Category Archives: capacity building

How CIOs and IT suppliers view GovIT change

By Tony Collins

CIOs and IT suppliers give their views on Government ICT in an authoritative report published today by the Institute for Government

Inside the wrapper of generally positive words, a report published today on government ICT by the Institute for Government suggests that major change is unlikely to happen, despite the best efforts of  CIOs and the Cabinet Office minister Francis Maude.

The report “System upgrade? The first year of the Government’s ICT strategy”  says progress has been made. But its messages suggest that reforms are unlikely to  amount to more than tweaks.

These are some of the key messages in the report:

If the minister and CIOs cannot direct change who can?

–          “… while the Minister for the Cabinet Office and government CIO are viewed as being responsible for delivering the ICT strategy (for example by the Public Accounts Committee) they currently lack the full authority to direct change.”

Not so agile

–           “While just over half of government departments may be running an agile project, there were concerns that these were often very minor projects running on the fringe of the departments.”

–          “We heard concerns from the supplier community and those inside government that in some areas projects may be being labelled as ‘agile’ without having really changed the way in which they were run.”

–          “CIOs should question whether they are genuinely improving the ways that they are working in areas such as agile, or whether they are just attaching a label to projects to get a tick in the box,” says the Institute for Government.

Savings not real?

–          “There was also an element of challenge to the savings figures provided by government. For example, some from government and the supplier community questioned whether the numbers represented genuine savings or just cuts in the services provided or deferred expenditure. “

–          “Others … cautioned that project scope creep or change requests could reduce actual savings in time. It was pointed out that the NAO [National Audit Office] will scrutinise whether savings have been achieved in future, which was seen as a clear incentive for accuracy – but there were, nonetheless, concerns that pressure to provide large savings figures meant that inadequate attention might be paid to verifying the savings …”

CIOs want faster ICT progress

–          “Among the CIOs we interviewed, there was a clear recognition that government ICT needed to improve.  ‘You expect an Amazon experience from a government department…’ ”

Lack of money good for change

–          “As one ICT lead noted, a lack of money was ‘always helpful’ in driving change as it promoted cross-government solution-sharing and led to more rigour in approving new spend.”

–          “Both ICT leaders and suppliers felt that the ICT moratorium had been a helpful stimulus for increased focus on value for money.”

–          “Though some of the larger suppliers felt bruised by the ‘smash and grab’ of initial interactions with the Coalition government, there was a recognition that the moratorium had been about ‘stopping things which were inappropriate’”.

GDS challenges norms

–          “New ways of working in the new Government Digital Service and the opening up of government through the Transparency agenda were also seen as providing a challenge to existing norms.”

–          The new Government Digital Service (GDS) is providing an example of a new way of doing things, and was pointed to by those inside and outside of government as embodying mould-breaking attitudes, using innovative techniques and … delivering results on very short timescales. Several interviews mentioned being invigorated by the positive approach of the GDS and their focus on delivering services to meet end-user needs.

ICT so poor staff circumvent it

–          “Public servants are increasingly frustrated that the ICT they use in their private lives appears to be far more advanced than the tools available to them at work. Indeed, there are already examples of employees circumventing the ICT that government provides them as they attempt to perform their job more effectively: creating what is known as a system of ‘shadow ICT’ that creates significant challenges for maintaining government security, collaborative working and government knowledge management.”

Joined-up Govt impossible?

–          “The possibility that departmental incentives continue to trump corporate contributions is further suggested by our survey results. Individuals do not yet feel that corporate contributions are valued or rewarded … elements of the [ICT] strategy call for departments to give up an element of autonomy and choice for the ‘greater good’. Several CIOs expressed concerns that by adopting elements of the strategy that were being developed or delivered by another department, they would end up having to accept a service that had been designed  around the needs of a different department.”

–          “Similarly, there were concerns that the host department would be at the top priority in the event of any problems or opportunities to develop services further. This speaks to a strongly department-centric culture. Suppliers noted, for example, that certain parts of government were still happy to ‘pay a premium for their autonomy’.”

–          “… the vast majority of those we spoke to suggested that departmental interests would almost always ultimately trump cross-government interests in the current government culture and context.”

–          “CIOs felt that they would be rewarded for delivery of departmental priorities – not pan-government work …”

CIO Council frustrations

“CIOs noted that there could be a discrepancy between what got agreed at the old CIO Council meetings and what people actually went away and did. Larger department CIOs also expressed frustration that – despite holding the largest budgets and carrying the largest delivery risks – their voices could easily be outweighed by the multitude of other people round the table.”

“The delivery board model [which has superseded CIO Council] has been recognised by both big and small departments as pragmatically dealing with both sides of this issue. Larger departments now form part of an inner-leadership circle, but with this recognition of their clout comes additional responsibility to own and drive through parts of the strategy… the challenge will now be to ensure that the ICT strategy doesn’t become a ‘large department-only’ affair and that other ICT leads can be effectively engaged.”

Canny suppliers?

–          The majority of ICT leads …stated that they believed the ICT strategy would benefit their department and government as a whole. This confidence was less apparent in the attitudes of suppliers who were, on the whole, more sceptical of government’s ability to drive change, though again generally supportive of the direction of travel.

A toothless ICT Strategy is of little value?

–          “…There was also a lack of clarity on how different elements of the [ICT] strategy would be enforced. As one ICT leader commented … ‘Is this a mandatable strategy or a reference document?’ ”

–          … “there are risks that the strategy could be delivered in a way that still doesn’t transform ICT performance.”

Francis Maude an asset

–          “Government ICT has also been a priority of the Minister for the Cabinet Office, Francis Maude – giving the [change] agenda unprecedented ministerial impetus. He has been a visible face of ICT to many inside and outside of government, from demanding departmental data on ICT to being heavily involved in negotiations with ICT suppliers. Though few of his ministerial colleagues appear as passionate about improving government ICT, the CIOs we interviewed overwhelmingly expressed confidence that they would receive the support they needed to implement the changes in ICT.”

Smaller-budget CIOs out of the loop?

–          “With the CIO Council in hiatus for most of the last year, the CIOs of smaller departments felt out of the loop …”

Most ICT spending is outside SW1

–          “Suppliers and other ICT leaders pointed out, rightly, that the vast majority of ICT expenditure happens outside SW1 – with agencies, local government and organisations like primary care trusts and police forces still determining much of the citizen and workforce experience of ICT.”

SMEs still left out?

–          “Smaller suppliers … were generally encouraged that government was trying to use more contractual vehicles which would be open to them – but noted that it was ‘still extremely difficult to get close to government as an SME’.”

Who knows if use of ICT is improving?

–          “Government still lacks the information it needs to judge whether use of ICT across government is improving.”

System upgrade? The first year of the Government’s ICT Strategy.

Too early to claim success on GovIT – Institute for Government

Farewell to Ian Watmore – the antithesis of Sir Humphrey

By Tony Collins

A good insight into the departure of Ian Watmore comes from Peter Smith of Spend Matters who says:

 “He (Watmore) lives in Cheshire still (and does a weekly commute to London) and this seems to be driven by personal factors – he wants to do more non-executive stuff,  work with charities, education bodies, and support his wife who is being ordained as a vicar shortly.

“There will be a competition to replace him but Melanie Dawes (?) will be the interim Perm Sec.”

Watmore leaves in June at the height of his civil service career. It would be too easy to cite his background as UK Managing Director of Accenture to say that he came to the civil service with a sympathy for big suppliers and not upsetting the smooth-running of the government IT machine.

Indeed he will not go down in civil service history as a heavy-handed enforcer of central government reforms: he respects too much the work of senior civil servants and particularly CIO colleagues to be seen as an opponent whose will cannot be overcome.

Rather he has been an authoritative go-between, a pragmatist who has sought to implement the radical cost-saving measures demanded by the Cabinet Office minister Francis Maude without giving departments any excuse to cite central diktats as the reason for disruption to frontline services.

Watmore gave an insight into his relationship with Maude at a Parliamentary committee hearing earlier this year. His comments also exploded the myth that the private and public sectors can be run on comparable lines.

“I have been on both sides of the divide on private and public,” said Watmore. “The thing that is different about  the public sector is the combination of leadership from the ministerial class and the civil service class. There is no corporate analogue for it. People talk about the way it analogises to the business world—I don’t think it does; it is different…

“I work on a daily basis with Francis Maude. I am not going to make any political comments about Francis, but as a man I feel that he cares about what he is doing;  he knows his stuff and he drives us very hard. In response, I give, shall we say, robust advice in return. Mostly, he listens and sometimes I defer to him and we come back to the same place we started, but more often than not we flesh out the differences behind closed doors and then we come out on a united front. I think that is the best way to get civil service and ministerial leadership. If you have a weakness in one part or the other, the whole thing breaks down.”

At Campaign4Change we will remember Watmore’s career in the civil service for his openness, honesty and lack of ego.

When answering questions before Parliamentary committees, some permanent secretaries seem to see MPs as adversaries. These civil servants’ replies are characterised by clever, evasive or adversarial comments.  They apologise if the mistakes were before their time but usually they’re protective of their departments, as if defending their children against criticism by outsiders.

Watmore is the antithesis of the archetypal civil servant.  Whereas, for example, most civil servants want to keep confidential internal “Gateway” reports on the progress or otherwise of high-risk IT and construction projects, Watmore is on record as saying he would like them published (though they haven’t been).

And he has earned respect among MPs for his straightforwardness. He’ll speak lucidly on his department’s achievements, but not his own.

How much effect he has had on other departments is hard to gauge. It’s difficult to see how the most ruthless enforcer in the Cabinet Office could ever have much influence in other departments.

For though the Cabinet Office has powers from David Cameron to enforce cost-savings,  departmental heads remain accountable for their own decisions. Watmore has spoken of the tensions between the Cabinet Office and departments.  He told MPs earlier this year:

“There are lots of examples where we and Departments have common cause. There will be times when we challenge what they want to do and it can be a tense relationship. Sometimes we agree with what they were going to do anyway, and other times they agree with us, but it means that we are engaging with them.”

Chair: How well is it working on a scale of one to 10 … on the cross-departmental working?

Watmore: “On the whole cross-departmental working, I would say it is somewhere around the six or seven mark. There is more to do.”

Watmore shuns the trappings of high office.  He doesn’t even have an office. “I refuse to have one,” he told MPs this year. “I don’t believe in physical offices for managers. I hot-desk wherever I happen to feel it is appropriate to work that week…

“What I tend to do is I move around and I sit with a different group in the Cabinet Office for a week. Initially people think it is a bit odd having the Permanent Secretary sitting next to them but once you carry on as normal they realise you are just another person working there.

“You actually get to find out quite a lot about how the operation works by being there with the staff for a week as well as hearing from them in a more formal setting…

“It is how I operated when I was in business so it is a long-term way of working. But when I came into Government I discovered it by accident; when I wanted to move the staff from two different bits of Government into a new building and introduce flexible working, hot-desking and all the rest of it, I said, ‘If it is good enough for the rest of the staff, it should be good enough for me…’

Will Maude find someone authoritative and influential but without a big ego to replace Watmore at the top of the Cabinet Office? A difficult assignment.

Universal Credit: who’ll be responsible if it goes wrong?

By Tony Collins

When asked whether Universal Credit will work, be on budget and on time, Ian Watmore, Permanent Secretary, Cabinet Office, gave a deft reply. He told Conservative MP Charlie Elphicke on 13 March 2012:

“From where I sit today, I think all the signs are very positive. I am never going to predict that something is going to be on time and on budget until it is.”

If the plans do not fall into place who, if anyone, will be responsible? In theory it’ll be Iain Duncan Smith, the Secretary of State for Work and Pensions. But as Watmore told the Public Administration Committee, there are several other organisations involved. Although the DWP and HMRC are building the IT systems, the success of Universal Credit also relies on local authorities, which are overseen by the Department for Communities and Local Government.

There are also the Cabinet Office and the Treasury whose officials seek to “ensure that what is going on is appropriate” said Watmore.

If Univeral Credit goes awry all the departments may be able to blame the private sector: the employers that must pass PAYE information to HMRC so that the Revenue’s Real-Time Information element of Universal Credit can work.

David Gauke is the minister responsible for HMRC so would he take some of the blame if Real-Time Information didn’t work, or was not on budget, or was delayed?

Or would the main IT suppliers Accenture and IBM take any of the blame? Highly unlikely, whatever the circumstances.

There is also a dependency on the banks.

But nothing is wrong … is it?

All those putatively responsible for Universal Credit continue to say that all is going well.

Duncan Smith told the House of Commons on 5 March 2012:

“We are making good progress towards the delivery of universal credit in 2013, and I have fortnightly progress meetings with officials and weekly reports from my office. I also chair the universal credit senior sponsorship group, which brings together all Government Departments and agencies that are relevant to the delivery of universal credit.

“Design work is well under way and is being continually tested with staff and claimants, and the development of the necessary IT systems will continue in parallel.”

He said that universal credit will reduce complexity by putting together all the benefits that are relevant to people going back to work – though benefit systems that are not relevant to the coalition’s “Work programme” will not be included in the DWP’s Universal Credit IT consolidation.

To reduce risks Universal Credit will be phased in over four years from October 2013, each stage bringing in a different group of claimants.

But …

Campaign4Change has asked the DWP to publish its various reports on the progress of Universal Credit and it has refused, even under the Freedom of Information Act. It seems the DWP’s secretiveness is partly because all of the risks related to Universal Credit have not been mitigated. We will report more on this in the next few days.

Meanwhile to try and answer the question in our headline: who’ll be responsible if Universal Credit goes wrong? The answer is: the private sector probably. Or rather nobody in the public sector.

Can hundreds of millions be spent on Universal Credit in an agile way?

Universal Credit suppliers Accenture and IBM look to India for skills.

Is Universal Credit a brilliant idea that’s bound to fail?

Universal Credit latest

Universal Credit and the banks.

Shared services disaster: a gain for some officials and ERP suppliers?

By Tony Collins

Today an impressive report by the National Audit Office shows in detail how various shared services ventures in central government have, over time, cost rather than saved money.

Five shared services centres studied by the NAO have cost £1.4bn so far; they were supposed to have saved £159m by 2010-11 but the net cost has been £255m. Setting up the centres since 2004 has been good, though, for some suppliers (and officials who wanted to gain new skills in Oracle and SAP enterprise resource planning systems).

The Cabinet Office has now intervened and plans a new shared services strategy, based on the DWP [Oracle v11i ERP) and Department for Transport [SAP ERP] offering independent major shared service centres to departments and agencies.

One of the urgent drivers for the Cabinet Office’s publishing a new strategy in July 2011 was that three shared service centres face an investment of £47m to upgrade their Oracle ERP systems before November 2013, says the NAO.

“The current version of Oracle will not be supported by the manufacturer past this date,” says the NAO. “This means that if their core system fails, there is a high risk that they would not be able to re-instate it quickly. This gave the Cabinet Office an opportunity to see if it could derive better value-for-money options for shared services.”

Saving £32m on Oracle upgrade costs?

The Cabinet Office expects its new plans to save £32m on Oracle upgrade costs, says the NAO. Indeed the Cabinet Office has questioned whether departments need to use large ERP systems. It acknowledges that smaller, simpler software solutions may be appropriate, says the NAO.

Civil servants in search of new ERP skills rather than saving money?

The NAO report hints that civil servants at the five service centres might have wanted to implement new Oracle or SAP ERP software more than to save money.

Says the NAO: “The [shared service] Centres have prioritised increasing the number of customers or implementing new software, rather than working with existing customers to drive efficiency… There are other options to reduce costs in addition to increasing the number of customers or implementing a new ERP system.”

Indeed the NAO questions why the service centres bought big and expensive ERP systems that are now under-used, without looking at smaller and simpler accounting packages.

“These ERP systems [installed at five shared service centres studied by the NAO] are complex and it is not easy to modify them when needs change, such as when an organisation is restructured or processes are redesigned.

“We found the Centres are only using a small part of the capability their ERP systems provide. The systems are capable of handling larger volumes of transactions and more services and it is not clear why such expensive solutions were bought. Other smaller and simpler accounting packages were not looked at to see if they may have provided the required functionality.”

Concludes the NAO:

The shared services initiative has not so far delivered value for money for the taxpayer. Since the Gershon Review recommended the creation of shared services in 2004, the Government has spent £1.4 billion against a planned £0.9 billion on the five Centres we examined.

“By creating complex services that are overly tailored to individual departments, government has increased costs and reduced flexibility. In addition, it has failed to develop the necessary benchmarks against which it could measure performance. The Cabinet Office has issued an ambitious new shared services strategy to address these issues.”

Failing to standardise ways of working

Shared services are about standardising ways of working, not running separate services for every client but the NAO found that the five centres replicated old ways of working.

“The services provided are overly customised. We found shared services to be more complex than we expected. They are overly tailored to meet customer needs. This limits the ability for the Centres to make efficiencies as they have an overhead of running multiple systems and processes.”

Big cheques to big ERP suppliers?

The NAO said departments have wasted money on ERP systems – and now plan to spend more on DRP systems.:

“The software systems used in the Centres have added complexity and cost. All the Centres we visited use Enterprise Resource Planning (ERP) software systems. These are complex and have proven to be expensive. They are designed to manage all the information generated by an organisation by using standard processes. These systems work most effectively with large volumes of heavily automated transactions.

“With a lack of scale and usage in some Centres, limited standardisation and low levels of automation, the cost to establish, maintain and upgrade these systems is high. As a result two Centres intend to totally re-implement their existing systems with simpler, standard ERP software, despite the significant investment already made.

“All the Centres acknowledge they need to simplify and standardise their systems and reduce customisation.”

Cabinet Office took a back seat instead of driving sensible change

Says the NAO: “The Cabinet Office and Civil Service Steering Board could have done more to ensure shared services were implemented appropriately. While the Cabinet Office led by example in initiating their own shared service arrangements, more could have been done to challenge the performance achieved by customers and providers.

“They could have established reliable cost and performance benchmarks and done more to document best practice and lessons learned for customers. Also, they could have done more to remove the barriers to departments and agencies joining shared services.

“The Cabinet Office relied on a collaborative model of governance, which was consistent with the role of central government at the time. Under this model it was left to individual departments to implement shared services and eight shared services have been established. There has been little actual sharing of services between departments…”

Should officials have been forced to take part in shared services?

“Departments have struggled to fully roll-out shared services across all their business units and arm’s-length bodies,” says the NAO. “This is because participation has largely been voluntary. Of the five Centres we examined, three had not attracted the customers they had expected and two had potential spare capacity of 50 per cent.”

Cabinet Office is trying to repair the damage

Using DWP and DfT centres the Cabinet Office plans to have two independent shared service centres and a host of sub centres. But the NAO suggests the strategy may fail unless the Cabinet Office mandates the use of the centres. [But there’s no point in mandating change unless working practices are standardised.  If they cannot be standardised shared services may end up – again – costing more.]

Says the NAO  “The Cabinet Office did not have the powers to mandate shared services. Without a mandate, we do not think that coherent shared services are likely to be achieved. If there is an overall value-for-money case for the taxpayer, the Cabinet Office should seek appropriate authority to mandate the shared services strategy and its implementation.

“The Cabinet Office should also make sure that there is clear accountability for implementing its new shared services strategy.”

MPs ignored

“…the Committee of Public Accounts set out recommendations (on shared services) for the Cabinet Office in 2008,” says the NAO. “None of the recommendations have been fully implemented. All are relevant to shared services today.”

The five shared service centres under NAO scrutiny – and their ERP

• The Department for Environment, Food and Rural Affairs (Defra) Centre provides services to 16,000 customer users (full-time equivalents)7 from the Department and 13 of its agencies. Enterprise Resource Planning System: Oracle 11i, upgrade to Oracle v12 in 2012-13.

• The Department for Transport (DfT) Centre provides services for 14,000 customer users from the Department and four of its agencies. SAP ERP.

• The DWP Centre provides services for 130,000 customer users from the Department, the Cabinet Office and the Department for Education. Main site Norcross. ERP system: Oracle 11i, upgrade to Oracle v12 planned in 2012-13.

• The Ministry of Justice Centre manages two separate systems – serving 47,000 customer users for its National Offender Management Service and 27,000 for the Home Office. Enterprise Resource Planning System: Oracle 11i, upgrade to Oracle v12 in 2012-13 and plans to completely re-implement its system to remove all customisation.

• Research Councils UK Centre provides services to 11,000 customer users from seven Research Councils. ERP is Oracle 12.

Three major shared service centres not under NAO scrutiny

• The Ministry of Defence’s Defence Business Services, which was established in July 2011. ERP is Oracle 11i. An upgrade to Oracle v12 in planned for 2012-13.

• The Department of Health NHS Shared Business Services Ltd (joint venture with Steria) which does not provide services to central government. (ERP is Oracle v12)

• HMRC which set up a shared service centre – but no other departments used it. ERP is SAP.

Comment:

Anyone reading the NAO report could be forgiven for thinking that civil servants setting up shared service centres have aimed to fail, perhaps to prove to ministers that major change within central government is a bad idea. We doubt this.

What is more likely is that civil servants, encouraged by some suppliers, thought it a good idea to buy big ERP systems from which they thought savings would naturally flow. But big has not proved to be better. When will this message get through? Isn’t it time for civil servants to stop throwing money at big suppliers?

[And there may be some substance in the NAO’s hint that some civil servants have preferred to work on big ERP systems rather than save money. Having strong ERP skills is an insurance against job loss.]

NAO report  

New child support system has 90,000 requirements – in phase one

                               A new old-style government IT disaster?

By Tony Collins

While officials in the Cabinet Office offcials try to simplify and cut costs of Government IT, a part of the Department for Work and Pensions has commissioned a system with 90,000 requirements in phase one.

The projected costs of the child maintenance system have risen by 85% and the delivery date has slipped by more than two years.

Even with 90,000 requirements, phase one, which is due to go live in October, excludes 70 requirements that are “deemed critical” says a report published today by the National Audit Office.

The NAO report indicates that the Child Maintenance and Enforcement Commission has commissioned an old-style large IT system using traditional developing techniques and relying on large companies.

G-Cloud and SMEs have not featured in the Commission’s IT strategy – and it abandoned agile techniques last year on its child maintenance project.

The Commission put the cost of its new child maintenance system at £149m in January 2011. Ten months later it put the cost at £275m, an 85% increase. The Commission was unable to give the NAO a full explanation for the difference.

Lessons from past failures not learned?

Today’s NAO report says there is a risk the Commission will repeat mistakes by the Child Support Agency whose IT system and business processes were criticised in several Parliamentary reports. The Commission takes in the work of the Child Support Agency – and indeed runs its own systems and the Child Support Agency’s in parallel.

Officials at the Commission told the NAO they have a good track record of holding back IT releases until they are satisfied they will work.  “Nevertheless, we found that the Commission is at risk of repeating many of the mistakes of 2003,” said the NAO. Those mistakes include over-optimism and a lack of internal expertise to handle suppliers.

Mixing “agile” and “waterfall” doesn’t work

Initially civil servants at the Commission tried to “mix and match” agile and traditional developing techniques – which Agile advocates say should not be attempted.

In 2011 the Commission gave up on agile and “reverted to a more traditional approach to system development” says the NAO report.

The mix and match approach meant there were two distinct routes for specifying requirements and “resulted in duplicated, conflicting and ambiguous specifications”.  The Commission did not have previous experience of using the agile approach.

The Commission’s child maintenance system was due to go live in April 2010 but the delivery date has slipped three times. Phase one is now due to go live in October 2012 and phase two in July next year but the NAO report raises questions about whether the go-lives will happen successfully. The Commission has not planned in its financial estimates for the failure of the system.

The NAO finds that the Commission has struggled to make its requirements for the new system clear. The Commission’s main developer Tata Consulting Services has had protracted discussions over the meaning and implementation of requirements.

The NAO also hints that IT costs may be out of control. It says the Commission may not secure value for money without properly considering alternative options for restructuring and “adequately controlling its IT development …”

These are some of the NAO’s findings:

IT costs could increase further

“The new system is based on ‘commercial off-the-shelf’ products. However, a recent audit by Oracle identified that the performance, maintainability and adaptability of the new system would be key risks. This could increase the cost of supporting the system. The scheme does not yet include plans for the integration with HM Revenue & Customs’ Real Time Information system due to be implemented in 2013, or introducing Universal Credit because of the differing timescales,” says the NAO which adds:

“Achieving the Commission’s plans without further cost increases or delays appears unlikely. The Commission reported to the audit committee in October 2011 on the high risk that the change programme may not deliver phase two functionality within agreed timescales … The Commission did not develop a benefits realisation plan until November 2011.”

103,000 of Commission’s 1.1m cases are handled manually

“Ongoing technical problems have resulted in a large number of cases being removed from the IT system and managed manually. These are known as clerical cases … The Commission has had to operate the ‘old’ and ‘current’ schemes in parallel.  Due to flaws in the IT systems for each scheme, some 100,000 cases have had to be processe:d separately by clerical staff at a cost of £48 million,” says the NAO. It takes 900 contractors to manage the clerical cases.

Comment

Despite numerous NAO reports on failures of Government IT-based projects over the past 30 years the disasters are still happening, with the same mistakes repeated: over-optimism in every aspect of the project including timetables and financial estimates; excessive complexity and over-specification, no sign of cost-consciousness and, worst of all, an apparent indifference to being held accountable for a major failure.

A glance at the monthly outgoings of the Commission (well done to the coalition for requiring departments and agencies to publish contracts over £25,000) show sizeable and regular payments to familiar names among the large suppliers: HP Enterprise Services (formerly EDS), Capgemini, Tata Consultancy Services, BT Global Services and Capita. There is hardly an SME in sight and no sign of imaginative thinking.

Meanwhile some senior officials at the Commission put in monthly expenses for thousands of pounds in travel, accomodation and subsistence for “Commission meetings”. One wonders: to what useful effect?

Officials at the Cabinet Office are trying to change the culture of departments and agencies. They are encouraging departmental heads to do things differently. They advocate the use of  SMEs to show how new ways of working can trounce traditional approaches to projects.

But the Cabinet Office has little influence on the Department of Work and Pensions. Indeed the DWP has lost its impressive chief innovator James Gardner.

We praise the NAO for noting that the Commission risks repeating the IT-related and project management mistakes of the Child Support Agency. But we note with concern that the NAO still puts up with Whitehall’s non-publication of  Gateway reviews, which are independent reports on the progress or otherwise of big and risky IT-based projects.

Would the Commission have been so apparently careless of the risks if it had known that regular Gateway reports on its shortcomings would be published?

How many more government IT-based projects are late, over budget and at risk of failing, their weaknesses hidden by an unwritten agreement between the coalition and civil servants to keep Gateway reviews secret?

NAO report – Child Maintenance and Enforcement Commission: cost reduction

Government repeating child support mistakes – ComputerworldUK

Good news: IBM-led shared services company is recognised as “failing”

By Tony Collins

After years of depicting problems at an IBM-led shared services company, Southwest One, as teething, Somerset County Council has conceded that the venture is failing.

The Conservative leader of Somerset County Council Councillor Ken Maddock used the word “failing” nine times in a speech on Wednesday about Southwest One, a company run by IBM on behalf Somerset County Council, Taunton Deane Borough Council and Avon and Somerset Police.

Southwest One’s contract, which was signed in the early hours of a Saturday morning in 2007, was doomed from the start, in part because of the complexity of the arrangements and in part because of pervasive secrecy that antagonised hundreds of Somerset council staff who were already opposed to the joint venture; and they were the very staff who were seconded to Southwest One to make the venture work. [It’s a truism that staff, if they are motivated, will often make their way around difficulties but may be overwhelmed by them if not motivated.]

Last month Campaign4Change set out in detail some of the most disruptive and continuing problems at Southwest One; and we said the difficulties could not be tackled in earnest while Somerset council and its partners were portraying the venture as a success. On 31 January 2012, our post was mentioned on the website of the local Conservative MP Ian Liddell-Grainger.

The good news now is that the council has, this week, for the first time, spoken of Southwest One in unequivocally negative terms. No longer is every council criticism of the company qualified by a positive comment, such that one cancels out the other.

Whether our post last month has made any difference is not important. What’s pleasing is that IBM and Southwest One’s partners are free to make progress, now that Somerset has told it like it is. Much of the credit for the council’s emergence from its long, self-administered anaesthesia lies with Dave Orr who has campaigned for years to highlight the failings of Southwest One, as has Liddell-Grainger.

Maddock’s speech on Southwest One

Maddock’s speech to a full council meeting is reported at length by the Somerset County Gazette and by Liddell-Grainger.

Maddock said

“As an administration we inherited a partnership that promised a huge amount, but it was not delivering. Southwest One’s accounts year on year show losses, staggering losses just published of £31m, and failures to hit modest savings targets.

“We have bent over backwards to try to make this partnership work. But we have to state clearly that our primary duty in looking after the public’s hard earned money is to make sure we get the best possible deals, that we get the best possible value for the public’s money.

“I have to say that Southwest One is failing this test.

“We are currently looking at all our services and all our contracts to see whether we are doing the best we can for our customers,  whether we are providing the best possible services for our customers and at the best possible prices for our customers.

“I have to say that Southwest One is failing this test.

“We need a Council that can cope with future government cuts and rising demand. We will need to be efficient and flexible.

“I have to say that Southwest One is failing this test.

“Sadly, Southwest One is failing. It is failing to deliver promised savings; failing to cope with a changing financial landscape; failing to be flexible enough to adapt in challenging times and provide the best possible value for money.

“To make up for this failure, we will now accelerate our extensive review of everything that the council does: Almost half our most vital services are carried out by private sector or not for profit organisations – we will look to increase this where appropriate.

“We will encourage social enterprises, partnerships, communities and voluntary groups to get more involved in what we do and what we run. We will look to put the customer at the heart of what we do.

“And we will do this whilst we continue to do all we can to make Southwest One work. But I have to be clear; it is failing; it is inflexible; and it is intransigent. We are therefore looking at all the options available to us.

“I do have one final message for Southwest One – and that is to the staff and our Somerset County Council colleagues and secondees working there.  The message is this: This continuing failure is not about you. It is about the contract, the complications, the failed technology, the missed opportunities, the lack of promised savings.  It is about Southwest One itself, not about the people working for it.”

Comments on Maddock’s speech

Some of the comments on the Somerset County Gazette website were apt. One said “Somerset County Council has finally come to accept what we, the minions, have known for years: South West One is a failure and a pretty expensive one…”

Another said

“At last SCC admits to what everyone in the real world knew from day one …”

Comment:

One of the lessons from IT disasters in the private and public sectors is that things often start to improve once the main parties own up to the seriousness of the problems. The good news, perhaps, is that Southwest One may now be at its lowest point. It has at long last purged its bowels, so to speak.

Ian Liddell-Grainger’s website.

Southwest One gets £10m IBM amid “staggering” losses.

IBM struggles with SAP two years on – a shared services warning?

Some success in cutting Whitehall costs

By Tony Collins

The coalition government, Cabinet Office, Treasury, departments and agencies have succeeded in cutting central government costs, according to a National Audit Office report published today.

The NAO found that “in particular, large reductions have been made in spending on consultants, temporary staff, property and information technology” in 2010-11.

Departments cut their spend on consultants by £645m in – a real-terms reduction of 37%, said the NAO which also identified “£537m reduced capital spending on IT-related items”.

Unlike some previous reports of the NAO that have questioned the credibility of officialdom’s claims of savings, the NAO’s latest report “Cost reduction in central government: summary of progress” found that the savings claimed by the Cabinet Office, Treasury and government were usually genuine.

Where departments have cut costs by cancelling IT projects or having contracts renegotiated – as opposed to simplifying and streamlining the way they work – the NAO was unsure whether the savings could be sustained.

Said the NAO

“Central government departments took effective action in 2010-11 to reduce costs and successfully managed within the reduced spending limits announced following the 2010 election.

“This resulted in a 2.3% real-terms reduction in spending within departments’ control, compared with 2009-10. Some £3.75bn or around half the reduction was in areas targeted by the Efficiency and Reform Group for cuts in back‑office and avoidable costs.”

Are IT cuts sustainable without a change in working practices?

The NAO said:

 “The fall of 35 per cent in IT capital spend is partly the result of decisions to permanently halt or reduce spending on specific projects, and partly the result of action to reduce the costs of IT products and services including through contract renegotiation.

“However, it is unlikely that IT capital spending will remain at this lower level in total, given the key role of IT and online services in increasing productivity.”

The NAO mentioned the actions of some departments by name.

–          The Home Office cut costs in part by “significant reductions in IT, estates and consultancy spending”.

– HM Revenue & Customs, the Department for Work and Pensions and the Ministry of Defence aimed to secure the bulk of cost reductions from within their organisations. HM Revenue & Customs has established comprehensive governance arrangements to reduce costs, with a central team and programme management infrastructure. The Department for Work and Pensions put in place a transformation programme board in May 2011 to oversee the redesign of its corporate centre and broader cultural change. “However, it cannot finalise plans beyond 2011-12 as they depend on the future business model after the introduction of Universal Credit,” said the NAO. The DWP’s finance team has provided ‘What the Future Holds’ updates and interactive briefings for staff.

– The NAO said it “identified strong leadership as a key factor in the success of the Foreign and Commonwealth Office’s cost reduction efforts”.

– The Centre for Environment, Fisheries and Aquaculture Services within the Department for Environment, Food and Rural Affairs “held sufficiently detailed information to be able to challenge its project managers to reduce costs without affecting services”. The NAO said the “resulting savings identified from some 200 projects made up 30 per cent of the Agency’s efforts to meet their efficiency savings target”.

In July 2011, the Cabinet Office’s Efficiency and Reform Group reported to the Public Accounts Committee that it had helped save some £3.75bn through various initiatives. “Our analysis of the audited accounts of the 17 main departments confirms that spending in the areas targeted was reduced on this scale”, said the NAO.

Comment

The NAO report shows that within some departments officials are cutting costs by simply reducing grants but some parts of central government are making an effort to do things differently.

We hope the coalition and Cabinet Office keep up the pressure for cost-cutting because, in IT alone, the potential savings are in the billions. The NAO report shows there has been a good start. We hope that the officials who are achieving lasting success will pass on their learning experiences to those who are struggling to make cuts sustainable.

NAO report Cost reduction in central government – a summary of progress

NPfIT Cerner go-live at Bristol – Trust issues apology

By Tony Collins

North Bristol NHS Trust has issued an apology on its website after problems with the implementation of a Cerner Millennium patient record system under the National Programme for IT.

Some Bristol consultants had regarded the software as installed at the Trust as “potentially dangerous”.

The Trust went live on 9 December 2011 with a Cerner patient administration system at Frenchay Hospital and Southmead Hospital that replaced two systems. But the Trust has had to revert to paper in some areas.

On its website the Trust says that its “65 wards and maternity department are all using the new system successfully”.

It accepts that it has “experienced significant problems” in outpatient clinics. It says “These problems have been caused by the incorrect set up of clinic lists, which meant staff could not access the system and errors in the data migration of existing appointments.

“As a result, some patients may have received the wrong appointment dates, no confirmation of appointment or letters being sent out in error.  Again, processes are in place to minimise further disruption to out-patient appointments and ensure patient safety.”

TheTrust says it has engineers and technicians re-building the clinics’ system or they are “in clinics correcting problems as they happen, providing solutions and resolving issues”.

The intention is that 90% of areas will be using Cerner by the end of today [31 January]. “Our aim is that by early February all outpatient clinics will be using Cerner. All other outpatient appointments are being managed via other systems and paper processes.”

The Trust says it is contacting patients by phone or letter to advise them of their current appointment slot. “We have ensured that any urgent referrals including cancer two week waits have been prioritised to ensure they are unaffected.”

It adds “During the process of correcting the issues with outpatient clinics and to support GPs and their patients we have written to them to advise them that all patients who have been referred to us either through Choose & Book, fax or Fast Track are within our appointments system.

“We have advised GPs of a dedicated telephone number, fax number and email address for GPs or their patients to contact for further advice. To provide further reassurance to patients and GPs we will keep the helpline service running until the end of February.”

Apology

The Trust says on its website:

“We apologise and would like to thank the public for their patience and our staff for their hard work and dedication in ensuring that patient safety is not compromised.

“These issues have caused disruption and frustration for our patients and our staff and we recognise that this has not delivered the level of service that we expect, and the public expect, from us.

“It has also placed extra workload on our staff, who nevertheless, remain dedicated to ensuring the best possible patient care during this period, and managing the issues that the Trust faces.

“Our Information Management & Technology Team, supported by our suppliers BT and Cerner, have been working very hard to sort out these initial issues and we are already seeing improvements.

“We remain confident that once the new system is fully implemented, it will significantly improve services for our patients and better equip us to meet future challenges.”

Meanwhile the Bristol Evening Post reports that the Chief Executive of the hospital trust, Ruth Brunt, has called for an independent inquiry into the issues surrounding the implementation of the Cerner system.

She said people who have turned up to appointments and operations that have been cancelled or were not on the system would be compensated.  A hotline has also been set up so that people can check whether their appointments are in the system.

The Bristol Evening Post also reported that reception staff had walked out due to the pressure of dealing with patients who were unhappy to find their appointments not on the new system.

“It is horrendous – what used to take us five or six clicks is currently taking 24 and we cannot access the details,” a staff member said. “The notes have not been available when people turn up.

“We have all worked hard and I am sure if it was anywhere else we would have gone on strike. The people on the ground are struggling. It is really demoralising because we are doing our best. Girls on reception are dealing with queues of people and there has been an occasion where a receptionist has walked out because they were so stressed.

“When patients call up we want to be able to help them, but at the moment we don’t know where to look.”

The employee did not believe the trust’s claims that everything would be sorted out by 13 February.

Halt Cerner implementations says MP

DWP defends £316m HP contract

By Tony Collins

The Department for Work and Pensions could lead the public sector in technical innovations. It has had some success in cutting its IT-related costs. It has also had some success so far with Universal Credit, which is based on agile principles.

It has further launched an imaginative welfare-to-work scheme , the so-called Work Programme, which seeks to get benefit claimants into jobs they keep.

Despite media criticism of the way the scheme has been set up – especially in the FT – a report by the NAO this week made it clear that the DWP has, for the most part, taken on risks that officials understand.

Some central government departments have updated business cases as they went through a major business-change programme and not submitted the final case until years into the scheme, as in parts of the NPfIT.

But the DWP has implemented the Work Programme unusually quickly, in a little more than a year, by taking sensible risks.  The NAO report on the scheme said the business case and essential justification for the Work Programme were drawn up after key decisions had already been made. But the NAO also picked out some innovations:

– some of the Work Programme is being done manually rather than rush the IT

– suppliers get paid by results, when they secure jobs that would not have occurred without their intervention. And suppliers get more money if the former claimant stays in the job.

– the scheme is cost-justified in part on the wider non-DWP societal benefits of getting the long-term unemployed into jobs such as reduced crime and improved health.

So the DWP is not frightened of innovation. But while Universal Credit and welfare-to-work scheme are centre stage, the DWP is, behind the safety curtain, awarding big old-style contracts to the same suppliers that have monopolised government IT for decades.

Rather than lead by example and change internal ways of working – and thus take Bunyan’s steep and cragged paths – the DWP is taking the easy road.

It is making sure that HP, AccentureIBM and CapGemini are safe in its hands. Indeed the DWP this week announced a £316m desktop deal with HP.  EDS, which HP acquired in 2008, has been a main DWP supplier for decades.

DWP responds to questions on £316m HP deal 

I put it to the DWP that the £316m HP deal was olde worlde, a big contract from a former era. These were its responses. Thank you to DWP press officer Sandra Roach who obtained the following responses from officials. A DWP spokesperson said:

“This new contract will deliver considerable financial savings and a range of modern technologies to support DWP’s strategic objectives and major initiatives such as Universal Credit.

“The DWP has nearly 100,000 staff, processing benefits and pensions, delivering services to 22 million people.

“DWP is on schedule to make savings of over £100m in this financial year for it’s Baseline IT operational costs, including the main IT contracts with BT and HPES [Hewlett Packard Enterprise Services].

“All contracts have benchmarking clauses to ensure best value for money in the marketplace.

“The five year contract was awarded through the Government Procurement framework and has been scrutinised to ensure value for money.”

My questions and the DWP’s answers:

Why has the DWP awarded HP a £316m contract when the coalition has a presumption against awarding contracts larger than £100m?

DWP spokesperson: “The Government IT Strategy says (page 10) ‘Where possible the Government will move away from large and expensive ICT projects, with a presumption that no project will be greater than £100m. Moving to smaller and more manageable projects will improve project delivery timelines and reduce the risk of project failure’.

“HM Treasury, Cabinet Office and DWP’s commercial and finance teams have scrutinised the DWP Desktop Service contract to ensure that it represents the most economically advantageous proposition.”

What is the role, if any for SMEs ?

DWP: “There are a number of SMEs whose products or services will form part of or contribute to the DWP Desktop Service being delivered by HP, for example ActivIdentity, Anixter, AppSense, Azlan, Click Stream, Cortado, Juniper Networks, Quest Software, Repliweb Inc, Scientific Computers Limited (SCL), Westcon etc.”

Why is there no mention of G-Cloud?

DWP: “Both the new contract and the new technical solution are constructed in such a way as to support full or partial moves to cloud services at DWP’s discretion.”

Comment:

For the bulk of its IT the DWP is trapped by a legacy of complexity. It is arguably too welcoming of the safety and emollients offered by its big suppliers.

The department is not frightened by risk – hence the innovative Work Programme which the NAO is to be commended on for monitoring at an early stage of the scheme. So if the DWP is willing to take on sensible risks, why does it continue to bathe its major IT suppliers in soothingly-large payments, a tradition that dates back decades? What about G-Cloud?

DWP reappoints HP on £316m desktop deal

DWP signs fifth large deal with HP

“DWP awards Accenture seven year application services deal”

“DWP awards IT deals to IBM and Capgemini”

G-Cloud – it’s starting to happen

By Tony Collins

Anti-cloud CIOs should “move on” says Cabinet Office official, “before they have caused too much harm to their business”.

For years Chris Chant, who’s programme director for G Cloud at the Cabinet Office, has campaigned earnestly for lower costs of government IT. Now his work is beginning to pay off.

In a blog post he says that nearly 300 suppliers have submitted offers for about 2,000 separate services, and he is “amazed” at the prices. Departments with conventionally-good rates from suppliers pay about £700-£1,000 a month per server in the IL3 environment, a standard which operates at the “restricted” security level. Average costs to departments are about £1,500-a-month per server, says Chant.

“Cloud prices are coming in 25-50% of that price depending on the capabilities needed.”  He adds:

“IT need no longer be delivered under huge contracts dominated by massive, often foreign-owned, suppliers.  Sure, some of what government does is huge, complicated and unique to government.  But much is available elsewhere, already deployed, already used by thousands of companies and that ought to be the new normal.

“Rather than wait six weeks for a server to be commissioned and ready for use, departments will wait maybe a day – and that’s if they haven’t bought from that supplier before (if they have it will be minutes).  When they’re done using the server, they’ll be done – that’s it.  No more spend, no asset write down, no cost of decommissioning.”

Chant says that some CIOs in post have yet to accept that things need to change; and “even fewer suppliers have got their heads around the magnitude of the change that is starting to unfold”.

“In the first 5 years of this century, we had a massive shift to web-enabled computing; in the next 5 the level of change will be even greater.  CIOs in government need to recognise that, plan for it and make it happen.

“Or move on before they have caused too much harm to their business.”

He adds: “Not long from now, I expect at least one CIO to adopt an entirely cloud-based model.  I expect almost all CIOs to at least try out a cloud service in part of their portfolio.

“Some CIOs across government are already tackling the cloud and figuring out how to harness it to deliver real saves – along with real IT.  Some are yet to start.

“Those that have started need to double their efforts; those that haven’t need to get out of the way.”

Cloud will cut government IT costs by 75% says Chris Chant

Chris Chant’s blog post