Category Archives: health records

Will coalition sign a new NPfIT deal with CSC?

By Tony Collins

CSC has told investors that its discussions with the UK government on an interim agreement for deploying Lorenzo to the NHS are “continuing positively”.

CSC says that an agreement could commit a certain number of NHS trusts to take Lorenzo. Some of those trusts would be named in the interim agreement and the remainder within six months. CSC refers to them as “committed named trusts”.

[Such a legal commitment for named NHS trusts to take Lorenzo may run counter to the post-NPfIT coalition philosophy of giving trusts the freedom to buy what they want, when they want, and from whom they want. The named trusts might have indicated on a  DH questionnaire a wish to take Lorenzo but an agreement between the government and CSC would commit the trusts irrevocably, or the DH could have to pay CSC compensation for non-deployment.]

CSC says the deployed product would be categorized as “base product” or “additional product” for pricing purposes. The DH would commit money to the base product. Other funds would be available centrally available for “additional products,  supplemental trust activity and local configuration”.

The DH would give CSC a structured set of payments following certain product deliveries, as well as additional payments to cover various deployments for the named trusts and payments for work already performed.

If the government does not sign a new deal, and allows CSC’s existing contracts to run down until they expire formally in 2015, this could keep further NPfIT-related costs to the taxpayer to a minimum.  But it risks legal action from CSC, which says the NHS contract is enforceable and that the NHS has no existing right to terminate the contract, unless for convenience (which is unlikely).

If the government had terminated CSC’s contracts for its convenience (as opposed to alleged breach of contract) it would have had to pay CSC a termination fee capped at £329m as of 29 June 2012. CSC would also have been entitled to compensation for the profit it would have earned for the 12 months after the contract was terminated.

If the contract is not terminated, a new deal not signed, and no legal action is taken by either side, the amounts the UK government would have to pay CSC are likely to be minimised.  It is in CSC’s interests to maintain and enhance Lorenzo for those NHS sites that have deployed it.

So will the government sign a new deal with CSC at least to reduce the risks of CSC legal action? Or could the government hold out not signing any agreement until expiry of the contracts in 2015 on the basis that CSC has not delivered all it promised?

If a new deal is signed – and CSC indicates that an agreement is likely – the government may face accusations that it has broken its undertaking to dismantle the NPfIT.

David Camerson intervened personally to have the Cabinet Office’s Major Projects Authority look closely at NPfIT commitments.  His “efficiency” minister Francis Maude is likely to resist the signing of any new agreement

But will CSC accept the government’s refusal to sign a new deal, when such a deal could enable CSC to recover at least some of the $1.485bn (£0.95bn) it recorded as an NPfIT contract charge in the third quarter of 2012?

Cerner US-wide outage – what went wrong?

By Tony Collins

Hospital EMR and EHR has an account of what caused Cerner’s outage which affected its client sites across the USA and some international customers, according to reports.

It makes the point that the problem had little or nothing to do with the cloud.

The Los Angeles Times reports that within minutes of the outage, doctors and nurses reverted to writing orders and notes by hand, but in many cases they no longer had access to previous patient information saved remotely with Cerner.

“That information isn’t typically put on paper charts when records are kept electronically,” said the newspaper which quoted Dr. Brent Haberman, a pediatric pulmonologist in Memphis as saying, “If you can’t get to all the patient notes and all the previous data, you can imagine it’s very confusing and mistakes could be made…A new doctor comes on shift and doesn’t have access to what happened the past few hours or days.”

Hospital EMR and EHR

Some hospitals cope well through the outage

Some lessons from a major outage

By Tony Collins

One of the main reasons for remote hosting is that you don’t have to worry about security and up-time is guaranteed. Support is 24x7x365. State-of-the-art data centres offer predictable, affordable, monthly charges.

In the UK more hospitals are opting for remote hosting of business-critical systems. Royal Berkshire NHS Foundation Trust and Homerton University Hospital NHS Foundation Trust are among those taking remote hosting from Cerner, their main systems supplier.

More trusts are expected to do the same, for good reasons: remote hosting from Cerner will give Royal Berkshire a single point of contact to deal with on technical problems without the risks and delay of ascertaining whether the cause is hardware, third party software or application related.

But what when the network goes down – across the country and possibly internationally?

With remote hosting of business-critical systems becoming more widespread it’s worth looking at some of the implications of a major outage.

A failure at CSC’s Maidstone data centre in 2006 was compounded by problems with its recovery data centre in Royal Tunbridge Wells. Knock-on effects extended to information services in the North and West Midlands. The outage affected 80 trusts that were moving to CSC’s implementation of Lorenzo under the NPfIT.

An investigation later found that CSC had been over-optimistic when it informed NHS Connecting for Health that the situation was under control. Chris Johnson, a professor of computing science at Glasgow University, has written an excellent case study on what happened and how the failure knocked out primary and secondary levels of protection. What occured was a sequence of events nobody had predicted.

Cerner outage

Last week Cerner had a major outage across the US. Its international customers might also have been affected.

InformationWeek Healthcare reported that Cerner’s remote hosting service went down for about six hours on Monday, 23 July. It hit “hospital and physician practice clients all over the country”. Information Week said the unusual outage “reportedly took down the vendor’s entire network” and raised “new questions about the reliability of cloud-based hosting services”.

A Cerner spokesperson Kelli Christman told Information Week,

“Cerner’s remote-hosted clients experienced unscheduled downtime this week. Our clients all have downtime procedures in place to ensure patient safety. The issue has been resolved and clients are back up and running. A human error caused the outage. As a result, we are reviewing our training protocol and documented work instructions for any improvements that can be made.”

Christman did not respond to a question about how many Cerner clients were affected. HIStalk, a popular health IT blog, reported that hospital staff resorted to paper but it is unclear whether they would have had access to the most recent information on patients.

One Tweet by @UhVeeNesh said “Thank you Cerner for being down all day. Just how I like to start my week…with the computer system crashing for all of NorCal.”

Another by @wsnewcomb said “We have not charted any pts [patients] today. Not acceptable from a health care leader.”

Cerner Corp tweeted “Our apologies for the inconvenience today. The downtime should be resolved at this point.”

One HIStalk reader praised Cerner communications. Another didn’t:

“Communication was an issue during the downtime as Cerner’s support sites was down as well. Cerner unable to give an ETA on when systems would be back up. Some sites were given word of possible times, but other sites were left in the dark with no direction. Some sites only knew they were back up when staff started logging back into systems.

“Issue appears to have something to do with DNS entries being deleted across RHO network and possible Active Directory corruption. Outage was across all North America clients as well as some international clients.”

Colleen Becket, chairman and co-CEO of Vurbia Technologies, a cloud computing consultancy, told InformationWeek Healthcare that NCH Healthcare System, which includes two Tampa hospitals, had no access to its Cerner system for six hours. The outage affected the facilities and NCH’s ambulatory-care sites.

Lessons?

A HIStalk reader said Cerner has two electronic back-up options for remote hosted clients. Read-only access would have required the user to be able to log into Cerner’s systems, which wouldn’t have been possible with the DNS servers out of action last week.

Another downtime service downloads patient information to local computers, perhaps at least one on each floor, at regularly scheduled intervals, updated say every five minutes. “That way, even if all connection with [Cerner’s data centre] is lost, staff have information (including meds, labs and more) locally on each floor which is accurate up to the time of the last update”.

Finally, says the HIStalk commentator, “since this outage was due to a DNS problem, anyone logged into the system at the time it went down was able to stay logged in. This allowed many floors to continue to access the production system even while most of the terminals couldn’t connect.”

But could the NHS afford a remote hosted service, and a host of on-site back-up systems?

Common factors in health IT implementation failures

In its discussion on the Cerner outage, HIStalk put its finger on the common causes of hospital IT implementation failures. It says the main problems are usually:

– a lack of customer technical and implementation resources;
– poorly developed, self-deceiving project budgets that don’t support enough headcount, training, and hardware to get the job done right;
– letting IT run the project without getting users properly involved
– unreasonable and inflexible timelines as everybody wants to see something light quickly up after spending millions; and
– expecting that just implementing new software means clearing away all the bad decisions (and indecisions) of the past and forcing a fresh corporate agenda on users and physicians, with the suppplier being the convenient whipping boy for any complaints about ambitious and sometimes oppressive changes that the culture just can’t support.

Cerner hosting outage raises concerns

HIStalk on Cerner outage

Case study on CSC data centre crash in 2006

Will health IT market “heat up” when NPfIT contracts expire?

By Tony Collins

At a second-quarter earnings call, Marc Naughton, Chief Financial Officer at US-based health software supplier Cerner, singled out the UK as one country where there will be probably be “a lot of demand” for new health IT products and services subject to capital being available.

He said,

“As more and more of those trusts are becoming foundation trusts, which means they control their capital outlet – outlay as opposed to the government putting the dollars out there – we think that’s going to turn into a more normalised US-type market where each trust is going to go out to the market and look to acquire technology.

“In 2015, the current NHS [NPfIT] contracts expire. So almost all of those trusts are going to be looking in the market in some form or fashion, probably depending on their access to capital.

“So we think that market is one that could heat up in 12 to 18 months from now, assuming that they can get access to capital. But it is going to be a little bit lumpy.”

 

Trust buys extras-laden system for 20% of BT’s price

By Tony Collins

An NHS Trust has paid £1.8m for the “Rio” patient record system and a host of extras – which raises fresh questions about why the Department of Health paid BT £9m for each Rio deployment under the NPfIT.

BT’s deal with the Department of Health under the NPfIT costs taxpayers £224.3m for 25 deployments of Rio – about £9m for each one. The deal included support for five years, until October 2015.

But a deal struck directly between Cambridgeshire and Peterborough NHS Foundation Trust and Rio’s supplier CSE-Healthcare Systems includes support for a year longer – six years in total. At £1.806m the cost of Cambridgeshire and Peterborough’s deal is about 20% BT’s price.

Cambridgeshire and Peterborough has secured more extras. CSE-Healthcare Systems will supply Cambridgeshire and Peterborough with:

  – Medical software development services

– Software consultancy services

 – Computer support services

– System implementation planning services

– Software implementation services

– Project management consultancy services

– Business and management consultancy services

– Medical software package

– Database and operating software package

– Information systems and servers

– Computer and related services

– Software support services

It’s not clear though whether the deal includes disaster recovery – which the Department of Health argues is one reason for the price paid to BT for Rio.

Comment:

Disaster recovery does not explain how or why the Department of Health agreed to pay BT five times more for Rio than paid by Cambridgeshire and Peterborough.

What is not in doubt is that if BT, like Accenture and Fujitsu before it, had left the NPfIT, the programme would have been indelibly stamped a disaster – at a time when the Department of Health and ministers were proclaiming it an unacknowledged success (in the run up to a general election).

Was BT paid a hugely costly premium to stay in the NPfIT?  If so, should tax money have been used to secure the affections of a supplier whose profits were otherwise being squeezed on the contract?

Last year the Department of Health gave the Public Accounts Committee an explanation of its Rio payments to BT, some of which is below. The explanation is long, vague and defensive enough to sound like the excuses of a young boy who, when questioned by his teacher, gives various accounts of why he took a classmate’s sweets.

What the DH told MPs

This is what the DH told the Public Accounts Committee last year, after one of its MPs Richard Bacon queried the payments to BT for Rio (and Cerner).

“Assessing the value for money of the RiO prices was part of the CCN3 [change control note 3] negotiation process … The CCN3 negotiation process was lengthy and involved many iterations challenging the component parts of the BT cost model. This included ensuring that rates offered were competitive and that the effort ascribed to various activities was justifiable.

Taken together, competitive rates and reasonable effort comprise value for money. BT was required to provide numerous iterations of financial models. These models were reviewed in detail by the Authority, resulting in multi-million pound savings.

The Authority negotiated reduced day rates on all of the BT labour within the contract. In addition, BT’s profit margin on the contract was also significantly reduced. Other commitments were also obtained by the Authority, in particular around sub-contractor pricing; for example, Cerner has confirmed that the pricing provided to the Authority (via BT) is the best it provides to any of its customers.

The Authority then requested further financial assurances and agreed with BT that a requirement of signing CCN3 would be that a verification exercise would be conducted by third party, independent financial experts (KPMG)…

In October 2010 KPMG were requested by the Authority to verify the costs presented by BT, including those for RiO, in the CCN3 Financial Model.

The approach adopted by KPMG was as follows:

—  Their work focussed on the Cost Data sheet within the CCN3 Financial Model and was conducted on a sample basis, designed to provide a high coverage of costs with a reasonable sample size.

—  The cost elements for potential duplicate entries were reviewed.

—  The cost rates associated with BT labour were validated to cost rate cards and payroll records.

—  The hours presented in the Model associated with BT labour were reviewed for reasonableness.

—  Sub-contractor and other supplier costs were validated to the agreements entered into by BT with their suppliers.

—  Cost elements and supporting documentation requested from BT were sampled to substantiate the costs provided…

On 3 November 2010 KPMG concluded that “BT has provided underpinning evidence to support the agreed delivery costs” and that “no proposed adjustments are required for Agreed Delivery Costs”.

None of the trusts consulted had purchased the same RiO product offering and all trusts varied significantly from the offering provided to NPFIT trusts, making a direct price comparison difficult. However, trusts within the programme typically had significant advantages to those outside the programme, namely:

—  The ability to influence the functionality of the product.

—  Centrally provided and hosted hardware.

—  Centrally-provided disaster recovery with 100% capacity and availability.

—  No additional development costs for subsequent releases.

—  Spine connectivity.

BT estimate that the monthly charge for hardware, disaster recovery, service management and Spine connectivity to be in the region of £42,500 per month or just over £2 million of value over a 48 month contract term.

Furthermore the NPFIT investment in the development of the RiO has significantly enhanced the functionality of the product to the benefit of all trusts. Examples of functionality in the latest deployed version (v5) and soon to be deployed (R1, 2011) of RiO include:

—  Standard assessment forms.

—  Care-plans and reports.

—  Spine connectivity, enabling integration with central demographics services, and functionality to support smart cards and role based access controls.

—  Waiting lists.

—  Results reporting.

—  Prevention, screening and surveillance.

—  SNOMED.

—  Inpatient prescribing.

—  Functionality to support multi-disciplinary care planning.

DH statement to MPs on Rio (and Cerner) prices paid to BT

MP seeks inquiry into £546m NHS deal with BT.

Breakdown of £546m NPfIT payment to BT

Lessons from an IT disaster

By Tony Collins

Only rarely is an independent report on an IT-related disaster published.  So North Bristol NHS Trust deserves credit for publishing a report  by Pricewaterhousecoopers into the problematic go-live of Cerner Millennium in December 2011.  PwC calls the Cerner system a “business-critical patient record system”.

The implementation, says PwC,  resulted in significant continuing  operational difficulty. PwC was asked to review the implementation, identify what went wrong and make recommendations.

What is clear from PWC’s report is that North Bristol NHS Trust repeated the known mistakes of other trusts that had gone live with Cerner Millennium:

–          A lack of independent challenge

–          Not enough testing of the system and new business processes

–          Inadequate contingency arrangements

–          Not enough time for data migration

–          Training systems not the same as those to be used

–          Preparations treated as an IT project, not a change programme.

–          Differences between legacy and Cerner systems not fully understood before go live

–          Staff did not always understand new or changed business processes

In 2007 the National Audit Office reported in detail on the lessons from the go-live of Cerner Millennium at Nuffield Orthopaedic Centre, Oxford in December 2005.

One of those lessons was that the Trust did not learn lessons from earlier NPfIT Cerner Millennium go-lives. This happened again at North Bristol, suggests the PwC report:

“There were not dissimilar Cerner implementations within the Greenfield [other ex-Fujitsu and now BT-managed Cerner Millennium implementations under the NPfIT] systems running a few months before NBT’s [North Bristol Trust] implementation. Similar difficulties were experienced there, but they were more successfully addressed.”

Below are extracts from PwC’s report “Independent review of Cerner Millennium implementation North Bristol NHS Trust”.

“The success of an implementation of this scale, complexity and timing depends on substantial, robust and enduring programme management focusing on:

–          The IT implementation. Incorporating configuration of Cerner Millennium, infrastructure, security, interfaces and testing;

–          The migration of data from the two legacy PAS systems into Cerner Millennium;

–          Change management to engage and train stakeholders, embed change in the organisation and ensure that processes and procedures are aligned to the new system;

–          Continuous communication with users about changes to business processes as a result of the implementation; and

–          Quality control criteria and the association governance to ensure that go-live went ahead in a safe and sustainable manner.

–          The Trust needed stringent programme management with programme and project managers of the highest quality, to ensure that effective governance and project planning procedures were followed.

–          The go-live decision and assurances needed to pass strict criteria with sufficient evidence to provide assurance to the board that all necessary activities were completed prior to go-live.

The implementation in both the wards and the Emergency Department (ED) went well. Staff in ED were well engaged in the project and as a result were fully aware of the changes to their business processes at go live. There were some minor system issues initially but these were resolved quickly and ED was fully operational with Cerner Millennium soon after go live. One of the underlying factors in the success of the deployment to ED was that there was no data migration required as the historical data remains in the old system.

The launch in the wards went as expected; the functionality was tested well and the data was loaded manually, although there now appear to be issues with staff engaging and using the system as intended.

The majority of problems encountered at go live related to the theatre and outpatient clinic builds.

Outpatients had the most disruption immediately after go live. The Trust’s back office team had not finished building the outpatient clinics in Cerner Millennium, so the new and old systems did not mirror each other and data could not successfully migrate. Changes continued to be made to clinics in the old PAS systems, and these were not all reflected in Cerner Millennium.

Ad hoc clinics were used in the old PAS system to allow overbooking to maximise activity. These were not separated from real clinics at go live and migrated to Cerner Millennium as real clinics. The ad hoc clinics in PAS had deliberately abnormal timings so they could be excluded from time-based reports, for example 12:30am and 5:30am. The system generated letters for these ad hoc out- of-hours clinics, and many were sent to patients.

In the old system, clinics for a number of consultants could be pooled to facilitate patients seeing the next available consultant.  All clinics in Cerner Millennium are specific to a consultant and this caused significant confusion to administration staff using the new system.

PAS [the legacy patient administration system] treats “weeks” differently to Cerner Millennium. On migration, weeks were misaligned and the dates for clinics and theatres was incorrect. This created huge confusion as patient notes did not agree with Cerner Millennium , despite exhaustive work before go live to ensure that all patient notes were ready for the clinics that should have been on the system.  This also affected information in letters, with patients advised to attend their appointment on the wrong date.

There was a further issue in theatres relating to theatre procedure codes. The Trust did not map the old procedure codes to the new to ensure that all the required procedures would be available in Cerner Millennium for the data to migrate successfully. The Trust identified this issue soon after go live and has run a parallel manual process to ensure patients received the correct procedures.

The training provided to staff by the Trust did not equip them to be able to use Cerner Millennium at go live. The training environment did not mirror the system the Trust implemented as certain elements of the system were not complete when the training domain was created. Theatre staff and outpatient appointments could not train on a system with theatre schedules and outpatient clinics built in.

The Trust is now beginning to move out of the crisis and return to normal operations.

Lack of effective quality controls

There was insufficient rigour over the controls criteria and sign off of the gateway reviews.

There was inadequate operational control over the go live process, such as clinic freeze and updates pre-, during, and post go-live. Evidence from the interviews suggests that:

  • There was little challenge to confirm that the gateway criteria had in fact been met.
  • There was no evidence presented to the Cerner Programme Board or the Trust Board to demonstrate that the gateway criteria had been met.
  • There was not enough focus on or monitoring of risks and issues and their impact on go live.
  • The cleansing of old and out-of-date data from the legacy PAS systems was inadequate; as a result, erroneous data became live data in the Cerner system.
  • Data Migration issues were not all resolved and their impact on go live was not considered.
  • The outpatient and theatre builds were neither complete nor accurate, and there were no controls which could have detected this before go live.
  • There were inadequate controls over clinic freeze and clinic changes prior to go live.

Lack of effective programme planning

Programme plans were not rigorously updated as the programme progressed and planning around training, testing and data migration and build was not robust. The Trust failed to recognise this programme as a change programme and did not effectively manage the engagement and feedback from their stakeholders. Evidence from the interviews suggests that:

  • The Trust did not factor contingency into its programme plan to account for changes to the go live date.
  • The Cerner Programme Management Office was not effective because of inadequate resource and programme tools.
  • The Trust had a lack of sufficiently skilled resources for a project on this scale.
  • The Trust’s operational staff were not fully engaged in the Cerner project.
  • The Cerner project was treated as an IT project and not a business change programme.
  • The training was inadequate and did not provide users with the skills they needed to be able to use the system at go live.
  • The testing focused on the functionality of the system and not end-user testing of the outpatient and theatre builds.
  • There was no end-user testing of the final outpatient clinic and theatre builds prior to go live.
  • There was lack of understanding of roles within the wider programme team.
  • External parties offered NBT help and advice. They felt that the advice was not taken and the help was refused.

Lack of effective programme governance

Programme governance processes were not reviewed and updated regularly to ensure that they were adequate and there was inappropriate accountability for key decision making. During the implementation, the Trust established new overarching change management arrangements for the Building our Future programme. Evidence from the interviews suggests that:

  • The Cerner Project team failed to comply with the Trust’s Building our Future governance processes
  • The information presented to the Cerner Programme Board and the Trust board by the Cerner Project team was inadequate for them to make informed decisions;
  • The Cerner Programme Board was not effective; and
  • Significant issues relating to the theatre and outpatient clinic build were not escalated to the Cerner Programme Board or the Trust board.

PwC’s Conclusions

For a programme of this scale and complexity, the management arrangements were not sufficiently extensive or robust. There were many issues with the software and data migration, the training of users and operational go live planning. The Trust Board and the Cerner Programme Board did not plan to have, and did not receive, independent assurance that the state of the programme supported a decision to go-live.

Complex IT implementations are never without risks and issues that need to be managed, even at the point of go live. The scale of the issues in this implementation was not properly understood by those with responsibility, and as a result they were not in a position to make sound decisions.

Many of the problems are associated with poor data and process migration. Staff found that a significant proportion of migrated data was incorrect in the new system, and this had rapid and substantial operational impact which has taken a considerable time to rectify with manual processes. Staff needed to be more directly involved in migration and process testing.

The implementation was manifestly a complex change programme. But IT took the lead, and there was no intelligent customer with sufficient distance from IT to ensure products and progress were properly challenged.

There were not dissimilar Cerner implementations within the Greenfield running a few months before NBT implementation. Similar difficulties were experienced there, but they were more successfully addressed.”

PwC recommends that:

–  the Trust “stop and take stock”. It says  “The Trust needs to take stock of its position and develop a coherent and detailed plan for the remainder of the recovery stage. The Trust then needs to ensure that effective cross programme planning and governance arrangements are enforced for all current projects, especially those under the Building Our Future programme.”

PwC also recommends that the Trust carry out a:

–  Governance review

– Capability/capacity review

– Cross programme plan review

– Operational assessment

– Review of process and controls

– Review of information requirement

– Technical resilience/infrastructure review

– Review of access controls

Comment:

To me the PwC report throws up at least six points:

1) Are NPfIT go-lives more political than pragmatic?

In the 1990s Barclays Bank went live with new systems for all its branches. During the night (I was invited to watch the go-live at head office) the most striking element was a check list that asked questions on progress so far. The answers determined whether the go-live would happen. The check-list was completed repeatedly – seemingly endlessly – during the night.

Many  different types of mishaps could have stopped the go-live.  None did.  Go-lives of Cerner Millennium are different. They seem unstoppable, whatever the circumstances, whatever the problems.  There was nothing political about the Barclays go-live. But NPfIT go-lives are intensely political.

Would North Bristol’s board have accepted with equanimity a last-minute cancellation, especially after go-lives had been postponed at least twice before?

2)  Are NHS boards too focused on “good news” to oversee an NPfIT go live?

North Bristol NHS Trust deserves praise for publishing the PwC report.  But it’s not the whole story.  The report says little about any potentially serious impact on patients. Also it mentions (almost in passing) that the Trust board discussed in November 2011 the readiness of Cerner Millennium to go live. That discussion was probably positive because Millennium went live a month later. But there is no mention of that discussion in the Trust’s board papers for November 2011.

Why did the Trust discuss its readiness to go live in secret? And why did it keep secret its November 2011 report on its readiness to go live?

If North Bristol, like so many NHS trusts, is congenitally beset with a good news culture at board level, can the full truth ever be properly discussed?

3) Isn’t it time Cerner lessons were learnt?

After seven years of Cerner implementations in the NHS, several of them notorious failures, isn’t it time Trusts learnt the lessons?

4)  What’s the current position?

PwC’s report is succinct and professional. It’s also diplomatically-worded. There is little in the report that points to how the Trust is coping with the operational difficulties. Indeed it suggests the Trust is returning to normal. “The Trust is now beginning to move out of the crisis and return to normal operations,” says the PwC report. But that is, in essence, what the Trust has been saying publicly since January 2012.  PwC says nothing about whether the safety of patients has been jeopardized by the go-live.

5) Where were the Trust’s Audit Committee – and internal auditors?

Every NHS Trust has an audit committee and internal auditors to warn about things that are going wrong, or may go wrong. It appears that they were out to lunch when it came to North Bristol’s Cerner Millennium project and its consequences.  The Audit Committee seems hardly to have mentioned the project. Should North Bristol’s board hold the Audit Committee and internal auditors to account?

6) Is the Trust board to blame?

Perhaps rightly PwC does not seek to apportion blame. But did the Trust board ask the right questions often enough?  The tacit criticism in the PwC report is of the IT department and layers of management below board level. But is that criticism misdirected? If the board’s culture of encouraging good news – of “bring me solutions not problems” –  has not changed, perhaps little or nothing will have been learned from North Bristol’s IT-related disaster.

PWC report Independent review of Cerner Millennium implementation North Bristol NHS Trust.

Lessons from Nuffield Orthopaedic’s Cerner Millennium implementation in 2005.

North Bristol apologises over Cerner go-live.

New hospital system caused chaos.

MP asks why two Cerner systems cost vastly different prices.

All change at the DH, CfH and on NPfIT – or not?

By Tony Collins

Katie Davis is to leave as interim Managing Director of NHS Informatics, says eHealth Insider which has seen an internal memo.

.The memo indicates that Davis “intends to focus on being a full-time mother to her two children”.

She joined the Department of Health on 1 July 2011, on loan from the Cabinet Office where she was Executive Director, Operational Excellence, in the Efficiency and Reform Group.

Before that she was Executive Director of Strategy at the Identity and Passport Service in the Home Office.

The memo indicates that the director responsible for the day-to-day delivery of NHS programmes and services, Tim Donohoe, will take-over Davis’ role until NHS Connecting for Health shuts down at the end of March 2013.

CfH’s national projects look set to move to the NHS Commissioning Board in Leeds, while its delivery functions will move to the Health and Social Care Information Centre.

Davis had told eHeath Insider that her priorities included concluding a piece of unfinished business on the NPfIT – the future of the [CSC] local service provider deal for the North, Midlands and East.

Comment:

Davis has been a strong independent voice at the Department of Health. Partly under her influence buying decisions have passed to NHS trusts without penalties being paid by the NHS to NPfIT local service provider CSC.

It is a little worrying, though, that high-level responsibility for the rump of the NPfIT – CSC’s contracts, Choose and Book, the Spine, Summary Care Record and other centrally-managed projects and programmes – may fall to David Nicholson, Chief Executive of the NHS.

Labour appointed Nicholson in 2006 with a brief that included making a success of the NPfIT. He has been the NPfIT’s strongest advocate.

Indeed a confidential briefing paper from the Department of Health to the then PM Tony Blair in 2007 on the progress of the NPfIT said:

“… much of the programme is complete with software delivered to time and to budget.”

It is difficult to see the NPfIT being completely dismantled under David Nicholson. It’s probable that CfH will be shut down in name but recreated in other parts of the NHS, while the NPfIT programmes and projects run down very slowly.  It’s even conceivable that CSC’s and BT’s local service provider contracts will be extended before they are due to expire in 2015/16.

A comment on eHealth Insider says:

“My understanding is that NPfIT is leaving us with a legacy of ancient PAS systems barely fit for purpose which cost a fortune to operate and which will transfer to a massive service charge once national contracts end. That’s if you don’t count the most expensive PACS system in the universe. And I wonder what Lorenzo cost?”

It’s hard to argue with that. Meanwhile the costly NPfIT go-lives are due to continue, at Imperial College Healthcare NHS Trust, for example.

End game for Davis and CfH announced.

Cancer waits mix-up – how concerned is the Trust?

By Tony Collins

When a passenger jet crashes, if the airline’s next board meeting barely mentions it, and instead discusses a catering award and a staff survey, those booked on flights with the airline may have cause for concern.

So should patients at Imperial College Healthcare Trust be concerned that the trust has not mentioned in its latest published board papers a blunder that led to the Trust’s losing track, for nearly a year, of hundreds of patients with possible cancer?

The Department of Health requires that patients who go to their GP with symptoms that may indicate cancer are seen by a specialist within a maximum of two weeks.

Records incomplete

But Imperial has lost track of an unknown number of patients who went to their GPs with signs of possible cancer. It has been checking 900 hospital records which it found were incomplete.

For some of the patients the blunder won’t matter:  they will have been called by staff at GP practices, some of whom have systems that track patients under the two-week rule.

But some patients might have slipped through the net and not been alerted by Imperial to their urgent appointments. Imperial has no clear idea how many.

It has asked GP organisations for help in contacting patients, their carers or representatives, to‘ascertain whether the patient has received treatment or still requires treatment’”.

What detail has emerged on the problem has come not from Imperial but from NHS North West London which is a single management team that represents eight PCTs.  NWL  covers St Mary’s Hospital, Paddington, Hammersmith Hospital and Charing Cross Hospital, which are all managed by Imperial.

“Substantial concern”

NWL has what it calls “substantial concern” about the problems at Imperial. In addition to the problem reporting its two-week cancer waits, the Trust is trying to clear a backlog of patients who have waited more than 18 weeks from referral to consultant-led treatment.

“Systematic failings”

NWL executives report that Deloitte has carried out an external audit and “concerns remain about record keeping at Imperial”.  The executives say that “systematic failings” have been identified which will take time to resolve. This issue will be given close attention in the coming year, says NWL.

Patient safety an issue?

NWL also says that a “Clinical Review” is being carried out and a panel is being set up to look at the clinical issues that have arisen at Imperial. “The Director of Nursing confirmed that the clinical review would look at all patients affected by the problems at Imperial …”

In contrast to the concerns about Imperial’s performance among London PCTs, Imperial seems a little surprised that we are even investigating the problems.

“The problems are administrative and nothing to do with IT,” said a spokesperson.

The Trust is right. The problems are nothing to do with IT.  And yet the problems may be everything to do with IT. Appointments for patients with possible cancer have not been entered onto IT systems – and where they have, data has been incorrect, entered into duplicate records, or not followed up to check appointments were kept, or the patient seen for treatment and investigations.

Eye off the ball?

For nearly a year the problem was not spotted, which has left some North West London executives wondering how it could have happened. It is known the Trust has devoted time and attention of senior management to a replacement of existing systems with Cerner, under the National Programme for IT.  Has the Trust taken its eye off the ball while making plans for Cerner?

Some working in the NHS may ask whether it was more important for the Trust to have ensured that appointments for possible cancer were entered correctly onto existing systems, and routines written into software to provide alerts when cancer records were not closed off, or were incomplete.

**

Below are some of the comments of NWL PCTs about Imperial’s problems. Their concerns raise questions about whether the Trust’s processes and administration are stable enough for a transition from existing IT to new systems, which could cause further disruption.

These are some NWL statements in its board papers relating to Imperial:

“It was reported that at Imperial, the calculations of the backlog of referrals had been completed and work is underway to clear the backlog. However Deloitte has carried out an external audit and concerns remain about record keeping at Imperial. Systematic failings have been identified which will take time to resolve. This issue will be given close attention in the coming year.

“A Clinical Review is being carried out and a panel is being set up to look at the clinical issues that have arisen. The Director of Nursing confirmed that the clinical review would look at all patients affected by the problems at Imperial …”

Does NWL always trust what Imperial says?

Jeff Zitron [Chair, NHS NW London, Inner & Outer NWL Sub Clusters] said that the Board needs evidenced assurance that the issues that have arisen at Imperial and North West London Hospitals are being adequately addressed.

**

“Trish Longdon [Vice-chairman, NHS North West London Cluster Board] noted that although the Imperial targets were shown as ‘Green’  this does not reflect the true position. This was agreed and it was noted that they were in fact being treated as if they were Amber.”

“Urgent meeting”

“The Chairman asked for an update on the situation at Imperial College Healthcare Trust which had been the subject of substantial concern at the last INWL Inner North West London NHS] Board meeting. The INWL Board had agreed that an urgent meeting should be held with the Chairman and Chief Executive of Imperial, involving the CCG Chairs, the Tri-Borough Cabinet Members for Health, himself and Anne Rainsberry [Chief Executive North West London Cluster]. This was taking place later that day.”

Clinical harm?

“ Following investigation of Serious Incidents in May 2011, ICHT [Imperial College Healthcare NHS Trust] is unable to provide sufficient assurance of robust data quality in regard to reported performance for 18 weeks RTT [Referral To Treatment], cancer waiting times and the elective waiting list.

The Trust board have approved a reporting break until end of June 2012 which has been agreed by the Cluster in conjunction with NHS London. To ensure due diligence, an independent audit of waiting list management across all specialities has been undertaken and a set of recommendations made.

“ICHT continue to provide shadow reports to NHS NWL during this period with weekly reporting. Some evidence of improved performance management is observed. However this is not yet consistently embedded Trust- wide and clearance of the current backlog of patients is not at sufficient pace to meet the agreed trajectory…

“A clinical review will be undertaken to ensure that patients have not experienced harm due to an elongated wait.”

**

“Anne Rainsberry [Chief Executive North West London Cluster] referred to a range of discussions taking place on Imperial’s performance issues, focussing on the backlog of the Referral to Treatment waiting lists which had resulted in a reporting break being granted.

“Work was concluding at the end of April [2012] to reduce the original backlog of patient cases and enable reporting systems to get back on track in June. A clinical review had also started to determine if any risks to patients had arisen due to the delays. The review findings would be brought back to the Board…

“Anne Rainsberry referred to a meeting she had attended with the Department of Health to review Imperial‟s approach to resolving these issues.”

Big organisational challenge

“Simon Weldon [Director of Commissioning and Performance, North West London Cluster Board] … asked the NWL Board to be aware of the enormity of the organisational challenge facing Imperial and that remedial actions would take time to take effect.”

Imperial responds

Campaign4Change put it to Imperial College Healthcare NHS Trust that there is nothing in its latest published board papers to show the trust is concerned about the problems relating to cancer waits and lost appointments. We said that PCT papers referred to  “substantial concern” but there was nothing similar in Imperial’s latest published papers. We let Imperial know we would be asking the question: how concerned is Imperial about the confusion over cancer waits?

This was the reply of Imperial’s spokeswoman (in full)

“The safety of patients is our absolute priority. Our Trust is taking the issues involved in the current situation very seriously and at all times the well-being of the patients we serve is foremost in our minds.

“We acknowledge that some patients may have been caused additional pain and anxiety associated with a prolonged wait for diagnosis and treatment and worked to address the problem as robustly and quickly as possible.”

Separately, in May 2012, Imperial told us that it was in the process of validating 900 patient records that indicate that a patient might have been waiting longer than two weeks.

At that stage it had closed more than 400 of the 900 records “as the majority indicated that patients have either received or are receiving treatment, or that the patient did not attend their appointment and their GP had advised there was no need for further follow up”.

The spokeswoman said “To date our investigations have found no suggestion that any delay in treatment has caused a patient to come to serious harm.”

She said “This is not an IT issue, but an administrative issue related to the physical input and extraction of data from patient records. It is entirely unrelated to IT systems.”

Comment

It is extraordinary that Imperial is seeking to replace existing systems when it is organisationally in a questionable state. Simon Weldon, Director of Commissioning and Performance, North West London Cluster Board, referred to the “enormity of the organisational challenge facing Imperial”.

Under the NPfIT, a number of implementations of Cerner at several NHS sites have gone badly wrong – and they did not have Imperial’s problems before going live. It would be common sense for Imperial to get its data accurate and its management processes and checks reliably in place before attempting a major switch of IT systems.

Two other things are particularly worrying: Imperial appears not to concede in public it has any major problems, and it appears to separate IT from administration.

Having the best IT in the NHS is of limited value if important parts of the Trust are in a state of administrative disorder.  If data is unreliable, incomplete and inaccurate, and solid processes are not in place to ensure that the correct data is entered into systems when it needs to be entered, and routines are not in place to provide alerts and follow-ups, costly hardware and software may not compensate. Is this an IT issue or not? Does that matter?

We would not like to see a Cerner NPfIT debacle similar to the ones at Barts in London, Royal Free Hampstead, and at hospitals in Oxford, Milton Keynes, Weston-super-Mare, Morecambe Bay, Worthing and Bristol.

But is Imperial particularly concerned? Is it in denial over the seriousness of its problems? Why is it reporting its position at Green when North West London NHS regards its position as Amber? Why do its latest published board papers not mention its problems tracking patients under the two-week rule? Is the Trust so preoccupied with replacing its existing systems with Cerner that it is not doing the basics well?

One specialist in the NHS said: “If the Trust wasn’t spending so much time and effort doing the Cerner deployment then maybe they would have concentrated its scarce resources on performing the  job of managing patients.”

Accountability for failure in the NHS is poor to non-existent. So will Imperial be able to do what it wants regardless?

Troubled Cerner NPfIT go-lives, so far:

Barts and The London

Royal Free Hampstead

Weston Area Health Trust

Milton Keynes Hospital NHS Trust

Worthing and Southlands

Barnet and Chase Farm Hospitals NHS Trust

Nuffield Orthopaedic

North Bristol.

St George’s Healthcare NHS Trust

University Hospitals of Morecambe Bay NHS Foundation Trust

Birmingham Women’s Foundation Trust

NHS Bury

*We acknowledge Pulse which broke the story on Imperial’s cancer wait problems.

GPs asked to contact hundreds of patients who may have missed treatment after hospital’s cancer referrals blunder  – Pulse

London LMCs alert over Imperial cancer waits mix-up – Pulse.

GPs kept in the dark over hospital cancer blunder – Pulse

Other links:

Halt NPfIT Cerner deployments says MP Richard Bacon

Bacon calls for halt on Millennium.

Cerner questions hospital bid process

by Tony Collins

NHS software supplier Cerner has written to Cambridge University Hospitals Foundation Trust questioning a process to procure an electronic patient record system.

The Trust chose Epic and HP as preferred supplier for a common platform for the Cambridge trust and Papworth Hospital Foundation Trust.

Now Cerner, which bid for the contract, is asking for the process to be be re-run, says the Health Service Journal. The Trust told the Health Service Journal its procurement was open and fair.

The Health Service Journal said it had seen Cerner’s letter. It quoted the letter as saying that the Trust’s favouring of Epic was in clear breach of the ‘equal treatment’ principle.

The letter said that Cerner found it difficult not to conclude that the Trust had made a pre-determined decision to award the tender to Epic some time before it designed the procurement process. This gave other vendors no realistic possibility of winning, said the letter.

The trust said it was continuing to proceed with the procurement process for “eHospital”.

Cerner supplies the NHS with the Millennium software, either directly or through BT under the NPfIT.

Medical dictionary should help prevent medication mistakes

By Tony Collins

The Department of Health says that a medicines dictionary, which is approved today, will make medical errors less likely by ensuring all staff who work in the NHS and healthcare use the same terminology when referring to medicines.

The Information Standards Board for Health and Social Care has approved the NHS dictionary of medicines and devices – called “dm+d” –  as a standard which, says the Department of Health,  “must be used by all staff”.

The DH says that “all doctors, nurses and pharmacists should move towards using the common medicines dictionary so that information exchanged electronically is accurate and safe”.

Using a single drug terminology will “enable information about patients’ medicines to transfer more effectively between different healthcare settings, reducing the risk of medication mistakes caused by human error”.

The NHS dictionary of medicines and devices is already used in the UK for the exchange of clinical information, including the Electronic Prescription Service and for patients’ Summary Care Records.

Dr Charles Gutteridge, National Clinical Director for Informatics at the Department of Health and Medical Director, Barts and the London NHS Trust said

“The adoption of dm+d is an important milestone. It will mean clearer and consistent communication throughout the NHS ensuring health professionals in all care settings …. I encourage all clinicians to accelerate their use of this common medical dictionary for the benefit of the patients we care for.”

Heidi Wright, from the Royal Pharmaceutical Society (RPS) said “The Royal Pharmaceutical Society supports the need for a single terminology to facilitate interoperability and to enable such initiatives as the Electronic prescription Service (EPS). We believe that the opportunities created for using dm+d are substantial in terms of interoperability, opportunities for comparison and reducing variation, enhancing patient safety i.e. reducing risks associated with system interfaces and providing links to clinical systems such as the British National Formulary .”

The dictionary contains unique identifiers and associated textual descriptions for medicines and medical devices.  It was developed and delivered through a partnership between the Department of Health Informatics Directorate  and the NHS Business Services Authority.

The DH Information Strategy says that  reducing the number of inconsistent or incompatible terminologies will allow better integration between systems and across health and social care, and better information to support care and improvement of care.