a risk that the eventual figure is going to be bigger?”

“That’s true.”

Barclay’s questioning will indicate to some that the DWP and its IT suppliers were so close it could have been difficult for the department’s officials to be objective about what they were being told.

Steady-state solution

Wood spoke of how DWP and the Major Projects Authority had designed a “steady-state solution” which was a simplified version of UC , from which a more comprehensive system could be developed.

Said Wood: “There is a steady-state solution … with business requirements, that was handed over to the SRO [senior responsible owner] on 17 May, so there is a complete design and there is a multidisciplinary team working that design through to the next level.”

She said the steady-state solution is twin-tracked. “There is a piece that designs the interactive activity with the user and with the agents, and there is a part that uses existing systems, such as the payment system and the customer information system, but there are some 32 legacy systems in between, the utility of which we did not know at the time we completed the reset on 17 May.”

The interactive part is managed by a multi-disciplinary team that involves the GDS [Government Digital Service] and used agile, with waterfall for legacy systems.

“So yes, there is a design, and it is a very good design.”

On the use of agile she said the important thing is to apply rigour and discipline as you go through those methodologies. “It is not an issue of methodology; it is an issue of the rigour and discipline that is applied to those approaches.”

Pathfinder

Instead of a national roll-out starting in October, which was the original plan, the DWP is running “pathfinder” projects which accept only simplified claims and use limited IT without full anti-fraud measures.

Wood said: “It [the pathfinder scheme] is not hopeless. As it was currently configured there was a limit to the volume of payments it could handle because of the manual interfaces required – the manual support it required. So there is a very limited number of cases it could handle …”

Bacon asked if she would describe the pathfinder as so substantially de-scoped it was not fit for purpose.

“At the time we did the review [earlier this year] that was our conclusion.”

“ Is it correct that the pathfinder technology platform will not support UC in the future – that it is not scalable?” asked Bacon

“Unless it can handle all the functionality we have just described I fail to see how it can be scalable,” replied Wood.

Lessons

Liberal Democrat MP Ian Swales said: “We have exactly the same names of suppliers failing to deliver on government contracts time after time. Poor specifications, very vague penalties involved, and a sense that they have a vested interest, almost, in failure and we are again sat around this table discussing the same sort of thing. What can be learned?

Wood replied that there are some important lessons. “One is that this is not just a procurement exercise; this is actually a contract management exercise. It is really important that one understands what the business needs to deliver. That is why I stress that this was constituted not as a business transformation programme, but as an IT programme. It is important that the business drives the IT requirements and manages the contracts accordingly.”

Is 2017 feasible?

Wood: “It is feasible to deliver the whole thing by 2017.”

Bacon pointed out that there is no approval for further spending on UC until November 2013 and only then if criteria is met. He asked Wood on what basis approval for more spending would be given. Wood said it will be based on whether the project is affordable, value for money, deliverable within timescales, and has the appropriate management place.

DWP’s evidence

Hodge complained repeatedly that the civil servants before her were not answering questions directly – perhaps a sign of how hard it can be to establish the truth when an IT-based project goes awry.

“I would be really grateful if you would answer the question,” asked Hodge when questioning Devereux about whether Universal Credit had a proper business plan, a strategy.

At another point Devereux said: “Let me try and answer these questions which have been bandied around.”

Hodge: “You do go round the houses. Just answer them directly.”

Later in the hearing:

Hodge: “What you are so good at is giving us a whole load of stuff that is completely irrelevant to what we are trying to get at. Just answer the question.”

And another occasion…

Hodge: “No just answer the question … please.”

And again …

Hodge: “What would be utterly delightful is if you simply answered the questions. Just answer the questions.”

Again …

Hodge: “I just don’t get where this is going. I am honestly trying to be fair to you today. Ask the question again Meg [Meg Hillier MP] and then see if we can get an answer.” [Hillier’s question was about why the DWP has treated Universal Credit as an IT project instead of what it actually is, a business transformation programme which changes the way people work and act rather than introduces new technology. Devereux gave no clear answer.]

An exchange about the UC’s pathfinder projects characterised the relationship between Hodge and Devereux. Critics of the pathfinders say they are pointless because the claimants are atypical, much of the claims process relies on manual work, the technology is largely without any agreed anti-fraud measures, and it cannot yet handle everyday circumstances.

Supporters of the pathfinders, particularly Devereux, say they are a useful step in assessing the behaviour of people when making claims and testing the interfaces between new technology and the DWP’s legacy systems.

Hodge: “You are not answering any of the questions Mr Devereux. I don’t mind a little bit of history and a little bit of what you want to say but answer the questions. Do you think the pilot was fit for purpose – yes or no?”

Devereux: “The pathfinder is testing useful things that we have fixed.”

Hodge: “Was it fit for purpose?”

Devereux: “It has been useful.”

“Was it fit for purpose?”

“What purpose did you have in mind?”

“No – you.”

“Ok well, for my purpose it has worked fine thank you. “

“To do what?”

“To make sure I can construct some brand new software to connect it to a –“

“On which you spent £300m …”

“To connect it to a very complicated legacy estate and then demonstrate all of those things – let me give you one example; we will not get anywhere otherwise. I have sat in front of this Committee and we have talked about the Work Programme. You have grilled me on the—

“Please don’t talk about the Work programme.”

“In that conversation—

“Please talk about the pathfinder…”

And subsequently …

“Can I really plead with you, if you can answer questions without going off on a sideline it would be really really helpful – really really helpful.”

MPs kept uninformed

Stephen Barclay put it to Devereux and Shiplee that the DWP was aware of serious UC problems in July 2013 but the public, media and Parliament were being given the impression all was well. Said Barclay: “In July you realised there were problems. In September [2013] your Department’s press office was telling Computer Weekly:

‘The IT is mostly built. It is on time and within budget.’

Barclay said in July 2013 Shiplee was asked by the chair of work and pensions select committee[Dame Anne Begg]: “So rumours that there is a large chunk of the IT that simply do not work and has been dumped are not true?”

“No,” replied Shiplee.

Barclay told Devereux and Shiplee: “Parliament seems to be getting told two different things.” He referred to the DWP’s “culture of denial”.

IT supplier reassurances

Shiplee said he has spent 12 of the 16 weeks since he started reviewing the UC project in great detail with IT suppliers.

“That is something that hasn’t been done to this level before. I have spent with experts from within DWP and with external experts and we have reviewed in detail what has been produced, what works, where it has got to. There are a number of points to make –

Barclay: “Could you clarify you wrote to the chair of the DWP committee to clarify that answer if you have done further work …”

Shiplee: “I have not concluded the work. I believe that from that work already, it is my view, supported by reports, that there is substantial utility in what has been produced… The use of agile is by itself very iterative and therefore to a certain extent it is potentially high risk.

“I wanted to look at how we could de-risk this, this utilisation of agile, and one of the ways to do that is to look at what we have already spent a great deal of money on, and whether it was usable and would actually serve to de-risk the programme…

“What I have discovered is that the Pathfinder does not represent the amount of development work that has been undertaken by suppliers. It [Pathfinder] has been heavily de-tuned from where they have actually got to.”

Why?

“Mainly around security, said Shiplee. “This is a unique piece of work. It [the DWP] is the only bank anywhere – effectively a bank – in which customers do not put money it. They simply take money out. It is therefore attractive from all sort of fraud point of view and therefore security is very important. The key element of security is personal identification. Nobody has yet found a way to do that effectively and totally online.”

Hodge: “Are you telling us that the technology developed so far is capable of being scaled up for a national roll-out?”

Shiplee: “On the basis of what I have been told and what I have seen so far, I believe it has been demonstrated that the suppliers have got the capability to scale this up. They have, for example, dealt with couples [Pathfinder system deals now only with single people.]

“The suppliers have explained where they have got to. It is very interesting. Some of the challenges we are facing now the suppliers have already faced in the past and have resolved those issues. I am trying to make sure that we use all of this to the best good and we don’t have to relearn every lesson again.”

Replaced project leaders

Devereux told of how he had replaced project leaders who , he suggested, were not solving problems but pushing ahead regardless, and were not good listeners.

“People I put in place here had experience and confidence. The challenge they had was very large and there came a point in my judgment they were no longer on top of it. There were cumulative issues to be resolved.

“When the cumulative bow wave of things that had not been resolved was being called out as not resolvable by just pushing on through, that is the point at which we decided to change, because it was also then that the point the Chair made about a good news culture within the programme was crystallising. Those two things cannot work.

“I need people who will drive things through. Howard is very good at driving things through, but the person that drives things through and does not listen to anyone at all is not going to help me at all.”

Comment

Last week James Naughtie on BBC’s R4 Today programme, R2’s Jeremy Vine, journalists at the BBC World Service and at other news services asked me whether Universal Credit was another government IT disaster. I said in essence that it was a good idea badly executed. The IT project has been dogged by an over-ambitious timetable, poor control and validation of supplier payments and a good news culture that to some extent still exists.

In past government IT disasters such as the NPfIT, C-NOMIS and the Rural Payments Agency’s Single Payment Scheme, ministers were not given bad news until it could be hidden no longer. Senior officials gave ministers only good news because that’s what they wanted to hear.

Deniability

Civil servants, perhaps, wanted to give ministers credible “deniability”. The less ministers knew of serious problems the more credibly they could deny in public the existence of them.

Thank goodness, then, for the scrutiny of the National Audit Office and the Public Accounts Committee on Universal Credit. Some important truths have now come to the surface. With the NAO and the Cabinet Office’s Major Projects Authority rightly breathing down its neck, the DWP is doing all it can to put the project back on track. But the DWP is still marred by a good news culture. Even after the NAO and PWC reports the DWP’s press office is still talking of the Universal Credit project as a success.

A DWP spokesperson told the Guardian this week:

“The IT for universal credit is up and running well in the early rollout of the new benefit.”

And Iain Duncan Smith and his senior officials appear to be dismissing the NAO’s report as historic – which it is to some extent – but much of it is also forward-looking.

Duncan Smith, Devereux and Shiplee are all very positive about the future of the project. But would it be better if they were genuinely sceptical, as would be a private sector board that was confronting a big and challenging IT-enabled change project?

Politics and IT don’t go well together and never have. There is every chance Universal Credit will follow what has happened with the last huge benefit computerisation project, Operational Strategy in the 1980s. It eventually worked but in a much more fragmented way than expected. It was several years late, cost several times the original estimate, and did not make the savings predicted. The likely fate of Universal Credit IT?

Learn from failure: the key lesson that Universal Credit should take from agile [Institute for Government]